10309 N NEWHOME AVE 91040
Certificate Information: 10309 N NEWHOME AVE 91040
- Application / Permit
- 24010-20000-02151
- Plan Check / Job No.
- B24VN07132
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: New 1- Story (22'-2" x 21'-6") Accessory Dwelling Unit per CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33 (c)-(d), (g). NFPA 13D Fire Sprinklers Throughout.
- Permit Issued
- Issued on 11/10/2024
- Issuing Office
- Current Status
- CofO Issued on 4/21/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/28/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/13/2024 | VAHAN JIVALAGIAN |
| Corrections Issued | 6/18/2024 | VAHAN JIVALAGIAN |
| Quality Review Completed | 6/25/2024 | OMID HEDAYAT |
| Applicant returned to address corrections | 7/23/2024 | VAHAN JIVALAGIAN |
| Applicant returned to address corrections | 8/9/2024 | VAHAN JIVALAGIAN |
| Applicant returned to address corrections | 8/12/2024 | VAHAN JIVALAGIAN |
| Plan Check Approved | 11/7/2024 | VAHAN JIVALAGIAN |
| Issued | 11/10/2024 | APPLICANT |
| CofO in Progress | 3/6/2026 | DAVID ANDERSON |
| CofO Issued | 4/21/2026 | RUBEN SALAS |
| Permit Finaled | 4/21/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/29/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 7/29/2024 | BIAINA HARITUNIAN |
| Street Frontage | Cleared | 7/29/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 7/31/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 7/31/2024 | BIAINA HARITUNIAN |
| GPI Written Notices | Cleared | 8/14/2024 | VAHAN JIVALAGIAN |
| Grading Pre-Inspection | Cleared | 8/14/2024 | VAHAN JIVALAGIAN |
| Hydrant and Access approval | Cleared | 10/30/2024 | PATRICK PEREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Medina,, Ferdinand Casaclang; Lic. No.: C88007 | 1051 S HOLT AVE APT F LOS ANGELES, CA 90035 |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/26/2025 | Corrections Issued | DAVID ANDERSON |
| Footing/Foundation/Slab | 3/5/2025 | Approved | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2025 | Partial Approval | DAVID ANDERSON |
| Special/Order Compliance | 4/24/2025 | Corrections Issued | DAVID ANDERSON |
| Deputy Wood Construction | 5/9/2025 | Conditional Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2025 | Approved | DAVID ANDERSON |
| Sewer | 6/3/2025 | Approved | DAVID ANDERSON |
| Underground Mechanical | 6/3/2025 | Partial Approval | DAVID ANDERSON |
| ELECTRICAL-Rough | 6/12/2025 | Corrections Issued | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2025 | Approved | DAVID ANDERSON |
| Green Building Rough | 6/12/2025 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 6/12/2025 | Corrections Issued | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 6/12/2025 | Approved | DAVID ANDERSON |
| ELECTRICAL-Rough | 6/17/2025 | Approved | KEVIN BERBERYAN |
| HVAC-Rough | 6/17/2025 | Corrections Issued | KEVIN BERBERYAN |
| PLUMBING-Rough | 6/17/2025 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 7/7/2025 | Approved | DAVID ANDERSON |
| HVAC-Rough | 7/7/2025 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 7/7/2025 | Partial Approval | DAVID ANDERSON |
| Insulation | 7/11/2025 | Approved | DAVID ANDERSON |
| Shower Pan | 7/11/2025 | Approved | DAVID ANDERSON |
| Drywall Nailing | 7/23/2025 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 7/23/2025 | Approved | WILLIAM WREN |
| Final | 2/19/2026 | Corrections Issued | DAVID ANDERSON |
| Green Building Final | 2/19/2026 | Not Ready for Inspection | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 2/19/2026 | SGSOV Not Required | DAVID ANDERSON |
| Service/Power Release | 2/19/2026 | Not Ready for Inspection | DAVID ANDERSON |
| Smoke Detectors | 2/19/2026 | Approved | DAVID ANDERSON |
| Final | 2/27/2026 | OK to Issue CofO | DAVID ANDERSON |
| Green Building Final | 2/27/2026 | Approved | DAVID ANDERSON |
| Service/Power Release | 2/27/2026 | Approved | DAVID ANDERSON |