23245 W OSTRONIC DR 91367
Certificate Information: 23245 W OSTRONIC DR 91367
- Application / Permit
- 24010-20000-02221
- Plan Check / Job No.
- B24VN07315
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- NEW 49'1/2"X20'2-1/4" 1-STORY ACCESSORY LIVING QUARTERS. (NFPA 13 R FIRE SPRINKLERS REQUIRED THROUGHOUT) {ALL ELECTRIC BUILDING} [2 OF 3]
- Permit Issued
- Issued on 11/25/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/11/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/23/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/30/2024 | MARVEL DELACRUZ |
| Corrections Issued | 6/13/2024 | MARVEL DELACRUZ |
| Quality Review Completed | 6/13/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 6/14/2024 | APPLICANT |
| Applicant returned to address corrections | 8/30/2024 | MARVEL DELACRUZ |
| Plan Check Approved | 9/5/2024 | MARVEL DELACRUZ |
| Issued | 11/25/2024 | APPLICANT |
| CofO in Progress | 2/25/2026 | GEVORK IPCHYAN |
| Permit Finaled | 4/11/2026 | MICHAEL PELHAM |
| CofO Issued | 4/11/2026 | MICHAEL PELHAM |
| Permit Finaled | 4/11/2026 | MICHAEL PELHAM |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 6/13/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 6/13/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/14/2024 | BIAINA HARITUNIAN |
| Hydrant and Access approval | Cleared | 8/26/2024 | JOHN CONNEALLY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 1/14/2025 | Corrections Issued | GEVORK IPCHYAN |
| Footing/Foundation/Slab | 1/31/2025 | Approved | GEVORK IPCHYAN |
| PLUMBING-Rough | 1/31/2025 | Partial Approval | GEVORK IPCHYAN |
| Deputy Shotcrete | 2/3/2025 | Conditional Approval | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 2/18/2025 | Partial Approval | TROY SANDERS |
| PLUMBING-Rough | 3/11/2025 | Approved | GEVORK IPCHYAN |
| Shower Pan | 3/27/2025 | Approved | GEVORK IPCHYAN |
| HVAC-Rough | 4/14/2025 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Rough | 4/21/2025 | Approved | GEVORK IPCHYAN |
| BUILDING-Rough-Frame | 4/28/2025 | Approved | GEVORK IPCHYAN |
| Green Building Rough | 4/28/2025 | Approved | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 4/28/2025 | Partial Approval | GEVORK IPCHYAN |
| MERV13>=Rough | 4/28/2025 | Approved | GEVORK IPCHYAN |
| Verify Sprinkler Sign Off | 4/28/2025 | Approved | GEVORK IPCHYAN |
| Interior/Exterior Lathing | 5/5/2025 | Partial Approval | TROY SANDERS |
| Drywall Nailing | 6/6/2025 | Approved | JEFFREY HARTLINE |
| ELECTRICAL-Final | 12/29/2025 | Not Ready for Inspection | GEVORK IPCHYAN |
| PLUMBING-Final | 12/29/2025 | Approved | GEVORK IPCHYAN |
| HVAC-Final | 1/9/2026 | Partial Approval | GEVORK IPCHYAN |
| ELECTRICAL-Final | 1/12/2026 | Not Ready for Inspection | GEVORK IPCHYAN |
| ELECTRICAL-Final | 1/21/2026 | Approved | GEVORK IPCHYAN |
| Final | 2/24/2026 | OK to Issue CofO | GEVORK IPCHYAN |
| Green Building Final | 2/24/2026 | Approved | GEVORK IPCHYAN |
| HVAC-Final | 2/24/2026 | Approved | GEVORK IPCHYAN |
| MERV13>=Final | 2/24/2026 | Approved | GEVORK IPCHYAN |
| SGSOV-Seismic Gas S/O Valve | 2/24/2026 | SGSOV Approved | GEVORK IPCHYAN |
| Service/Power Release | 2/24/2026 | Approved | GEVORK IPCHYAN |
| Smoke Detectors | 2/24/2026 | Approved | GEVORK IPCHYAN |