12508 W HATTERAS ST 91607
Certificate Information: 12508 W HATTERAS ST 91607
- Application / Permit
- 24010-20000-01972
- Plan Check / Job No.
- B24VN06560
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: New 27'-2"x29'detached one-story A.D.U per engineer design (1,200 SF max per Ordinance, LAMC 12.22 A.33 (c)-(d))
- Permit Issued
- Issued on 9/6/2024
- Issuing Office
- Current Status
- CofO Issued on 2/27/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/10/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/15/2024 | AUNG SOE |
| Corrections Issued | 6/3/2024 | AUNG SOE |
| Plan Check Approved | 9/4/2024 | AUNG SOE |
| Issued | 9/6/2024 | APPLICANT |
| CofO in Progress | 2/5/2025 | OGANES TARAKHCHYAN |
| Permit Finaled | 2/27/2025 | RUBEN SALAS |
| Permit Finaled | 2/27/2025 | RUBEN SALAS |
| CofO Issued | 2/27/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 7/24/2024 | KEVIN CHUNG |
| Roof/Waste drainage to street | Cleared | 7/24/2024 | KEVIN CHUNG |
| Eng Process Fee Ord 176,300 | Cleared | 7/25/2024 | KEVIN CHUNG |
| Sewer availability | Cleared | 7/29/2024 | KEVIN CHUNG |
| Construction near power lines | Cleared | 9/3/2024 | RIDWAN HARDY |
| Construction within easement | Cleared | 9/3/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Maalouf,, Sami; Lic. No.: C53210 | 15445 VENTURA BLVD STE 367 SHERMAN OAKS, CA 91403 |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 9/16/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 9/18/2024 | Approved | OGANES TARAKHCHYAN |
| Sewer | 9/24/2024 | Approved | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/9/2024 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 10/15/2024 | Approved | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 10/15/2024 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| HVAC-Rough | 10/30/2024 | Conditional Approval | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 10/30/2024 | Approved | GAREN HAYRAPETYAN |
| Deputy Wood Construction | 10/31/2024 | Conditional Approval | RAUL OLAGI |
| Wood Frame | 10/31/2024 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 11/5/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Insulation | 11/5/2024 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 11/5/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Drywall Nailing | 11/14/2024 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 11/14/2024 | Approved | GAREN HAYRAPETYAN |
| Shower Pan | 11/14/2024 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Final | 12/31/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 1/21/2025 | Partial Approval | OGANES TARAKHCHYAN |
| Green Building Final | 1/21/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Rough | 1/21/2025 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 1/21/2025 | SGSOV Not Required | OGANES TARAKHCHYAN |
| Service/Power Release | 1/21/2025 | Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 1/21/2025 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 2/4/2025 | Approved | OGANES TARAKHCHYAN |
| Final | 2/4/2025 | OK to Issue CofO | OGANES TARAKHCHYAN |
| Green Building Final | 2/4/2025 | Approved | OGANES TARAKHCHYAN |
| Verify Sprinkler Sign Off | 2/4/2025 | Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 2/20/2025 | Approved | OGANES TARAKHCHYAN |