11325 N COLLETT AVE 91344
Certificate Information: 11325 N COLLETT AVE 91344
- Application / Permit
- 24010-20000-02089
- Plan Check / Job No.
- B24VN06887
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- <ePLAN> (N) 26'0"X46'0" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) {ALL ELECTRIC BUILDING} (1 OF 2)
- Permit Issued
- Issued on 9/20/2024
- Issuing Office
- Current Status
- CofO Issued on 9/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/30/2024 | MARVEL DELACRUZ |
| Corrections Issued | 6/6/2024 | MARVEL DELACRUZ |
| Quality Review Completed | 6/6/2024 | OMID HEDAYAT |
| Applicant returned to address corrections | 9/11/2024 | MARVEL DELACRUZ |
| Plan Check Approved | 9/19/2024 | MARVEL DELACRUZ |
| No Progress | 9/19/2024 | MARVEL DELACRUZ |
| Plan Check Approved | 9/19/2024 | MARVEL DELACRUZ |
| Issued | 9/20/2024 | APPLICANT |
| CofO in Progress | 9/2/2025 | CHRISTOPHER ROJAS |
| No Progress | 9/4/2025 | RAUL OLAGI |
| CofO in Progress | 9/4/2025 | RAUL OLAGI |
| CofO in Progress | 9/5/2025 | CHRISTOPHER ROJAS |
| CofO in Progress | 9/11/2025 | CHRISTOPHER ROJAS |
| Permit Finaled | 9/12/2025 | RUBEN SALAS |
| CofO Issued | 9/12/2025 | RUBEN SALAS |
| Permit Finaled | 9/12/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/14/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 6/14/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 6/14/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 6/17/2024 | BIAINA HARITUNIAN |
| Grading Pre-Inspection | Cleared | 6/27/2024 | CHARLES POWELL |
| Hydrant and Access approval | Cleared | 8/24/2024 | RUEL COLE |
| GPI Written Notices | Cleared | 9/11/2024 | MARVEL DELACRUZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 3625 BEVERLY RIDGE DRIVE SHERMAN OAKS, CA 91423 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/26/2024 | Approved | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 10/17/2024 | Corrections Issued | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 11/5/2024 | Partial Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 11/5/2024 | Approved | JAVIER RAMOS JR |
| Insulation | 11/5/2024 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 11/5/2024 | Partial Approval | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 11/22/2024 | Corrections Issued | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 1/10/2025 | Partial Inspection | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 1/10/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 1/10/2025 | Corrections Issued | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 1/10/2025 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 1/10/2025 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2025 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 1/31/2025 | Approved | JAVIER RAMOS JR |
| Insulation | 1/31/2025 | No Access for Inspection | JAVIER RAMOS JR |
| Drywall Nailing | 2/21/2025 | Approved | LOUIS ESCOTO |
| Green Building Rough | 2/21/2025 | Approved | LOUIS ESCOTO |
| Insulation | 2/21/2025 | Approved | LOUIS ESCOTO |
| Shower Pan | 3/28/2025 | Approved | CHRISTOPHER ROJAS |
| Underground Mechanical | 3/28/2025 | Partial Approval | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 7/16/2025 | Approved | CHRISTOPHER ROJAS |
| Final | 7/16/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 7/16/2025 | Approved | CHRISTOPHER ROJAS |
| SGSOV-Seismic Gas S/O Valve | 7/16/2025 | SGSOV Approved | CHRISTOPHER ROJAS |
| Service/Power Release | 7/16/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Smoke Detectors | 7/16/2025 | Approved | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 7/16/2025 | Approved | CHRISTOPHER ROJAS |
| Final | 8/20/2025 | No Access for Inspection | CHRISTOPHER ROJAS |
| Service/Power Release | 8/20/2025 | No Access for Inspection | CHRISTOPHER ROJAS |
| Pre-Inspection | 8/22/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Final | 8/29/2025 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Service/Power Release | 8/29/2025 | Approved | CHRISTOPHER ROJAS |
| Final | 9/5/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 9/11/2025 | OK to Issue CofO | CHRISTOPHER ROJAS |