6647 N FAIR AVE 91606

Certificate Information: 6647 N FAIR AVE 91606

Application / Permit
24010-20000-01988
Plan Check / Job No.
B24VN06596
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*ePlan: NEW 2-STORY, DETACHED ACCESSORY DWELLING UNIT
Permit Issued
Issued on 6/28/2024
Issuing Office
Current Status
CofO Issued on 6/5/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/13/2024 APPLICANT
Assigned to Plan Check Engineer 5/23/2024 QUAN NGHIEM
Corrections Issued 5/25/2024 QUAN NGHIEM
Quality Review Completed 5/31/2024 MINYE PAK
Applicant returned to address corrections 6/13/2024 QUAN NGHIEM
Plan Check Approved 6/24/2024 QUAN NGHIEM
Issued 6/28/2024 APPLICANT
CofO in Progress 5/15/2025 JOSE AVILA
Permit Finaled 6/5/2025 RUBEN SALAS
CofO Issued 6/5/2025 RUBEN SALAS
Permit Finaled 6/5/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/6/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 6/6/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 6/7/2024 CARLOS AGUILERA
Sewer availability Cleared 6/8/2024 CARLOS AGUILERA

Contact Information

Contractor Ultimate Green Construction Inc; Lic. No.: 1023605-B       ,
Engineer Moser,, Bradley Charles; Lic. No.: C68803 116 OAKSIDE LN      BUELLTON, CA 93427

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/20/2024 Partial Approval JOSE AVILA
Excavation/Setback/Form/Re-Bar 8/27/2024 Approved DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 9/16/2024 Corrections Issued JOSE AVILA
Deputy Wood Construction 9/17/2024 Conditional Approval DAVID MATSON
Floor/Roof Diaphrgm/Shear Wall 9/18/2024 Partial Approval JOSE AVILA
Deputy Wood Construction 10/25/2024 Conditional Approval JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 10/25/2024 Corrections Issued JOSE AVILA
HVAC-Rough 11/1/2024 Approved JOSE AVILA
Wood Frame 11/1/2024 Not Ready for Inspection JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 11/5/2024 Partial Approval JOSE AVILA
Sewer 11/5/2024 Approved JOSE AVILA
Underground Mechanical 11/5/2024 Partial Approval JOSE AVILA
BUILDING-Rough-Frame 11/13/2024 Conditional Approval JOSE AVILA
ELECTRICAL-Rough 11/13/2024 Approved JOSE AVILA
PLUMBING-Rough 11/13/2024 Approved JOSE AVILA
Insulation 11/18/2024 Approved JOSE AVILA
Shower Pan 11/18/2024 Approved JOSE AVILA
Drywall Nailing 11/21/2024 Approved JOSE AVILA
Green Building Rough 11/21/2024 Approved JOSE AVILA
BUILDING-Rough-Frame 4/8/2025 Approved JOSE AVILA
Footing/Foundation/Slab 4/8/2025 Approved JOSE AVILA
PLUMBING-Final 4/8/2025 Corrections Issued JOSE AVILA
Verify Sprinkler Sign Off 4/8/2025 Approved JOSE AVILA
ELECTRICAL-Final 4/21/2025 Partial Approval JOSE AVILA
Final 4/21/2025 Corrections Issued JOSE AVILA
Green Building Final 4/21/2025 Approved JOSE AVILA
HVAC-Final 4/21/2025 Approved JOSE AVILA
PLUMBING-Final 4/21/2025 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 4/21/2025 SGSOV Not Required JOSE AVILA
Service/Power Release 4/21/2025 Approved JOSE AVILA
Smoke Detectors 4/21/2025 Approved JOSE AVILA
Final 5/14/2025 OK to Issue CofO JOSE AVILA