19710 W LANARK ST 91306

Certificate Information: 19710 W LANARK ST 91306

Application / Permit
24010-20000-02132
Plan Check / Job No.
B24VN07077
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN: NEW DETACHED 648 SF ACCESSORY DWELLING UNIT (ADU) PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g).
Permit Issued
Issued on 7/24/2024
Issuing Office
Current Status
CofO Issued on 8/26/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/20/2024 APPLICANT
Assigned to Plan Check Engineer 5/24/2024 LUISANGEL VALENZUELA
Corrections Issued 5/25/2024 LUISANGEL VALENZUELA
Plan Check Approved 6/2/2024 LUISANGEL VALENZUELA
Issued 7/24/2024 APPLICANT
CofO in Progress 8/5/2025 ALEXANDER HANDY
Permit Finaled 8/26/2025 JOHN JANSON
Permit Finaled 8/26/2025 JOHN JANSON
CofO Issued 8/26/2025 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 5/29/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 5/29/2024 EDGAR ALCARAZ
Roof/Waste drainage to street Cleared 5/29/2024 CARLOS RAMIREZ
Sewer availability Cleared 5/29/2024 EDGAR ALCARAZ

Contact Information

Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor Gaunty Construction Corp; Lic. No.: 1099695-B       ,

Inspector Information

DAVID FASTIGGI, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI
ALEXANDER HANDY, (818) 774-4317 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/11/2024 Approved ARUTYUN MADATYAN
Excavation/Setback/Form/Re-Bar 9/20/2024 Not Ready for Inspection DAVID SCANTLIN
PLUMBING-Rough 10/21/2024 Partial Approval ARUTYUN MADATYAN
Footing/Foundation/Slab 10/29/2024 Approved ALEXANDER HANDY
Floor/Roof Diaphrgm/Shear Wall 11/19/2024 Conditional Approval ALEXANDER HANDY
BUILDING-Rough-Frame 12/23/2024 Partial Approval ALEXANDER HANDY
ELECTRICAL-Rough 12/23/2024 Approved ALEXANDER HANDY
Floor/Roof Diaphrgm/Shear Wall 12/23/2024 Approved ALEXANDER HANDY
PLUMBING-Rough 12/23/2024 Approved ALEXANDER HANDY
Sewer 12/23/2024 Approved ALEXANDER HANDY
Verify Sprinkler Sign Off 12/23/2024 Not Ready for Inspection ALEXANDER HANDY
Drywall Nailing 1/8/2025 Approved SCOTT SOBEL
Insulation 1/8/2025 Approved SCOTT SOBEL
Interior/Exterior Lathing 1/8/2025 Partial Approval SCOTT SOBEL
Shower Pan 1/22/2025 Approved ALEXANDER HANDY
HVAC-Rough 2/4/2025 Corrections Issued ALEXANDER HANDY
BUILDING-Rough-Frame 5/6/2025 Approved ALEXANDER HANDY
ELECTRICAL-Final 5/6/2025 Corrections Issued ALEXANDER HANDY
Final 5/6/2025 Corrections Issued ALEXANDER HANDY
HVAC-Final 5/6/2025 Approved ALEXANDER HANDY
PLUMBING-Final 5/6/2025 Corrections Issued ALEXANDER HANDY
SGSOV-Seismic Gas S/O Valve 5/6/2025 SGSOV Approved ALEXANDER HANDY
Service/Power Release 5/6/2025 Not Ready for Inspection ALEXANDER HANDY
Smoke Detectors 5/6/2025 Approved ALEXANDER HANDY
ELECTRICAL-Final 8/5/2025 Approved ALEXANDER HANDY
Final 8/5/2025 OK to Issue CofO ALEXANDER HANDY
PLUMBING-Final 8/5/2025 Approved ALEXANDER HANDY
Service/Power Release 8/5/2025 Approved ALEXANDER HANDY