1216 E 56TH ST 90011
Certificate Information: 1216 E 56TH ST 90011
- Application / Permit
- 24010-20000-01969
- Plan Check / Job No.
- B24VN06543
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan: (N) 1 STORY DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c), (d), and (g). WORK PER ENGINEERED DESIGN. 1 OF 2
- Permit Issued
- Issued on 11/21/2024
- Issuing Office
- Current Status
- CofO Issued on 8/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/30/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 6/4/2024 | OMAR GARNICA |
| Corrections Issued | 6/5/2024 | OMAR GARNICA |
| Applicant returned to address corrections | 9/13/2024 | OMAR GARNICA |
| Plan Check Approved | 10/11/2024 | OMAR GARNICA |
| Issued | 11/21/2024 | APPLICANT |
| CofO in Progress | 7/30/2025 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 8/15/2025 | DEROLD HAUFF |
| Permit Finaled | 8/15/2025 | DEROLD HAUFF |
| CofO Issued | 8/15/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/27/2024 | JUSTIN BICOL |
| Community Plan Implem. Overlay | Cleared | 6/27/2024 | JUSTIN BICOL |
| Roof/Waste drainage to street | Cleared | 6/27/2024 | JUSTIN BICOL |
| Eng Process Fee Ord 176,300 | Cleared | 7/15/2024 | JUSTIN BICOL |
| Sewer availability | Cleared | 7/15/2024 | JUSTIN BICOL |
| Community Plan Implem. Overlay | Cleared | 7/16/2024 | DYNL MIRANDA |
| Community Plan Implem. Overlay | Cleared | 8/2/2024 | ANACANY HURTADO |
| Community Plan Implem. Overlay | Cleared | 9/4/2024 | OSCAR CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVE SUITE 201 LONG BEACH, CA 90813 |
Inspector Information
| ALEJANDRO DE ARTOLA, (213) 202-3128 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/12/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 12/18/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 12/18/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 12/23/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 12/23/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Pre-Inspection | 12/23/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Sewer | 12/23/2024 | Partial Approval | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 12/26/2024 | Corrections Issued | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 12/31/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 1/3/2025 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 1/7/2025 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 1/16/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 1/16/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Wood Frame | 1/16/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Insulation | 1/17/2025 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 1/17/2025 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 1/22/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 2/24/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 2/28/2025 | Corrections Issued | MICHAEL LEWIS |
| PLUMBING-Rough | 2/28/2025 | Approved | MICHAEL LEWIS |
| BUILDING-Rough-Frame | 3/7/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 3/7/2025 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 3/7/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 3/7/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 3/12/2025 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 3/12/2025 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 3/12/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 3/19/2025 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 3/19/2025 | Partial Approval | ALEJANDRO DE ARTOLA |
| Service/Power Release | 5/30/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 5/30/2025 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 7/17/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 7/17/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 7/17/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 7/17/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 7/17/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 7/17/2025 | SGSOV Not Required | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 7/17/2025 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 7/22/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Final | 7/22/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 7/22/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Final | 7/22/2025 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 7/22/2025 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 7/22/2025 | Approved | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 7/24/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 7/24/2025 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Final | 7/24/2025 | Approved | ALEJANDRO DE ARTOLA |
| Final | 7/29/2025 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| Green Building Final | 7/29/2025 | Approved | ALEJANDRO DE ARTOLA |