5653 N CORBIN AVE 91356

Certificate Information: 5653 N CORBIN AVE 91356

Application / Permit
24010-20000-02031
Plan Check / Job No.
B24VN05851
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED 1-STORY (30'-0"x32'-10"), 799 SQFT ACCESSORY DWELLING UNIT PER CA GOVT CODE 65852.2(e)(1)(D) AND LAMC 12.22 A.33(c)(d)(g). ALL ELECTRIC BUILDING. NFPA 13D SPRINKLERS REQUIRED THROUGHOUT (BACK LEFT)
Permit Issued
Issued on 7/30/2024
Issuing Office
Current Status
CofO Issued on 2/10/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/29/2024 APPLICANT
Assigned to Plan Check Engineer 5/2/2024 PETER MOSESIAN
Corrections Issued 5/5/2024 PETER MOSESIAN
Quality Review Completed 5/8/2024 OMID HEDAYAT
Applicant returned to address corrections 7/23/2024 PETER MOSESIAN
Plan Check Approved 7/30/2024 PETER MOSESIAN
Issued 7/30/2024 APPLICANT
CofO in Progress 1/2/2025 MORRIS JACKSON
Permit Finaled 2/10/2025 JOHN JANSON
CofO Issued 2/10/2025 JOHN JANSON
Permit Finaled 2/10/2025 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/4/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 6/4/2024 CARLOS AGUILERA
Sewer availability Cleared 6/4/2024 CARLOS AGUILERA
Address approval Cleared 6/5/2024 CARLOS AGUILERA
Hydrant and Access approval Cleared 7/12/2024 GILBERT URREA

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

JON MCHUGH, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI
IVAN SARABIA, (818) 774-4348 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 8/5/2024 Partial Approval JON MCHUGH
Excavation/Setback/Form/Re-Bar 8/15/2024 Approved MORRIS JACKSON
Footing/Foundation/Slab 8/15/2024 Approved MORRIS JACKSON
HVAC-Rough 9/23/2024 No Access for Inspection JON MCHUGH
Floor/Roof Diaphrgm/Shear Wall 9/25/2024 Corrections Issued MORRIS JACKSON
HVAC-Rough 9/25/2024 Approved MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 9/30/2024 Not Ready for Inspection MORRIS JACKSON
Gas Test 9/30/2024 Approved MORRIS JACKSON
PLUMBING-Rough 9/30/2024 Approved MORRIS JACKSON
ELECTRICAL-Rough 10/1/2024 Approved MORRIS JACKSON
Shower Pan 10/4/2024 Approved MORRIS JACKSON
Shower Pan 10/7/2024 Partial Inspection MORRIS JACKSON
Underground Mechanical 10/7/2024 Approved MORRIS JACKSON
Floor/Roof Diaphrgm/Shear Wall 10/15/2024 Corrections Issued MORRIS JACKSON
Green Building Rough 10/15/2024 Not Ready for Inspection MORRIS JACKSON
Interior/Exterior Lathing 10/15/2024 Partial Approval MORRIS JACKSON
MERV13>=Rough 10/15/2024 Not Ready for Inspection MORRIS JACKSON
Verify Sprinkler Sign Off 10/15/2024 Corrections Issued MORRIS JACKSON
BUILDING-Rough-Frame 10/21/2024 Corrections Issued MORRIS JACKSON
Green Building Rough 10/21/2024 Approved MORRIS JACKSON
Insulation 10/21/2024 Approved MORRIS JACKSON
Interior/Exterior Lathing 10/21/2024 Not Ready for Inspection MORRIS JACKSON
MERV13>=Rough 10/21/2024 Approved MORRIS JACKSON
Verify Sprinkler Sign Off 10/21/2024 Approved MORRIS JACKSON
BUILDING-Rough-Frame 10/24/2024 Approved MORRIS JACKSON
Interior/Exterior Lathing 10/24/2024 Approved MORRIS JACKSON
Drywall Nailing 10/25/2024 Approved MORRIS JACKSON
Interior/Exterior Lathing 10/25/2024 Approved MORRIS JACKSON
ELECTRICAL-Final 12/16/2024 Approved MORRIS JACKSON
HVAC-Final 12/16/2024 Approved MORRIS JACKSON
PLUMBING-Final 12/16/2024 Approved MORRIS JACKSON
Service/Power Release 12/16/2024 Not Ready for Inspection MORRIS JACKSON
Final 12/19/2024 OK to Issue CofO MORRIS JACKSON
Green Building Final 12/19/2024 Approved MORRIS JACKSON
MERV13>=Final 12/19/2024 Approved MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 12/19/2024 SGSOV Not Required MORRIS JACKSON
Service/Power Release 12/19/2024 Approved MORRIS JACKSON
Smoke Detectors 12/19/2024 Approved MORRIS JACKSON