14663 W CHATSWORTH DR 91345
Certificate Information: 14663 W CHATSWORTH DR 91345
- Application / Permit
- 24010-20000-02150
- Plan Check / Job No.
- B24VN07130
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 2-story Accessory Dwelling Unit (30' x 21') per LAMC 12.22 A.33 (c) - (d)
- Permit Issued
- Issued on 7/1/2024
- Issuing Office
- Valley
- Current Status
- Issued on 7/1/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/21/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/30/2024 | VAHAN JIVALAGIAN |
| Corrections Issued | 6/4/2024 | VAHAN JIVALAGIAN |
| Quality Review Completed | 6/6/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 6/10/2024 | APPLICANT |
| Plan Check Approved | 7/1/2024 | VAHAN JIVALAGIAN |
| Issued | 7/1/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 6/15/2024 | MARKOS PEREZ-BRAN |
| Roof/Waste drainage to street | Cleared | 6/15/2024 | MARKOS PEREZ-BRAN |
| Sewer availability | Cleared | 6/18/2024 | MARKOS PEREZ-BRAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/24/2024 | MARKOS PEREZ-BRAN |
Contact Information
| Contractor | Valenzuela Pancho Construction; Lic. No.: 1067736-B | 544 ORANGE GROVE AVE SAN FERNANDO, CA 91340 |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 6047 TAMPA AVE SUITE 304 TARZANA, CA 91356 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/30/2024 | Partial Approval | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 8/8/2024 | Approved | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 8/22/2024 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2024 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 8/28/2024 | Partial Approval | JACK KARGODORIAN |
| PLUMBING-Rough | 8/28/2024 | Approved | JACK KARGODORIAN |
| BUILDING-Rough-Frame | 9/3/2024 | Approved | RYAN SALAZAR |
| ELECTRICAL-Rough | 9/3/2024 | Approved | RYAN SALAZAR |
| Green Building Rough | 9/3/2024 | Approved | RYAN SALAZAR |
| HVAC-Rough | 9/3/2024 | Approved | RYAN SALAZAR |
| MERV13>=Rough | 9/3/2024 | Approved | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 9/3/2024 | Approved | RYAN SALAZAR |
| Insulation | 9/5/2024 | Approved | LOUIS ESCOTO |
| Drywall Nailing | 9/9/2024 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 9/17/2024 | Approved | JENNIFER RABUCHIN |
| Sewer | 1/9/2025 | Approved | JENNIFER RABUCHIN |
| Underground Mechanical | 1/9/2025 | Partial Approval | JENNIFER RABUCHIN |
| Final | 3/4/2025 | Corrections Issued | JUAN VALENZUELA |
| Green Building Final | 3/4/2025 | Approved | JUAN VALENZUELA |
| MERV13>=Final | 3/4/2025 | Not Ready for Inspection | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 3/4/2025 | SGSOV Not Required | JUAN VALENZUELA |
| Service/Power Release | 3/4/2025 | Not Ready for Inspection | JUAN VALENZUELA |
| Smoke Detectors | 3/4/2025 | Corrections Issued | JUAN VALENZUELA |
| Final | 3/11/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| MERV13>=Final | 3/11/2025 | Approved | KEVIN BERBERYAN |
| Service/Power Release | 3/11/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Smoke Detectors | 3/11/2025 | Not Ready for Inspection | KEVIN BERBERYAN |
| Final | 3/17/2025 | Not Ready for Inspection | JENNIFER RABUCHIN |
| HVAC-Final | 3/17/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 3/17/2025 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 3/17/2025 | Corrections Issued | JENNIFER RABUCHIN |
| Smoke Detectors | 3/17/2025 | Approved | JENNIFER RABUCHIN |