9013 W SAWYER ST 90035
Certificate Information: 9013 W SAWYER ST 90035
- Application / Permit
- 24010-20000-02044
- Plan Check / Job No.
- B24VN06738
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 41'-6" X 69'-7" TWO STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13-D FIRE SPRINKLERS THROUGHOUT
- Permit Issued
- Issued on 10/21/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/22/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/14/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/23/2024 | SELLA BENYAMIN |
| Corrections Issued | 5/30/2024 | SELLA BENYAMIN |
| Quality Review Completed | 5/31/2024 | STEVEN KIM |
| Building Plans Picked Up | 6/20/2024 | APPLICANT |
| Applicant returned to address corrections | 9/26/2024 | SELLA BENYAMIN |
| Plan Check Approved | 10/17/2024 | SELLA BENYAMIN |
| Issued | 10/21/2024 | APPLICANT |
| CofO in Progress | 5/18/2026 | ASHLEY THOMPSON |
| CofO in Progress | 5/22/2026 | BOBBY KEY |
| Permit Finaled | 5/22/2026 | RICHARD STEINBACH |
| CofO Issued | 5/22/2026 | RICHARD STEINBACH |
| Permit Finaled | 5/22/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 7/18/2024 | SARAH YOUSSEF |
| Eng Process Fee Ord 176,300 | Cleared | 7/30/2024 | DARIN LAM |
| Sewer availability | Cleared | 7/30/2024 | DARIN LAM |
| Permit | Cleared | 8/1/2024 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 8/1/2024 | HISASHI KOBAYAKAWA |
| Hydrant and Access approval | Cleared | 8/26/2024 | KURT CORRAL |
| Trees in Parkway | Cleared | 9/11/2024 | ADALBERTO VERA |
| GPI Written Notices | Cleared | 9/26/2024 | SELLA BENYAMIN |
| Grading Pre-Inspection | Cleared | 9/26/2024 | SELLA BENYAMIN |
Contact Information
| Contractor | Norman Construction; Lic. No.: 535530-B | 17614 SUPERIOR STREET NORTHRIDGE, CA 91325 |
| Engineer | Shachar,, Shaul Shkory; Lic. No.: C29686 | 18208 EMELITA ST TARZANA, CA 91356 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 11/6/2024 | Partial Inspection | BOBBY KEY |
| Footing/Foundation/Slab | 11/6/2024 | Corrections Issued | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 12/24/2024 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 1/10/2025 | Partial Approval | BOBBY KEY |
| Special/Order Compliance | 1/10/2025 | Partial Inspection | JAYLIN GRAVITTE |
| Wood Frame | 1/10/2025 | Partial Approval | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 1/14/2025 | Partial Approval | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/3/2025 | Corrections Issued | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/4/2025 | Partial Approval | ARAM AVEDISIAN |
| METHANE-Subgrade | 3/18/2025 | Corrections Issued | ASHLEY THOMPSON |
| METHANE-Subgrade | 3/20/2025 | Approved | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 3/25/2025 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2025 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 4/8/2025 | Not Ready for Inspection | STEPHANIE SWANSON |
| Shower Pan | 4/8/2025 | Not Ready for Inspection | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2025 | Corrections Issued | ASHLEY THOMPSON |
| Special/Order Compliance | 4/10/2025 | Partial Inspection | DAVID FEILER |
| HVAC-Rough | 4/15/2025 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Rough | 4/15/2025 | Corrections Issued | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 4/17/2025 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2025 | Corrections Issued | EVAN COOPER |
| Deputy Wood Construction | 4/21/2025 | Conditional Approval | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2025 | Conditional Approval | MEL KHACHATOURIAN |
| Green Building Rough | 5/6/2025 | Partial Approval | MEL KHACHATOURIAN |
| PLUMBING-Rough | 5/6/2025 | Approved | MEL KHACHATOURIAN |
| Verify Sprinkler Sign Off | 5/6/2025 | Approved | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 5/16/2025 | Approved | EVAN COOPER |
| Green Building Rough | 5/16/2025 | Approved | EVAN COOPER |
| HVAC-Rough | 5/16/2025 | Approved | EVAN COOPER |
| Shower Pan | 5/16/2025 | Approved | EVAN COOPER |
| Insulation | 6/2/2025 | Approved | EVAN COOPER |
| Deputy Drilled-In Anchors | 6/4/2025 | Conditional Approval | ARAM AVEDISIAN |
| Drywall Nailing | 6/12/2025 | Approved | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 6/12/2025 | Partial Approval | EVAN COOPER |
| Interior/Exterior Lathing | 6/12/2025 | Partial Approval | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 6/24/2025 | Approved | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 7/30/2025 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 3/3/2026 | Corrections Issued | ASHLEY THOMPSON |
| ELECTRICAL-Final | 4/2/2026 | Not Ready for Inspection | ASHLEY THOMPSON |
| PLUMBING-Final | 4/2/2026 | Corrections Issued | ASHLEY THOMPSON |
| ELECTRICAL-Final | 4/22/2026 | Not Ready for Inspection | WILBER ROSALES |
| HVAC-Final | 4/22/2026 | Approved | WILBER ROSALES |
| PLUMBING-Final | 4/22/2026 | Approved | WILBER ROSALES |
| Service/Power Release | 4/22/2026 | Not Ready for Inspection | WILBER ROSALES |
| Final | 5/5/2026 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Final | 5/5/2026 | Approved | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 5/5/2026 | SGSOV Not Required | ASHLEY THOMPSON |
| Service/Power Release | 5/5/2026 | Approved | ASHLEY THOMPSON |
| Smoke Detectors | 5/5/2026 | Approved | ASHLEY THOMPSON |
| Final | 5/18/2026 | OK to Issue CofO | ASHLEY THOMPSON |
| Service/Power Release | 5/18/2026 | Approved | ASHLEY THOMPSON |