6647 N FAIR AVE 91606
Certificate Information: 6647 N FAIR AVE 91606
- Application / Permit
- 24010-20000-01988
- Plan Check / Job No.
- B24VN06596
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *ePlan: NEW 2-STORY, DETACHED ACCESSORY DWELLING UNIT
- Permit Issued
- Issued on 6/28/2024
- Issuing Office
- Current Status
- CofO Issued on 6/5/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/13/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/23/2024 | QUAN NGHIEM |
| Corrections Issued | 5/25/2024 | QUAN NGHIEM |
| Quality Review Completed | 5/31/2024 | MINYE PAK |
| Applicant returned to address corrections | 6/13/2024 | QUAN NGHIEM |
| Plan Check Approved | 6/24/2024 | QUAN NGHIEM |
| Issued | 6/28/2024 | APPLICANT |
| CofO in Progress | 5/15/2025 | JOSE AVILA |
| Permit Finaled | 6/5/2025 | RUBEN SALAS |
| CofO Issued | 6/5/2025 | RUBEN SALAS |
| Permit Finaled | 6/5/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 6/6/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 6/6/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 6/7/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 6/8/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Ultimate Green Construction Inc; Lic. No.: 1023605-B | , |
| Engineer | Moser,, Bradley Charles; Lic. No.: C68803 | 116 OAKSIDE LN BUELLTON, CA 93427 |
Inspector Information
| GAREN HAYRAPETYAN, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERTO PALACIOS-LOPEZ, (818) 374-1171 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/20/2024 | Partial Approval | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 8/27/2024 | Approved | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2024 | Corrections Issued | JOSE AVILA |
| Deputy Wood Construction | 9/17/2024 | Conditional Approval | DAVID MATSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/18/2024 | Partial Approval | JOSE AVILA |
| Deputy Wood Construction | 10/25/2024 | Conditional Approval | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 10/25/2024 | Corrections Issued | JOSE AVILA |
| HVAC-Rough | 11/1/2024 | Approved | JOSE AVILA |
| Wood Frame | 11/1/2024 | Not Ready for Inspection | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 11/5/2024 | Partial Approval | JOSE AVILA |
| Sewer | 11/5/2024 | Approved | JOSE AVILA |
| Underground Mechanical | 11/5/2024 | Partial Approval | JOSE AVILA |
| BUILDING-Rough-Frame | 11/13/2024 | Conditional Approval | JOSE AVILA |
| ELECTRICAL-Rough | 11/13/2024 | Approved | JOSE AVILA |
| PLUMBING-Rough | 11/13/2024 | Approved | JOSE AVILA |
| Insulation | 11/18/2024 | Approved | JOSE AVILA |
| Shower Pan | 11/18/2024 | Approved | JOSE AVILA |
| Drywall Nailing | 11/21/2024 | Approved | JOSE AVILA |
| Green Building Rough | 11/21/2024 | Approved | JOSE AVILA |
| BUILDING-Rough-Frame | 4/8/2025 | Approved | JOSE AVILA |
| Footing/Foundation/Slab | 4/8/2025 | Approved | JOSE AVILA |
| PLUMBING-Final | 4/8/2025 | Corrections Issued | JOSE AVILA |
| Verify Sprinkler Sign Off | 4/8/2025 | Approved | JOSE AVILA |
| ELECTRICAL-Final | 4/21/2025 | Partial Approval | JOSE AVILA |
| Final | 4/21/2025 | Corrections Issued | JOSE AVILA |
| Green Building Final | 4/21/2025 | Approved | JOSE AVILA |
| HVAC-Final | 4/21/2025 | Approved | JOSE AVILA |
| PLUMBING-Final | 4/21/2025 | Approved | JOSE AVILA |
| SGSOV-Seismic Gas S/O Valve | 4/21/2025 | SGSOV Not Required | JOSE AVILA |
| Service/Power Release | 4/21/2025 | Approved | JOSE AVILA |
| Smoke Detectors | 4/21/2025 | Approved | JOSE AVILA |
| Final | 5/14/2025 | OK to Issue CofO | JOSE AVILA |