9216 N SHOSHONE AVE 91316

Certificate Information: 9216 N SHOSHONE AVE 91316

Application / Permit
24010-20000-02203
Plan Check / Job No.
B24VN07249
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: (N) DETACHED 1,200 SQFT ADU PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENG.
Permit Issued
Issued on 5/1/2025
Issuing Office
Current Status
CofO in Progress on 5/29/2026
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/28/2024 APPLICANT
Assigned to Plan Check Engineer 5/31/2024 LUISANGEL VALENZUELA
Corrections Issued 6/1/2024 LUISANGEL VALENZUELA
Applicant returned to address corrections 8/16/2024 LUISANGEL VALENZUELA
Applicant returned to address corrections 11/13/2024 LUISANGEL VALENZUELA
Applicant returned to address corrections 3/6/2025 LUISANGEL VALENZUELA
Applicant returned to address corrections 3/25/2025 LUISANGEL VALENZUELA
Plan Check Approved 4/7/2025 LUISANGEL VALENZUELA
No Progress 4/8/2025 LUISANGEL VALENZUELA
Plan Check Approved 4/8/2025 LUISANGEL VALENZUELA
No Progress 4/21/2025 LUISANGEL VALENZUELA
Plan Check Approved 4/21/2025 LUISANGEL VALENZUELA
Issued 5/1/2025 APPLICANT
CofO in Progress 5/29/2026 CHRISTOPHER ROJAS

Permit Application Clearance Information

Address approval Cleared 6/11/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 6/11/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/12/2024 CARLOS AGUILERA
Sewer availability Cleared 6/12/2024 CARLOS AGUILERA
Hydrant and Access approval Cleared 10/25/2024 LAVEON RIDER

Contact Information

Contractor Owner-Builder       ,
Engineer Zelada,, Mynor Anibal; Lic. No.: C48666 22634 SYLVAN ST      WOODLAND HILLS, CA 91367

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/11/2025 Approved NICHOLAS TROWBRIDGE
PLUMBING-Rough 7/25/2025 Approved NICHOLAS TROWBRIDGE
Excavation/Setback/Form/Re-Bar 8/1/2025 Corrections Issued CHRISTOPHER ROJAS
Footing/Foundation/Slab 8/1/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Footing/Foundation/Slab 8/7/2025 Not Ready for Inspection JOSE AVILA
Footing/Foundation/Slab 8/12/2025 Approved CHRISTOPHER ROJAS
Deputy Wood Construction 9/2/2025 Conditional Approval JUAN VALENZUELA
Wood Frame 9/5/2025 Corrections Issued NICHOLAS TROWBRIDGE
Floor/Roof Diaphrgm/Shear Wall 9/10/2025 Approved NICHOLAS TROWBRIDGE
Special/Order Compliance 9/10/2025 Corrections Issued NICHOLAS TROWBRIDGE
ELECTRICAL-Rough 9/11/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
ELECTRICAL-Rough 9/12/2025 Corrections Issued NICHOLAS TROWBRIDGE
HVAC-Rough 9/12/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
PLUMBING-Rough 9/12/2025 Corrections Issued NICHOLAS TROWBRIDGE
Sewer 9/12/2025 Partial Approval NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 10/3/2025 Approved NICHOLAS TROWBRIDGE
ELECTRICAL-Rough 10/3/2025 Approved NICHOLAS TROWBRIDGE
HVAC-Rough 10/3/2025 Approved NICHOLAS TROWBRIDGE
PLUMBING-Rough 10/3/2025 Approved NICHOLAS TROWBRIDGE
Sewer 10/3/2025 Approved NICHOLAS TROWBRIDGE
Verify Sprinkler Sign Off 10/3/2025 Approved NICHOLAS TROWBRIDGE
Insulation 10/8/2025 Corrections Issued NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 10/8/2025 Partial Approval NICHOLAS TROWBRIDGE
Insulation 10/10/2025 Approved NICHOLAS TROWBRIDGE
Drywall Nailing 10/17/2025 Approved NICHOLAS TROWBRIDGE
Interior/Exterior Lathing 10/20/2025 Approved LOUIS ESCOTO
Pre-Inspection 11/26/2025 Approved KEVIN BERBERYAN
ELECTRICAL-Final 3/13/2026 Corrections Issued CHRISTOPHER ROJAS
Final 3/13/2026 Corrections Issued CHRISTOPHER ROJAS
HVAC-Final 3/13/2026 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Final 3/13/2026 Corrections Issued CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 3/13/2026 SGSOV Not Required CHRISTOPHER ROJAS
Smoke Detectors 3/13/2026 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 4/3/2026 Not Ready for Inspection CHRISTOPHER ROJAS
Final 4/3/2026 Corrections Issued CHRISTOPHER ROJAS
HVAC-Final 4/3/2026 Not Ready for Inspection CHRISTOPHER ROJAS
PLUMBING-Final 4/3/2026 Not Ready for Inspection CHRISTOPHER ROJAS
Service/Power Release 4/3/2026 Not Ready for Inspection CHRISTOPHER ROJAS
Pre-Inspection 5/7/2026 Approved CHRISTOPHER ROJAS
Final 5/15/2026 Corrections Issued KEVIN BERBERYAN
Service/Power Release 5/15/2026 Not Ready for Inspection KEVIN BERBERYAN
Special/Order Compliance 5/22/2026 Approved JOSE AVILA
Final 5/29/2026 OK to Issue CofO CHRISTOPHER ROJAS
Service/Power Release 5/29/2026 Approved CHRISTOPHER ROJAS