11325 N COLLETT AVE 91344

Certificate Information: 11325 N COLLETT AVE 91344

Application / Permit
24010-20000-02089
Plan Check / Job No.
B24VN06887
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
<ePLAN> (N) 26'0"X46'0" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d) {ALL ELECTRIC BUILDING} (1 OF 2)
Permit Issued
Issued on 9/20/2024
Issuing Office
Current Status
CofO Issued on 9/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/16/2024 APPLICANT
Assigned to Plan Check Engineer 5/30/2024 MARVEL DELACRUZ
Corrections Issued 6/6/2024 MARVEL DELACRUZ
Quality Review Completed 6/6/2024 OMID HEDAYAT
Applicant returned to address corrections 9/11/2024 MARVEL DELACRUZ
Plan Check Approved 9/19/2024 MARVEL DELACRUZ
No Progress 9/19/2024 MARVEL DELACRUZ
Plan Check Approved 9/19/2024 MARVEL DELACRUZ
Issued 9/20/2024 APPLICANT
CofO in Progress 9/2/2025 CHRISTOPHER ROJAS
No Progress 9/4/2025 RAUL OLAGI
CofO in Progress 9/4/2025 RAUL OLAGI
CofO in Progress 9/5/2025 CHRISTOPHER ROJAS
CofO in Progress 9/11/2025 CHRISTOPHER ROJAS
Permit Finaled 9/12/2025 RUBEN SALAS
CofO Issued 9/12/2025 RUBEN SALAS
Permit Finaled 9/12/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/14/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 6/14/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 6/14/2024 BIAINA HARITUNIAN
Sewer availability Cleared 6/17/2024 BIAINA HARITUNIAN
Grading Pre-Inspection Cleared 6/27/2024 CHARLES POWELL
Hydrant and Access approval Cleared 8/24/2024 RUEL COLE
GPI Written Notices Cleared 9/11/2024 MARVEL DELACRUZ

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/26/2024 Approved JAVIER RAMOS JR
Footing/Foundation/Slab 10/17/2024 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 11/5/2024 Partial Approval JAVIER RAMOS JR
Footing/Foundation/Slab 11/5/2024 Approved JAVIER RAMOS JR
Insulation 11/5/2024 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 11/5/2024 Partial Approval JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 11/22/2024 Corrections Issued JAVIER RAMOS JR
BUILDING-Rough-Frame 1/10/2025 Partial Inspection JAVIER RAMOS JR
ELECTRICAL-Rough 1/10/2025 Approved JAVIER RAMOS JR
HVAC-Rough 1/10/2025 Corrections Issued JAVIER RAMOS JR
Interior/Exterior Lathing 1/10/2025 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 1/10/2025 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 1/31/2025 Approved JAVIER RAMOS JR
HVAC-Rough 1/31/2025 Approved JAVIER RAMOS JR
Insulation 1/31/2025 No Access for Inspection JAVIER RAMOS JR
Drywall Nailing 2/21/2025 Approved LOUIS ESCOTO
Green Building Rough 2/21/2025 Approved LOUIS ESCOTO
Insulation 2/21/2025 Approved LOUIS ESCOTO
Shower Pan 3/28/2025 Approved CHRISTOPHER ROJAS
Underground Mechanical 3/28/2025 Partial Approval CHRISTOPHER ROJAS
BUILDING-Rough-Frame 7/16/2025 Approved CHRISTOPHER ROJAS
Final 7/16/2025 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 7/16/2025 Approved CHRISTOPHER ROJAS
SGSOV-Seismic Gas S/O Valve 7/16/2025 SGSOV Approved CHRISTOPHER ROJAS
Service/Power Release 7/16/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Smoke Detectors 7/16/2025 Approved CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 7/16/2025 Approved CHRISTOPHER ROJAS
Final 8/20/2025 No Access for Inspection CHRISTOPHER ROJAS
Service/Power Release 8/20/2025 No Access for Inspection CHRISTOPHER ROJAS
Pre-Inspection 8/22/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Final 8/29/2025 Not Ready for Inspection CHRISTOPHER ROJAS
Service/Power Release 8/29/2025 Approved CHRISTOPHER ROJAS
Final 9/5/2025 Corrections Issued CHRISTOPHER ROJAS
Final 9/11/2025 OK to Issue CofO CHRISTOPHER ROJAS