16024 W TUPPER ST 91343

Certificate Information: 16024 W TUPPER ST 91343

Application / Permit
24010-20000-01917
Plan Check / Job No.
B24VN06317
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New two story detached ADU
Permit Issued
Issued on 1/31/2025
Issuing Office
Current Status
Issued on 1/31/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 5/29/2024 APPLICANT
Assigned to Plan Check Engineer 6/13/2024 JOE VO
Corrections Issued 6/28/2024 JOE VO
Quality Review Completed 7/2/2024 GARO TELMI
Plan Check Approved 1/5/2025 JOE VO
Issued 1/31/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 8/1/2024 CARLOS RAMIREZ
Roof/Waste drainage to street Cleared 8/1/2024 CARLOS RAMIREZ
Hydrant and Access approval Cleared 10/9/2024 JERRY KAO
Construction near power lines Cleared 11/8/2024 RIDWAN HARDY
Grading Pre-Inspection Cleared 12/30/2024 JOE VO
Eng Process Fee Ord 176,300 Cleared 1/6/2025 CARLOS RAMIREZ
Sewer availability Cleared 1/27/2025 CARLOS RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Samvelyan,, Taron; Lic. No.: C93740 1800 N VERDUGO RD APT 204      GLENDALE, CA 91208

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 9/12/2025 Partial Approval GAREN HAYRAPETYAN
Footing/Foundation/Slab 9/18/2025 Approved GAREN HAYRAPETYAN
Floor/Roof Diaphrgm/Shear Wall 10/6/2025 Partial Approval OGANES TARAKHCHYAN
Deputy Wood Construction 10/29/2025 Conditional Approval JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 11/5/2025 Not Ready for Inspection WAYNE REGESTER
Floor/Roof Diaphrgm/Shear Wall 11/7/2025 Approved WAYNE REGESTER
HVAC-Rough 11/14/2025 Approved GAREN HAYRAPETYAN
PLUMBING-Rough 11/14/2025 Approved GAREN HAYRAPETYAN
Special/Order Compliance 11/14/2025 Approved GAREN HAYRAPETYAN
BUILDING-Rough-Frame 12/1/2025 Corrections Issued GAREN HAYRAPETYAN
ELECTRICAL-Rough 12/1/2025 Approved GAREN HAYRAPETYAN
Green Building Rough 12/1/2025 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 12/1/2025 Partial Approval GAREN HAYRAPETYAN
Verify Sprinkler Sign Off 12/1/2025 Not Ready for Inspection GAREN HAYRAPETYAN
BUILDING-Rough-Frame 12/12/2025 Approved GAREN HAYRAPETYAN
Shower Pan 12/12/2025 Approved GAREN HAYRAPETYAN
Verify Sprinkler Sign Off 12/12/2025 Approved GAREN HAYRAPETYAN
Insulation 12/30/2025 Corrections Issued MICHAEL CORTEZ
Special/Order Compliance 1/6/2026 Corrections Issued GAREN HAYRAPETYAN
Special/Order Compliance 1/7/2026 Corrections Issued GAREN HAYRAPETYAN
Drywall Nailing 3/31/2026 Approved KIRK SANDERS
Insulation 3/31/2026 Approved KIRK SANDERS
Interior/Exterior Lathing 3/31/2026 Approved KIRK SANDERS
Underground Mechanical 5/27/2026 Partial Approval JOSE AVILA