18663 W HORACE ST 91326
Certificate Information: 18663 W HORACE ST 91326
- Application / Permit
- 24010-20000-02237
- Plan Check / Job No.
- B24VN07366
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN NEW 22'-3" X 32'-2" DETACHED 2-STORY ACCESSORY DWELLING UNIT LAMC 12.22 A.33 (c)-(d). ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 7/29/2025
- Issuing Office
- Current Status
- CofO in Progress on 5/19/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 6/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/13/2024 | RAPHAEL ROSAS |
| Corrections Issued | 6/18/2024 | RAPHAEL ROSAS |
| Quality Review Completed | 6/20/2024 | STEVEN KIM |
| Applicant returned to address corrections | 9/26/2024 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 12/12/2024 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 2/11/2025 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 3/12/2025 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 3/20/2025 | RAPHAEL ROSAS |
| Plan Check Approved | 4/10/2025 | RAPHAEL ROSAS |
| Issued | 7/29/2025 | APPLICANT |
| CofO in Progress | 5/19/2026 | JACK KARGODORIAN |
Permit Application Clearance Information
| Address approval | Cleared | 7/18/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/18/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 7/18/2024 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 7/24/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Endrawes,, George; Lic. No.: C91685 | 1140 PORTOFINO CT 103 CORONA, CA 92881 |
Inspector Information
| JACK KARGODORIAN, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
| KRISTEN CAUSEY, (818) 774-4319 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 8/26/2025 | Partial Approval | DAVID SCANTLIN |
| Excavation/Setback/Form/Re-Bar | 10/22/2025 | No Access for Inspection | DAVID SCANTLIN |
| Excavation/Setback/Form/Re-Bar | 10/27/2025 | Approved | KRISTEN CAUSEY |
| Footing/Foundation/Slab | 11/7/2025 | Not Ready for Inspection | DAVID SCANTLIN |
| Footing/Foundation/Slab | 1/27/2026 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Rough | 2/13/2026 | Corrections Issued | ROBERT GOLD |
| HVAC-Rough | 2/13/2026 | Corrections Issued | ROBERT GOLD |
| PLUMBING-Rough | 2/13/2026 | Corrections Issued | ROBERT GOLD |
| Wood Frame | 2/13/2026 | Corrections Issued | ROBERT GOLD |
| BUILDING-Rough-Frame | 2/20/2026 | Not Ready for Inspection | DAVID SCANTLIN |
| ELECTRICAL-Rough | 2/20/2026 | Approved | DAVID SCANTLIN |
| Green Building Rough | 2/20/2026 | Not Ready for Inspection | DAVID SCANTLIN |
| HVAC-Rough | 2/20/2026 | Approved | DAVID SCANTLIN |
| PLUMBING-Rough | 2/20/2026 | Approved | DAVID SCANTLIN |
| Verify Sprinkler Sign Off | 2/20/2026 | Not Ready for Inspection | DAVID SCANTLIN |
| BUILDING-Rough-Frame | 3/3/2026 | Approved | DAVID SCANTLIN |
| Green Building Rough | 3/3/2026 | Approved | DAVID SCANTLIN |
| Interior/Exterior Lathing | 3/3/2026 | Partial Approval | DAVID SCANTLIN |
| Verify Sprinkler Sign Off | 3/3/2026 | Approved | DAVID SCANTLIN |
| Insulation | 3/9/2026 | Not Ready for Inspection | DAVID SCANTLIN |
| Drywall Nailing | 3/20/2026 | Approved | JACK KARGODORIAN |
| Interior/Exterior Lathing | 3/27/2026 | Approved | DAVID SCANTLIN |
| Final | 4/24/2026 | Corrections Issued | DAVID SCANTLIN |
| Green Building Final | 4/24/2026 | Not Ready for Inspection | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 4/24/2026 | SGSOV Not Ready | DAVID SCANTLIN |
| Service/Power Release | 4/24/2026 | Not Ready for Inspection | DAVID SCANTLIN |
| Smoke Detectors | 4/24/2026 | Approved | DAVID SCANTLIN |
| Final | 5/5/2026 | Not Ready for Inspection | DAVID SCANTLIN |
| Green Building Final | 5/5/2026 | Approved | DAVID SCANTLIN |
| SGSOV-Seismic Gas S/O Valve | 5/5/2026 | SGSOV Not Ready | DAVID SCANTLIN |
| Service/Power Release | 5/5/2026 | Not Ready for Inspection | DAVID SCANTLIN |
| Final | 5/18/2026 | OK to Issue CofO | JACK KARGODORIAN |
| SGSOV-Seismic Gas S/O Valve | 5/18/2026 | SGSOV Approved | JACK KARGODORIAN |
| Service/Power Release | 5/18/2026 | Approved | JACK KARGODORIAN |