4803 N ABBEYVILLE AVE 91364
Certificate Information: 4803 N ABBEYVILLE AVE 91364
- Application / Permit
- 24010-20000-02047
- Plan Check / Job No.
- B24VN06747
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g).
- Permit Issued
- Issued on 7/19/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/17/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/14/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/21/2024 | PINANK PATEL |
| Corrections Issued | 5/21/2024 | PINANK PATEL |
| Building Plans Picked Up | 5/23/2024 | APPLICANT |
| Plan Check Approved | 7/19/2024 | SARKIS HARABEDIAN |
| Issued | 7/19/2024 | APPLICANT |
| CofO in Progress | 5/26/2025 | MORRIS JACKSON |
| No Progress | 6/11/2025 | SEAN WIRCH |
| CofO in Progress | 6/11/2025 | SEAN WIRCH |
| Permit Finaled | 3/17/2026 | JOHN JANSON |
| CofO Issued | 3/17/2026 | JOHN JANSON |
| Permit Finaled | 3/17/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 5/30/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/30/2024 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 5/30/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 5/30/2024 | EDGAR ALCARAZ |
| Grading Pre-Inspection | Cleared | 5/31/2024 | RUSSELL BONVOULOIR |
| Hydrant and Access approval | Cleared | 7/6/2024 | JOHN CONNEALLY |
| Construction near power lines | Cleared | 7/11/2024 | WALTER RAMIREZ |
| Construction within easement | Cleared | 7/11/2024 | WALTER RAMIREZ |
| GPI Written Notices | Cleared | 7/19/2024 | PINANK PATEL |
Contact Information
| Contractor | N R D P Construction Inc; Lic. No.: 859261-B | 6042 WOODLAND VIEW DRIVE WOODLAND HILLS, CA 91367 |
| Engineer | Samadzadeh,, Hooman Ali; Lic. No.: C87661 | 22430 CRISWELL ST WEST HILLS, CA 91307 |
Inspector Information
| JOHN HAYES, (818) 774-4302 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 7/26/2024 | Partial Approval | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 8/1/2024 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 8/1/2024 | Not Ready for Inspection | JOHN HAYES |
| Underground Mechanical | 8/1/2024 | Corrections Issued | JOHN HAYES |
| Underground Mechanical | 8/13/2024 | Partial Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 8/22/2024 | Corrections Issued | JOHN HAYES |
| Footing/Foundation/Slab | 8/27/2024 | Approved | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 10/15/2024 | Partial Approval | JOHN HAYES |
| Gas Test | 10/15/2024 | Partial Approval | JOHN HAYES |
| Gas Test | 10/28/2024 | Approved | JOHN HAYES |
| HVAC-Rough | 10/28/2024 | Approved | JOHN HAYES |
| PLUMBING-Rough | 10/28/2024 | Approved | JOHN HAYES |
| Underground Mechanical | 10/28/2024 | Partial Approval | JOHN HAYES |
| BUILDING-Rough-Frame | 11/12/2024 | Corrections Issued | JOHN HAYES |
| Green Building Rough | 11/12/2024 | Not Ready for Inspection | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 11/12/2024 | Partial Approval | JOHN HAYES |
| Shower Pan | 11/12/2024 | Approved | JOHN HAYES |
| Verify Sprinkler Sign Off | 11/12/2024 | Approved | JOHN HAYES |
| BUILDING-Rough-Frame | 11/20/2024 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 11/20/2024 | Approved | JOHN HAYES |
| Green Building Rough | 11/20/2024 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 11/20/2024 | Partial Approval | JOHN HAYES |
| Insulation | 12/3/2024 | Approved | JOHN HAYES |
| Drywall Nailing | 12/10/2024 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 12/10/2024 | Not Ready for Inspection | JOHN HAYES |
| Interior/Exterior Lathing | 12/12/2024 | Approved | JOHN HAYES |
| Gas Test | 4/9/2025 | Approved | JOHN HAYES |
| ELECTRICAL-Final | 5/7/2025 | Approved | JOHN HAYES |
| Final | 5/7/2025 | Corrections Issued | JOHN HAYES |
| Green Building Final | 5/7/2025 | Approved | JOHN HAYES |
| HVAC-Final | 5/7/2025 | Approved | JOHN HAYES |
| PLUMBING-Final | 5/7/2025 | Approved | JOHN HAYES |
| SGSOV-Seismic Gas S/O Valve | 5/7/2025 | SGSOV Not Ready | JOHN HAYES |
| Service/Power Release | 5/7/2025 | Not Ready for Inspection | JOHN HAYES |
| Smoke Detectors | 5/7/2025 | Approved | JOHN HAYES |
| Final | 5/23/2025 | OK to Issue CofO | MORRIS JACKSON |
| SGSOV-Seismic Gas S/O Valve | 5/23/2025 | SGSOV Approved | MORRIS JACKSON |
| Service/Power Release | 5/23/2025 | Approved | MORRIS JACKSON |
| Special/Order Compliance | 6/23/2025 | Corrections Issued | JOHN HAYES |