4237 N RHODES AVE 91604
Certificate Information: 4237 N RHODES AVE 91604
- Application / Permit
- 24010-20000-02088
- Plan Check / Job No.
- B24VN06886
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New one story irregular shaped 36' x 16' 4" ADU per CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g). NFPA 13D sprinkler required. All work done per engineer.
- Permit Issued
- Issued on 10/11/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/16/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/23/2024 | NAREG ATARIAN |
| Corrections Issued | 5/29/2024 | NAREG ATARIAN |
| Quality Review Completed | 5/29/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 5/30/2024 | APPLICANT |
| Applicant returned to address corrections | 8/22/2024 | NAREG ATARIAN |
| Plan Check Approved | 10/11/2024 | NAREG ATARIAN |
| Issued | 10/11/2024 | APPLICANT |
| CofO in Progress | 9/8/2025 | CHRISTOPHE COCHRAN |
| Permit Finaled | 9/25/2025 | RUBEN SALAS |
| CofO Issued | 9/25/2025 | RUBEN SALAS |
| Permit Finaled | 9/25/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/2/2024 | TAL SHEMEN |
| Roof/Waste drainage to street | Cleared | 6/2/2024 | TAL SHEMEN |
| Eng Process Fee Ord 176,300 | Cleared | 6/3/2024 | TAL SHEMEN |
| Sewer availability | Cleared | 6/3/2024 | TAL SHEMEN |
| ZI | Cleared | 6/5/2024 | DORIAN AGUILAR |
| Construction near power lines | Cleared | 10/7/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wang,, Hongyu; Lic. No.: C72679 | 8887 W FALMINGO RD STE 101 LAS VEGAS, NV 89147 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/16/2024 | Approved | CHRISTOPHE COCHRAN |
| Sewer | 10/16/2024 | Approved | CHRISTOPHE COCHRAN |
| Underground Mechanical | 10/16/2024 | Approved | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/20/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/10/2024 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 12/13/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Green Building Rough | 12/13/2024 | Approved | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 12/13/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 12/17/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 12/20/2024 | Approved | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 12/20/2024 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 12/23/2024 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 12/23/2024 | Approved | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 12/23/2024 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 2/11/2025 | Approved | JACK KARGODORIAN |
| Drywall Nailing | 2/18/2025 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 2/18/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Shower Pan | 2/20/2025 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 3/5/2025 | Approved | CHRISTOPHE COCHRAN |
| Final | 8/20/2025 | OK to Issue CofO | CHRISTOPHE COCHRAN |
| Green Building Final | 8/20/2025 | Approved | CHRISTOPHE COCHRAN |
| SGSOV-Seismic Gas S/O Valve | 8/20/2025 | SGSOV Approved | CHRISTOPHE COCHRAN |
| Service/Power Release | 8/20/2025 | Approved | CHRISTOPHE COCHRAN |
| Smoke Detectors | 8/20/2025 | Approved | CHRISTOPHE COCHRAN |