9216 N SHOSHONE AVE 91316
Certificate Information: 9216 N SHOSHONE AVE 91316
- Application / Permit
- 24010-20000-02203
- Plan Check / Job No.
- B24VN07249
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: (N) DETACHED 1,200 SQFT ADU PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENG.
- Permit Issued
- Issued on 5/1/2025
- Issuing Office
- Current Status
- CofO in Progress on 5/29/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/28/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/31/2024 | LUISANGEL VALENZUELA |
| Corrections Issued | 6/1/2024 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 8/16/2024 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 11/13/2024 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 3/6/2025 | LUISANGEL VALENZUELA |
| Applicant returned to address corrections | 3/25/2025 | LUISANGEL VALENZUELA |
| Plan Check Approved | 4/7/2025 | LUISANGEL VALENZUELA |
| No Progress | 4/8/2025 | LUISANGEL VALENZUELA |
| Plan Check Approved | 4/8/2025 | LUISANGEL VALENZUELA |
| No Progress | 4/21/2025 | LUISANGEL VALENZUELA |
| Plan Check Approved | 4/21/2025 | LUISANGEL VALENZUELA |
| Issued | 5/1/2025 | APPLICANT |
| CofO in Progress | 5/29/2026 | CHRISTOPHER ROJAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/11/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 6/11/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 6/12/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 6/12/2024 | CARLOS AGUILERA |
| Hydrant and Access approval | Cleared | 10/25/2024 | LAVEON RIDER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zelada,, Mynor Anibal; Lic. No.: C48666 | 22634 SYLVAN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/11/2025 | Approved | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 7/25/2025 | Approved | NICHOLAS TROWBRIDGE |
| Excavation/Setback/Form/Re-Bar | 8/1/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 8/1/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Footing/Foundation/Slab | 8/7/2025 | Not Ready for Inspection | JOSE AVILA |
| Footing/Foundation/Slab | 8/12/2025 | Approved | CHRISTOPHER ROJAS |
| Deputy Wood Construction | 9/2/2025 | Conditional Approval | JUAN VALENZUELA |
| Wood Frame | 9/5/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2025 | Approved | NICHOLAS TROWBRIDGE |
| Special/Order Compliance | 9/10/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Rough | 9/11/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Rough | 9/12/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| HVAC-Rough | 9/12/2025 | Not Ready for Inspection | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 9/12/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Sewer | 9/12/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 10/3/2025 | Approved | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Rough | 10/3/2025 | Approved | NICHOLAS TROWBRIDGE |
| HVAC-Rough | 10/3/2025 | Approved | NICHOLAS TROWBRIDGE |
| PLUMBING-Rough | 10/3/2025 | Approved | NICHOLAS TROWBRIDGE |
| Sewer | 10/3/2025 | Approved | NICHOLAS TROWBRIDGE |
| Verify Sprinkler Sign Off | 10/3/2025 | Approved | NICHOLAS TROWBRIDGE |
| Insulation | 10/8/2025 | Corrections Issued | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 10/8/2025 | Partial Approval | NICHOLAS TROWBRIDGE |
| Insulation | 10/10/2025 | Approved | NICHOLAS TROWBRIDGE |
| Drywall Nailing | 10/17/2025 | Approved | NICHOLAS TROWBRIDGE |
| Interior/Exterior Lathing | 10/20/2025 | Approved | LOUIS ESCOTO |
| Pre-Inspection | 11/26/2025 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Final | 3/13/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 3/13/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| HVAC-Final | 3/13/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Final | 3/13/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 3/13/2026 | SGSOV Not Required | CHRISTOPHER ROJAS |
| Smoke Detectors | 3/13/2026 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 4/3/2026 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 4/3/2026 | Corrections Issued | CHRISTOPHER ROJAS |
| HVAC-Final | 4/3/2026 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| PLUMBING-Final | 4/3/2026 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Service/Power Release | 4/3/2026 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Pre-Inspection | 5/7/2026 | Approved | CHRISTOPHER ROJAS |
| Final | 5/15/2026 | Corrections Issued | KEVIN BERBERYAN |
| Service/Power Release | 5/15/2026 | Not Ready for Inspection | KEVIN BERBERYAN |
| Special/Order Compliance | 5/22/2026 | Approved | JOSE AVILA |
| Final | 5/29/2026 | OK to Issue CofO | CHRISTOPHER ROJAS |
| Service/Power Release | 5/29/2026 | Approved | CHRISTOPHER ROJAS |