4541 N DENSMORE AVE 91436

Certificate Information: 4541 N DENSMORE AVE 91436

Application / Permit
24010-20000-01897
Plan Check / Job No.
B24VN06252
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
REMOVE ALL EXCEPT FOR A PORTION OF FRONT WALL OF (E) STORAGE & ERECT A 20' x 37'-10" ONE STORY DET. ACCESSORY DWELLING UNIT [PER CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)]; NFPA-13D THRU OUT
Permit Issued
Issued on 8/19/2024
Issuing Office
Valley
Current Status
CofO Issued on 4/11/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/6/2024 APPLICANT
Assigned to Plan Check Engineer 5/9/2024 SEAN SHAHMIRI
Corrections Issued 5/13/2024 SEAN SHAHMIRI
Quality Review Completed 5/17/2024 STEVEN KIM
Building Plans Picked Up 5/17/2024 APPLICANT
Applicant returned to address corrections 8/8/2024 RAPHAEL ROSAS
Applicant returned to address corrections 8/19/2024 SEAN SHAHMIRI
Plan Check Approved 8/19/2024 SEAN SHAHMIRI
Issued 8/19/2024 APPLICANT
CofO in Progress 3/3/2026 MORRIS JACKSON
Permit Finaled 4/11/2026 MICHAEL PELHAM
CofO Issued 4/11/2026 MICHAEL PELHAM
Permit Finaled 4/11/2026 MICHAEL PELHAM

Permit Application Clearance Information

Low Impact Development (LID) Cleared 5/22/2024 SARAH YOUSSEF
Address approval Cleared 5/29/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 5/29/2024 BIAINA HARITUNIAN
Sewer availability Cleared 5/29/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 5/31/2024 BIAINA HARITUNIAN
Public Works-Highway Ded. Cleared 7/18/2024 LEE GUILBEAUX
Hydrant and Access approval Cleared 7/30/2024 GILBERT URREA

Contact Information

Contractor Owner-Builder       ,
Engineer Nazari,, Arthur; Lic. No.: C53497 23300 POMPANO STREET      MALIBU, CA 90265

Inspector Information

THOMAS FINNILA, (818) 774-4324 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/11/2024 Not Ready for Inspection THOMAS FINNILA
Underground Mechanical 10/11/2024 Corrections Issued THOMAS FINNILA
Excavation/Setback/Form/Re-Bar 10/25/2024 Conditional Approval THOMAS FINNILA
Footing/Foundation/Slab 10/25/2024 Conditional Approval THOMAS FINNILA
Footing/Foundation/Slab 11/4/2024 Corrections Issued THOMAS FINNILA
Footing/Foundation/Slab 11/12/2024 Approved THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 1/23/2025 Partial Approval JEFFREY HARTLINE
Floor/Roof Diaphrgm/Shear Wall 1/27/2025 Not Ready for Inspection THOMAS FINNILA
PLUMBING-Rough 2/7/2025 Approved THOMAS FINNILA
Deputy Wood Construction 2/24/2025 Conditional Approval THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 2/26/2025 Not Ready for Inspection THOMAS FINNILA
HVAC-Rough 2/26/2025 Approved THOMAS FINNILA
Shower Pan 2/26/2025 Approved THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 3/5/2025 Not Ready for Inspection THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 3/10/2025 Corrections Issued THOMAS FINNILA
ELECTRICAL-Rough 3/13/2025 Approved THOMAS FINNILA
Floor/Roof Diaphrgm/Shear Wall 3/13/2025 Partial Approval THOMAS FINNILA
BUILDING-Rough-Frame 3/17/2025 Conditional Approval THOMAS FINNILA
Green Building Rough 3/17/2025 Approved THOMAS FINNILA
Interior/Exterior Lathing 3/24/2025 Not Ready for Inspection THOMAS FINNILA
Insulation 4/1/2025 Approved JOHN COLEMAN
Interior/Exterior Lathing 4/1/2025 Partial Approval JOHN COLEMAN
Drywall Nailing 4/10/2025 Approved JOHN COLEMAN
Interior/Exterior Lathing 4/10/2025 Approved JOHN COLEMAN
Drywall Nailing 4/14/2025 Approved JOHN COLEMAN
ELECTRICAL-Final 12/9/2025 Approved SEAN WIRCH
HVAC-Final 12/9/2025 Approved SEAN WIRCH
BUILDING-Rough-Frame 1/12/2026 Approved SEAN WIRCH
SGSOV-Seismic Gas S/O Valve 1/12/2026 SGSOV Not Ready SEAN WIRCH
Final 2/17/2026 OK to Issue CofO MORRIS JACKSON
Green Building Final 2/17/2026 Approved MORRIS JACKSON
SGSOV-Seismic Gas S/O Valve 2/17/2026 SGSOV Approved MORRIS JACKSON
Smoke Detectors 2/17/2026 Approved MORRIS JACKSON