18663 W HORACE ST 91326

Certificate Information: 18663 W HORACE ST 91326

Application / Permit
24010-20000-02237
Plan Check / Job No.
B24VN07366
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN NEW 22'-3" X 32'-2" DETACHED 2-STORY ACCESSORY DWELLING UNIT LAMC 12.22 A.33 (c)-(d). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 7/29/2025
Issuing Office
Current Status
CofO in Progress on 5/19/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 6/9/2024 APPLICANT
Assigned to Plan Check Engineer 6/13/2024 RAPHAEL ROSAS
Corrections Issued 6/18/2024 RAPHAEL ROSAS
Quality Review Completed 6/20/2024 STEVEN KIM
Applicant returned to address corrections 9/26/2024 RAPHAEL ROSAS
Applicant returned to address corrections 12/12/2024 RAPHAEL ROSAS
Applicant returned to address corrections 2/11/2025 RAPHAEL ROSAS
Applicant returned to address corrections 3/12/2025 RAPHAEL ROSAS
Applicant returned to address corrections 3/20/2025 RAPHAEL ROSAS
Plan Check Approved 4/10/2025 RAPHAEL ROSAS
Issued 7/29/2025 APPLICANT
CofO in Progress 5/19/2026 JACK KARGODORIAN

Permit Application Clearance Information

Address approval Cleared 7/18/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 7/18/2024 EDGAR ALCARAZ
Sewer availability Cleared 7/18/2024 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 7/24/2024 BIAINA HARITUNIAN

Contact Information

Contractor Owner-Builder       ,
Engineer Endrawes,, George; Lic. No.: C91685 1140 PORTOFINO CT 103      CORONA, CA 92881

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/26/2025 Partial Approval DAVID SCANTLIN
Excavation/Setback/Form/Re-Bar 10/22/2025 No Access for Inspection DAVID SCANTLIN
Excavation/Setback/Form/Re-Bar 10/27/2025 Approved KRISTEN CAUSEY
Footing/Foundation/Slab 11/7/2025 Not Ready for Inspection DAVID SCANTLIN
Footing/Foundation/Slab 1/27/2026 Approved DAVID SCANTLIN
ELECTRICAL-Rough 2/13/2026 Corrections Issued ROBERT GOLD
HVAC-Rough 2/13/2026 Corrections Issued ROBERT GOLD
PLUMBING-Rough 2/13/2026 Corrections Issued ROBERT GOLD
Wood Frame 2/13/2026 Corrections Issued ROBERT GOLD
BUILDING-Rough-Frame 2/20/2026 Not Ready for Inspection DAVID SCANTLIN
ELECTRICAL-Rough 2/20/2026 Approved DAVID SCANTLIN
Green Building Rough 2/20/2026 Not Ready for Inspection DAVID SCANTLIN
HVAC-Rough 2/20/2026 Approved DAVID SCANTLIN
PLUMBING-Rough 2/20/2026 Approved DAVID SCANTLIN
Verify Sprinkler Sign Off 2/20/2026 Not Ready for Inspection DAVID SCANTLIN
BUILDING-Rough-Frame 3/3/2026 Approved DAVID SCANTLIN
Green Building Rough 3/3/2026 Approved DAVID SCANTLIN
Interior/Exterior Lathing 3/3/2026 Partial Approval DAVID SCANTLIN
Verify Sprinkler Sign Off 3/3/2026 Approved DAVID SCANTLIN
Insulation 3/9/2026 Not Ready for Inspection DAVID SCANTLIN
Drywall Nailing 3/20/2026 Approved JACK KARGODORIAN
Interior/Exterior Lathing 3/27/2026 Approved DAVID SCANTLIN
Final 4/24/2026 Corrections Issued DAVID SCANTLIN
Green Building Final 4/24/2026 Not Ready for Inspection DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 4/24/2026 SGSOV Not Ready DAVID SCANTLIN
Service/Power Release 4/24/2026 Not Ready for Inspection DAVID SCANTLIN
Smoke Detectors 4/24/2026 Approved DAVID SCANTLIN
Final 5/5/2026 Not Ready for Inspection DAVID SCANTLIN
Green Building Final 5/5/2026 Approved DAVID SCANTLIN
SGSOV-Seismic Gas S/O Valve 5/5/2026 SGSOV Not Ready DAVID SCANTLIN
Service/Power Release 5/5/2026 Not Ready for Inspection DAVID SCANTLIN
Final 5/18/2026 OK to Issue CofO JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 5/18/2026 SGSOV Approved JACK KARGODORIAN
Service/Power Release 5/18/2026 Approved JACK KARGODORIAN