6647 N ETHEL AVE 91606

Certificate Information: 6647 N ETHEL AVE 91606

Application / Permit
24010-20000-02170
Plan Check / Job No.
B24VN07156
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: (N) 1-STORY ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 8/2/2024
Issuing Office
Current Status
CofO Issued on 5/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/21/2024 APPLICANT
Assigned to Plan Check Engineer 5/23/2024 DANIEL YIP
Corrections Issued 5/26/2024 DANIEL YIP
Quality Review Completed 5/29/2024 GARO TELMI
Applicant returned to address corrections 7/30/2024 DANIEL YIP
Plan Check Approved 8/2/2024 DANIEL YIP
Issued 8/2/2024 APPLICANT
CofO in Progress 5/4/2025 OGANES TARAKHCHYAN
Permit Finaled 5/15/2025 RUBEN SALAS
Permit Finaled 5/15/2025 RUBEN SALAS
CofO Issued 5/15/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/28/2024 CARLOS RAMIREZ
Roof/Waste drainage to street Cleared 5/28/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 5/30/2024 CARLOS RAMIREZ
Sewer availability Cleared 5/30/2024 CARLOS RAMIREZ

Contact Information

Contractor Advanced Builders And Contractors; Lic. No.: 900281-B       ,
Contractor Let'S Build It Inc; Lic. No.: 900281-B       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/3/2024 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 9/10/2024 Not Ready for Inspection DAVID MATSON
Footing/Foundation/Slab 9/12/2024 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 9/26/2024 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 9/30/2024 Approved OGANES TARAKHCHYAN
BUILDING-Rough-Frame 10/23/2024 Not Ready for Inspection GAREN HAYRAPETYAN
Green Building Rough 10/23/2024 Not Ready for Inspection GAREN HAYRAPETYAN
Rough-Elec/Plmb/HVAC 10/23/2024 Corrections Issued GAREN HAYRAPETYAN
Verify Sprinkler Sign Off 10/23/2024 Approved GAREN HAYRAPETYAN
ELECTRICAL-Rough 10/28/2024 Approved OGANES TARAKHCHYAN
HVAC-Rough 10/28/2024 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 10/28/2024 Not Ready for Inspection OGANES TARAKHCHYAN
ELECTRICAL-Rough 11/1/2024 Approved OGANES TARAKHCHYAN
HVAC-Rough 11/1/2024 Approved OGANES TARAKHCHYAN
PLUMBING-Rough 11/1/2024 Approved OGANES TARAKHCHYAN
Underground Mechanical 11/4/2024 Approved OGANES TARAKHCHYAN
Wood Frame 11/6/2024 Not Ready for Inspection OGANES TARAKHCHYAN
BUILDING-Rough-Frame 11/13/2024 Partial Approval OGANES TARAKHCHYAN
Green Building Rough 11/13/2024 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 11/13/2024 Partial Approval OGANES TARAKHCHYAN
Insulation 11/20/2024 Approved OGANES TARAKHCHYAN
Shower Pan 11/20/2024 Approved OGANES TARAKHCHYAN
Drywall Nailing 12/4/2024 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 12/4/2024 Approved GAREN HAYRAPETYAN
Pre-Inspection 4/17/2025 Not Ready for Inspection OGANES TARAKHCHYAN
BUILDING-Rough-Frame 4/22/2025 Approved OGANES TARAKHCHYAN
Final 4/22/2025 Not Ready for Inspection OGANES TARAKHCHYAN
Green Building Final 4/22/2025 Approved OGANES TARAKHCHYAN
Service/Power Release 4/22/2025 Approved OGANES TARAKHCHYAN
Smoke Detectors 4/22/2025 Approved OGANES TARAKHCHYAN
Final 5/1/2025 OK to Issue CofO OGANES TARAKHCHYAN