1216 E 56TH ST 90011

Certificate Information: 1216 E 56TH ST 90011

Application / Permit
24010-20000-01969
Plan Check / Job No.
B24VN06543
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
eplan: (N) 1 STORY DETACHED ACCESSORY DWELLING UNIT PER GCS 65852.2(e)(1)(B) and LAMC 12.22 A.33(c), (d), and (g). WORK PER ENGINEERED DESIGN. 1 OF 2
Permit Issued
Issued on 11/21/2024
Issuing Office
Current Status
CofO Issued on 8/15/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/30/2024 APPLICANT
Assigned to Plan Check Engineer 6/4/2024 OMAR GARNICA
Corrections Issued 6/5/2024 OMAR GARNICA
Applicant returned to address corrections 9/13/2024 OMAR GARNICA
Plan Check Approved 10/11/2024 OMAR GARNICA
Issued 11/21/2024 APPLICANT
CofO in Progress 7/30/2025 ALEJANDRO DE ARTOLA
Permit Finaled 8/15/2025 DEROLD HAUFF
Permit Finaled 8/15/2025 DEROLD HAUFF
CofO Issued 8/15/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/27/2024 JUSTIN BICOL
Community Plan Implem. Overlay Cleared 6/27/2024 JUSTIN BICOL
Roof/Waste drainage to street Cleared 6/27/2024 JUSTIN BICOL
Eng Process Fee Ord 176,300 Cleared 7/15/2024 JUSTIN BICOL
Sewer availability Cleared 7/15/2024 JUSTIN BICOL
Community Plan Implem. Overlay Cleared 7/16/2024 DYNL MIRANDA
Community Plan Implem. Overlay Cleared 8/2/2024 ANACANY HURTADO
Community Plan Implem. Overlay Cleared 9/4/2024 OSCAR CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Castillo,, Margarito; Lic. No.: S4808 1205 PINE AVE   SUITE 201    LONG BEACH, CA 90813

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/12/2024 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 12/18/2024 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 12/18/2024 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 12/23/2024 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Rough 12/23/2024 Corrections Issued ALEJANDRO DE ARTOLA
Pre-Inspection 12/23/2024 Corrections Issued ALEJANDRO DE ARTOLA
Sewer 12/23/2024 Partial Approval ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 12/26/2024 Corrections Issued JOHN QUINTANILLA
Footing/Foundation/Slab 12/31/2024 Corrections Issued ALEJANDRO DE ARTOLA
Excavation/Setback/Form/Re-Bar 1/3/2025 Corrections Issued ENRIQUE MIRELES
Footing/Foundation/Slab 1/7/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 1/16/2025 Partial Approval ALEJANDRO DE ARTOLA
Underground Mechanical 1/16/2025 Corrections Issued ALEJANDRO DE ARTOLA
Wood Frame 1/16/2025 Partial Approval ALEJANDRO DE ARTOLA
Insulation 1/17/2025 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 1/17/2025 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 1/22/2025 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 2/7/2025 Corrections Issued ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 2/24/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 2/28/2025 Corrections Issued MICHAEL LEWIS
PLUMBING-Rough 2/28/2025 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 3/7/2025 Corrections Issued ALEJANDRO DE ARTOLA
ELECTRICAL-Rough 3/7/2025 Approved ALEJANDRO DE ARTOLA
Green Building Rough 3/7/2025 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 3/7/2025 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 3/12/2025 Approved ALEJANDRO DE ARTOLA
HVAC-Rough 3/12/2025 Approved ALEJANDRO DE ARTOLA
Insulation 3/12/2025 Corrections Issued ALEJANDRO DE ARTOLA
Drywall Nailing 3/19/2025 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 3/19/2025 Partial Approval ALEJANDRO DE ARTOLA
Service/Power Release 5/30/2025 Corrections Issued ALEJANDRO DE ARTOLA
Underground Mechanical 5/30/2025 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 7/17/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 7/17/2025 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 7/17/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 7/17/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 7/17/2025 Corrections Issued ALEJANDRO DE ARTOLA
SGSOV-Seismic Gas S/O Valve 7/17/2025 SGSOV Not Required ALEJANDRO DE ARTOLA
Smoke Detectors 7/17/2025 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 7/22/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 7/22/2025 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 7/22/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 7/22/2025 Approved ALEJANDRO DE ARTOLA
PLUMBING-Final 7/22/2025 Approved ALEJANDRO DE ARTOLA
Service/Power Release 7/22/2025 Approved ALEJANDRO DE ARTOLA
ELECTRICAL-Final 7/24/2025 Approved ALEJANDRO DE ARTOLA
Final 7/24/2025 Corrections Issued ALEJANDRO DE ARTOLA
Green Building Final 7/24/2025 Approved ALEJANDRO DE ARTOLA
Final 7/29/2025 OK to Issue CofO ALEJANDRO DE ARTOLA
Green Building Final 7/29/2025 Approved ALEJANDRO DE ARTOLA