4639 S PURDUE AVE 90230
Certificate Information: 4639 S PURDUE AVE 90230
- Application / Permit
- 24010-20000-01921
- Plan Check / Job No.
- B24VN06339
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 53' 8" x 25' 2" two stories Single Family Dwelling per SB9 Two-Unit Development Ca Govt Code 65852.21. NFPA 13D sprinkler required. All work done per engineer.
- Permit Issued
- Issued on 5/28/2025
- Issuing Office
- Valley
- Current Status
- Issued on 5/28/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 5/7/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/23/2024 | NAREG ATARIAN |
| Corrections Issued | 5/31/2024 | NAREG ATARIAN |
| Quality Review Completed | 6/4/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 6/4/2024 | APPLICANT |
| Applicant returned to address corrections | 6/7/2024 | NAREG ATARIAN |
| Applicant returned to address corrections | 1/27/2025 | NAREG ATARIAN |
| Applicant returned to address corrections | 3/12/2025 | NAREG ATARIAN |
| Applicant returned to address corrections | 3/28/2025 | NAREG ATARIAN |
| Plan Check Approved | 5/15/2025 | NAREG ATARIAN |
| Issued | 5/28/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/11/2024 | KIMBERLY HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/12/2024 | DIANA RENTERIA |
| Roof/Waste drainage to street | Cleared | 12/12/2024 | DIANA RENTERIA |
| Sewer availability | Cleared | 12/12/2024 | DIANA RENTERIA |
| Senate Bill 9 | Cleared | 2/4/2025 | ALEX VELA |
| Specific Plan | Cleared | 3/17/2025 | RICHARD WOO |
| Construction near power lines | Cleared | 4/16/2025 | TINA MIRANDA |
| Hydrant and Access approval | Cleared | 4/23/2025 | RUEL COLE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nohroodi,, Nader Gholi; Lic. No.: C36971 | 7389 PERIGORD CT TUJUNGA, CA 91042 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/12/2025 | Partial Approval | RUBEN RIVAS |
| Excavation/Setback/Form/Re-Bar | 6/23/2025 | Approved | MICHAEL ALLEN |
| Deck | 7/11/2025 | Not Ready for Inspection | JAYLIN GRAVITTE |
| Floor/Roof Diaphrgm/Shear Wall | 10/22/2025 | Approved | WILBER ROSALES |
| BUILDING-Rough-Frame | 11/5/2025 | Corrections Issued | WILBER ROSALES |
| ELECTRICAL-Rough | 11/5/2025 | Corrections Issued | WILBER ROSALES |
| Green Building Rough | 11/5/2025 | Not Ready for Inspection | WILBER ROSALES |
| HVAC-Rough | 11/5/2025 | Approved | WILBER ROSALES |
| PLUMBING-Rough | 11/5/2025 | Approved | WILBER ROSALES |
| Verify Sprinkler Sign Off | 11/5/2025 | Approved | WILBER ROSALES |
| BUILDING-Rough-Frame | 12/2/2025 | Not Ready for Inspection | RUBEN RIVAS |
| ELECTRICAL-Rough | 12/2/2025 | Corrections Issued | RUBEN RIVAS |
| Green Building Rough | 12/2/2025 | Not Ready for Inspection | RUBEN RIVAS |
| Interior/Exterior Lathing | 12/2/2025 | Partial Approval | RUBEN RIVAS |
| MERV13>=Rough | 12/2/2025 | Partial Approval | RUBEN RIVAS |
| BUILDING-Rough-Frame | 12/10/2025 | Not Ready for Inspection | WILBER ROSALES |
| ELECTRICAL-Rough | 12/10/2025 | Approved | WILBER ROSALES |
| Green Building Rough | 12/10/2025 | Approved | WILBER ROSALES |
| MERV13>=Rough | 12/10/2025 | Approved | WILBER ROSALES |
| Insulation | 1/26/2026 | Approved | ANTHONY EGSON |
| Drywall Nailing | 1/30/2026 | Approved | DAKOTA LOW |
| Shower Pan | 2/4/2026 | Corrections Issued | DAKOTA LOW |
| Shower Pan | 2/6/2026 | Approved | DAKOTA LOW |
| Interior/Exterior Lathing | 2/13/2026 | Corrections Issued | DAKOTA LOW |
| Pre-Inspection | 3/3/2026 | Approved | DAKOTA LOW |
| Underground Mechanical | 4/21/2026 | Partial Approval | DAKOTA LOW |