23245 W OSTRONIC DR 91367

Certificate Information: 23245 W OSTRONIC DR 91367

Application / Permit
24010-20000-02220
Plan Check / Job No.
B24VN07315
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
MAJOR REMODEL & ADDITION TO MAKE AN IRREGULAR SHAPED 2-STORY 99'1/2"X82'1/2" SINGLE FAMILY DWELLING WITH AN ATTACHED GARAGE AND TRELLISES. (NFPA 13 R FIRE SPRINKLERS REQUIRED) [1 OF 3]
Permit Issued
Issued on 11/25/2024
Issuing Office
Valley
Current Status
CofO Issued on 4/11/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/23/2024 APPLICANT
Assigned to Plan Check Engineer 5/30/2024 MARVEL DELACRUZ
Corrections Issued 6/13/2024 MARVEL DELACRUZ
Quality Review Completed 6/13/2024 OMID HEDAYAT
Building Plans Picked Up 6/14/2024 APPLICANT
Applicant returned to address corrections 8/30/2024 MARVEL DELACRUZ
Plan Check Approved 9/5/2024 MARVEL DELACRUZ
Issued 11/25/2024 APPLICANT
CofO in Progress 3/11/2026 GEVORK IPCHYAN
Permit Finaled 4/11/2026 MICHAEL PELHAM
CofO Issued 4/11/2026 MICHAEL PELHAM
Permit Finaled 4/11/2026 MICHAEL PELHAM

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 6/13/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 6/14/2024 BIAINA HARITUNIAN
Sewer availability Cleared 6/14/2024 BIAINA HARITUNIAN
Trees in Parkway Cleared 7/8/2024 ADALBERTO VERA
Permit Cleared 7/30/2024 BIAINA HARITUNIAN
Hydrant and Access approval Cleared 8/17/2024 JOHN CONNEALLY

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 1/14/2025 Corrections Issued GEVORK IPCHYAN
Footing/Foundation/Slab 1/31/2025 Approved GEVORK IPCHYAN
PLUMBING-Rough 1/31/2025 Partial Approval GEVORK IPCHYAN
Deputy Reinf. Concrete 2/3/2025 Conditional Approval HENRY KIM
Floor/Roof Diaphrgm/Shear Wall 2/18/2025 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 2/28/2025 Partial Approval GEVORK IPCHYAN
PLUMBING-Rough 3/11/2025 Approved GEVORK IPCHYAN
Shower Pan 3/27/2025 Approved GEVORK IPCHYAN
HVAC-Rough 4/14/2025 Approved JEFFREY HARTLINE
ELECTRICAL-Rough 4/21/2025 Approved GEVORK IPCHYAN
BUILDING-Rough-Frame 4/28/2025 Approved GEVORK IPCHYAN
Green Building Rough 4/28/2025 Approved GEVORK IPCHYAN
Interior/Exterior Lathing 4/28/2025 Partial Approval GEVORK IPCHYAN
MERV13>=Rough 4/28/2025 Approved GEVORK IPCHYAN
Interior/Exterior Lathing 5/5/2025 Partial Approval TROY SANDERS
Drywall Nailing 6/6/2025 Approved JEFFREY HARTLINE
ELECTRICAL-Final 12/29/2025 Not Ready for Inspection GEVORK IPCHYAN
PLUMBING-Final 12/29/2025 Approved GEVORK IPCHYAN
HVAC-Final 1/9/2026 Partial Approval GEVORK IPCHYAN
ELECTRICAL-Final 1/12/2026 Corrections Issued GEVORK IPCHYAN
ELECTRICAL-Final 1/21/2026 Approved GEVORK IPCHYAN
Service/Power Release 1/21/2026 Approved GEVORK IPCHYAN
Final 2/24/2026 Not Ready for Inspection GEVORK IPCHYAN
Green Building Final 2/24/2026 Approved GEVORK IPCHYAN
HVAC-Final 2/24/2026 Approved GEVORK IPCHYAN
MERV13>=Final 2/24/2026 Approved GEVORK IPCHYAN
SGSOV-Seismic Gas S/O Valve 2/24/2026 SGSOV Approved GEVORK IPCHYAN
Smoke Detectors 2/24/2026 Approved GEVORK IPCHYAN
Final 3/10/2026 OK to Issue CofO GEVORK IPCHYAN