19710 W LANARK ST 91306
Certificate Information: 19710 W LANARK ST 91306
- Application / Permit
- 24010-20000-02132
- Plan Check / Job No.
- B24VN07077
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: NEW DETACHED 648 SF ACCESSORY DWELLING UNIT (ADU) PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g).
- Permit Issued
- Issued on 7/24/2024
- Issuing Office
- Current Status
- CofO Issued on 8/26/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/20/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/24/2024 | LUISANGEL VALENZUELA |
| Corrections Issued | 5/25/2024 | LUISANGEL VALENZUELA |
| Plan Check Approved | 6/2/2024 | LUISANGEL VALENZUELA |
| Issued | 7/24/2024 | APPLICANT |
| CofO in Progress | 8/5/2025 | ALEXANDER HANDY |
| Permit Finaled | 8/26/2025 | JOHN JANSON |
| Permit Finaled | 8/26/2025 | JOHN JANSON |
| CofO Issued | 8/26/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 5/29/2024 | CARLOS RAMIREZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/29/2024 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 5/29/2024 | CARLOS RAMIREZ |
| Sewer availability | Cleared | 5/29/2024 | EDGAR ALCARAZ |
Contact Information
| Architect | Dembsky,, Amit; Lic. No.: NA30383 | , |
| Contractor | Gaunty Construction Corp; Lic. No.: 1099695-B | , |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/11/2024 | Approved | ARUTYUN MADATYAN |
| Excavation/Setback/Form/Re-Bar | 9/20/2024 | Not Ready for Inspection | DAVID SCANTLIN |
| PLUMBING-Rough | 10/21/2024 | Partial Approval | ARUTYUN MADATYAN |
| Footing/Foundation/Slab | 10/29/2024 | Approved | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2024 | Conditional Approval | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 12/23/2024 | Partial Approval | ALEXANDER HANDY |
| ELECTRICAL-Rough | 12/23/2024 | Approved | ALEXANDER HANDY |
| Floor/Roof Diaphrgm/Shear Wall | 12/23/2024 | Approved | ALEXANDER HANDY |
| PLUMBING-Rough | 12/23/2024 | Approved | ALEXANDER HANDY |
| Sewer | 12/23/2024 | Approved | ALEXANDER HANDY |
| Verify Sprinkler Sign Off | 12/23/2024 | Not Ready for Inspection | ALEXANDER HANDY |
| Drywall Nailing | 1/8/2025 | Approved | SCOTT SOBEL |
| Insulation | 1/8/2025 | Approved | SCOTT SOBEL |
| Interior/Exterior Lathing | 1/8/2025 | Partial Approval | SCOTT SOBEL |
| Shower Pan | 1/22/2025 | Approved | ALEXANDER HANDY |
| HVAC-Rough | 2/4/2025 | Corrections Issued | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 5/6/2025 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 5/6/2025 | Corrections Issued | ALEXANDER HANDY |
| Final | 5/6/2025 | Corrections Issued | ALEXANDER HANDY |
| HVAC-Final | 5/6/2025 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 5/6/2025 | Corrections Issued | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 5/6/2025 | SGSOV Approved | ALEXANDER HANDY |
| Service/Power Release | 5/6/2025 | Not Ready for Inspection | ALEXANDER HANDY |
| Smoke Detectors | 5/6/2025 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 8/5/2025 | Approved | ALEXANDER HANDY |
| Final | 8/5/2025 | OK to Issue CofO | ALEXANDER HANDY |
| PLUMBING-Final | 8/5/2025 | Approved | ALEXANDER HANDY |
| Service/Power Release | 8/5/2025 | Approved | ALEXANDER HANDY |