9013 W SAWYER ST 90035

Certificate Information: 9013 W SAWYER ST 90035

Application / Permit
24010-20000-02044
Plan Check / Job No.
B24VN06738
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 41'-6" X 69'-7" TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 10/21/2024
Issuing Office
Valley
Current Status
CofO Issued on 5/22/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/14/2024 APPLICANT
Assigned to Plan Check Engineer 5/23/2024 SELLA BENYAMIN
Corrections Issued 5/30/2024 SELLA BENYAMIN
Quality Review Completed 5/31/2024 STEVEN KIM
Building Plans Picked Up 6/20/2024 APPLICANT
Applicant returned to address corrections 9/26/2024 SELLA BENYAMIN
Plan Check Approved 10/17/2024 SELLA BENYAMIN
Issued 10/21/2024 APPLICANT
CofO in Progress 5/18/2026 ASHLEY THOMPSON
CofO in Progress 5/22/2026 BOBBY KEY
Permit Finaled 5/22/2026 RICHARD STEINBACH
CofO Issued 5/22/2026 RICHARD STEINBACH
Permit Finaled 5/22/2026 RICHARD STEINBACH

Permit Application Clearance Information

Low Impact Development (LID) Cleared 7/18/2024 SARAH YOUSSEF
Eng Process Fee Ord 176,300 Cleared 7/30/2024 DARIN LAM
Sewer availability Cleared 7/30/2024 DARIN LAM
Permit Cleared 8/1/2024 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 8/1/2024 HISASHI KOBAYAKAWA
Hydrant and Access approval Cleared 8/26/2024 KURT CORRAL
Trees in Parkway Cleared 9/11/2024 ADALBERTO VERA
GPI Written Notices Cleared 9/26/2024 SELLA BENYAMIN
Grading Pre-Inspection Cleared 9/26/2024 SELLA BENYAMIN

Contact Information

Contractor Norman Construction; Lic. No.: 535530-B 17614 SUPERIOR STREET      NORTHRIDGE, CA 91325
Engineer Shachar,, Shaul Shkory; Lic. No.: C29686 18208 EMELITA ST      TARZANA, CA 91356

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/6/2024 Partial Inspection BOBBY KEY
Footing/Foundation/Slab 11/6/2024 Corrections Issued BOBBY KEY
Excavation/Setback/Form/Re-Bar 12/24/2024 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 1/10/2025 Partial Approval BOBBY KEY
Special/Order Compliance 1/10/2025 Partial Inspection JAYLIN GRAVITTE
Wood Frame 1/10/2025 Partial Approval BOBBY KEY
Floor/Roof Diaphrgm/Shear Wall 1/14/2025 Partial Approval MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 2/3/2025 Corrections Issued ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 2/4/2025 Partial Approval ARAM AVEDISIAN
METHANE-Subgrade 3/18/2025 Corrections Issued ASHLEY THOMPSON
METHANE-Subgrade 3/20/2025 Approved ASHLEY THOMPSON
Footing/Foundation/Slab 3/25/2025 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 4/8/2025 Corrections Issued STEPHANIE SWANSON
HVAC-Rough 4/8/2025 Not Ready for Inspection STEPHANIE SWANSON
Shower Pan 4/8/2025 Not Ready for Inspection STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 4/10/2025 Corrections Issued ASHLEY THOMPSON
Special/Order Compliance 4/10/2025 Partial Inspection DAVID FEILER
HVAC-Rough 4/15/2025 Corrections Issued ASHLEY THOMPSON
PLUMBING-Rough 4/15/2025 Corrections Issued ASHLEY THOMPSON
ELECTRICAL-Rough 4/17/2025 Approved EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 4/17/2025 Corrections Issued EVAN COOPER
Deputy Wood Construction 4/21/2025 Conditional Approval ASHLEY THOMPSON
Floor/Roof Diaphrgm/Shear Wall 5/6/2025 Conditional Approval MEL KHACHATOURIAN
Green Building Rough 5/6/2025 Partial Approval MEL KHACHATOURIAN
PLUMBING-Rough 5/6/2025 Approved MEL KHACHATOURIAN
Verify Sprinkler Sign Off 5/6/2025 Approved MEL KHACHATOURIAN
BUILDING-Rough-Frame 5/16/2025 Approved EVAN COOPER
Green Building Rough 5/16/2025 Approved EVAN COOPER
HVAC-Rough 5/16/2025 Approved EVAN COOPER
Shower Pan 5/16/2025 Approved EVAN COOPER
Insulation 6/2/2025 Approved EVAN COOPER
Deputy Drilled-In Anchors 6/4/2025 Conditional Approval ARAM AVEDISIAN
Drywall Nailing 6/12/2025 Approved EVAN COOPER
Excavation/Setback/Form/Re-Bar 6/12/2025 Partial Approval EVAN COOPER
Interior/Exterior Lathing 6/12/2025 Partial Approval EVAN COOPER
Excavation/Setback/Form/Re-Bar 6/24/2025 Approved ASHLEY THOMPSON
Interior/Exterior Lathing 7/30/2025 Approved ASHLEY THOMPSON
ELECTRICAL-Final 3/3/2026 Corrections Issued ASHLEY THOMPSON
ELECTRICAL-Final 4/2/2026 Not Ready for Inspection ASHLEY THOMPSON
PLUMBING-Final 4/2/2026 Corrections Issued ASHLEY THOMPSON
ELECTRICAL-Final 4/22/2026 Not Ready for Inspection WILBER ROSALES
HVAC-Final 4/22/2026 Approved WILBER ROSALES
PLUMBING-Final 4/22/2026 Approved WILBER ROSALES
Service/Power Release 4/22/2026 Not Ready for Inspection WILBER ROSALES
Final 5/5/2026 Corrections Issued ASHLEY THOMPSON
Green Building Final 5/5/2026 Approved ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 5/5/2026 SGSOV Not Required ASHLEY THOMPSON
Service/Power Release 5/5/2026 Approved ASHLEY THOMPSON
Smoke Detectors 5/5/2026 Approved ASHLEY THOMPSON
Final 5/18/2026 OK to Issue CofO ASHLEY THOMPSON
Service/Power Release 5/18/2026 Approved ASHLEY THOMPSON