14117 W VALERIO ST 91405

Certificate Information: 14117 W VALERIO ST 91405

Application / Permit
24010-20000-02102
Plan Check / Job No.
B24VN06960
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
**Eplan** New 2 story detached ADU per ordinance per engineer design
Permit Issued
Issued on 1/20/2025
Issuing Office
Current Status
CofO Issued on 8/19/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/20/2024 APPLICANT
Assigned to Plan Check Engineer 5/30/2024 YASHAR EMAMI
Corrections Issued 6/7/2024 YASHAR EMAMI
Quality Review Completed 6/18/2024 KAVIAN REFAHI
Applicant returned to address corrections 1/3/2025 YASHAR EMAMI
Plan Check Approved 1/17/2025 YASHAR EMAMI
Issued 1/20/2025 APPLICANT
CofO in Progress 7/30/2025 VINCENT HANLEY
Permit Finaled 8/19/2025 RUBEN SALAS
CofO Issued 8/19/2025 RUBEN SALAS
Permit Finaled 8/19/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 8/5/2024 KENIA CASTILLO
Roof/Waste drainage to street Cleared 8/5/2024 KENIA CASTILLO
Sewer availability Cleared 8/7/2024 KENIA CASTILLO
ZI Cleared 8/7/2024 ALEX VELA
ZI Cleared 8/7/2024 ALEX VELA
Eng Process Fee Ord 176,300 Cleared 9/5/2024 KENIA CASTILLO
Hydrant and Access approval Cleared 9/20/2024 LAVEON RIDER

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/18/2025 Partial Approval VINCENT HANLEY
Excavation/Setback/Form/Re-Bar 2/27/2025 Approved VINCENT HANLEY
Footing/Foundation/Slab 2/27/2025 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 3/14/2025 Partial Approval MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 3/25/2025 Corrections Issued WILLIAM WREN
Deputy Wood Construction 3/26/2025 Conditional Approval RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 3/28/2025 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 4/4/2025 Approved VINCENT HANLEY
PLUMBING-Rough 4/4/2025 Approved VINCENT HANLEY
BUILDING-Rough-Frame 4/8/2025 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 4/8/2025 Approved VINCENT HANLEY
Green Building Rough 4/8/2025 Approved VINCENT HANLEY
HVAC-Rough 4/8/2025 Approved VINCENT HANLEY
Insulation 4/16/2025 Corrections Issued JACK KARGODORIAN
Interior/Exterior Lathing 4/16/2025 Partial Approval JACK KARGODORIAN
Shower Pan 4/16/2025 Not Ready for Inspection JACK KARGODORIAN
Insulation 4/17/2025 Approved VINCENT HANLEY
Shower Pan 4/18/2025 Approved VINCENT HANLEY
Drywall Nailing 4/21/2025 Approved MICHAEL CORTEZ
Shower Pan 4/28/2025 Approved DAVID MATSON
Interior/Exterior Lathing 5/2/2025 Approved VINCENT HANLEY
Sewer 5/19/2025 Approved VINCENT HANLEY
Underground Mechanical 5/19/2025 Approved VINCENT HANLEY
ELECTRICAL-Final 7/24/2025 Approved VINCENT HANLEY
Final 7/24/2025 Corrections Issued VINCENT HANLEY
Green Building Final 7/24/2025 Approved VINCENT HANLEY
HVAC-Final 7/24/2025 Approved VINCENT HANLEY
PLUMBING-Final 7/24/2025 Approved VINCENT HANLEY
SGSOV-Seismic Gas S/O Valve 7/24/2025 SGSOV Not Required VINCENT HANLEY
Service/Power Release 7/24/2025 Approved VINCENT HANLEY
Smoke Detectors 7/24/2025 Approved VINCENT HANLEY
Final 7/29/2025 OK to Issue CofO VINCENT HANLEY