5004-5006 N ENFIELD AVE 91316
Certificate Information: 5004-5006 N ENFIELD AVE 91316
- Application / Permit
- 24010-20000-01843
- Plan Check / Job No.
- B24VN06084
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE ENTIRE (E) SFD EXCEPT FOR 3'-4" WALL AND BUILD NEW SINGLE FAMILY DWELLING (3837 SQFT) W/ATTACHED ADU (839 SQFT) PER LAMC 12.22 A.33(c)(e) AND ATTACHED 2-CAR GARAGE (397 SQFT) AND FRONT COVERED PORCH (29 SQFT) W/NFPA 13D SPRINKLERS THROUGHOUT.
- Permit Issued
- Issued on 7/12/2024
- Issuing Office
- Current Status
- CofO Issued on 8/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/2/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/9/2024 | PETER MOSESIAN |
| Corrections Issued | 5/12/2024 | PETER MOSESIAN |
| Quality Review Completed | 5/14/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 5/14/2024 | APPLICANT |
| Plan Check Approved | 7/10/2024 | PETER MOSESIAN |
| Issued | 7/12/2024 | APPLICANT |
| CofO in Progress | 8/5/2025 | JOHN KIDWELL |
| Permit Finaled | 8/21/2025 | JOHN JANSON |
| CofO Issued | 8/21/2025 | JOHN JANSON |
| Permit Finaled | 8/21/2025 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 5/24/2024 | TAL SHEMEN |
| Roof/Waste drainage to street | Cleared | 5/24/2024 | TAL SHEMEN |
| Miscellaneous | Cleared | 6/3/2024 | ALEX VELA |
| Eng Process Fee Ord 176,300 | Cleared | 6/21/2024 | TAL SHEMEN |
| Sewer availability | Cleared | 6/21/2024 | TAL SHEMEN |
| Hydrant and Access approval | Cleared | 6/28/2024 | GILBERT URREA |
Contact Information
| Contractor | Sunset Built Inc; Lic. No.: 1005054-B | 8383 WILSHIRE BLVD #800 BEVERLY HILLS, CA 90211 |
| Engineer | Nazari,, Arthur; Lic. No.: C53497 | 23300 POMPANO STREET MALIBU, CA 90265 |
| Landscape Architect | Alaniz,, Arthur Louis; Lic. No.: LA5554 | 26 CLEAR VISTA ROLLING HILLS ESTATES, CA 90274 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 8/14/2024 | Partial Approval | JOHN KIDWELL |
| Footing/Foundation/Slab | 8/14/2024 | Partial Approval | JOHN KIDWELL |
| PLUMBING-Rough | 8/19/2024 | Partial Approval | JOHN KIDWELL |
| Underground Mechanical | 8/19/2024 | Partial Approval | JOHN KIDWELL |
| Deputy Other (see comments) | 8/29/2024 | Partial Approval | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 8/29/2024 | Approved | JOHN KIDWELL |
| Footing/Foundation/Slab | 8/29/2024 | Approved | JOHN KIDWELL |
| Deputy Reinf. Concrete | 9/3/2024 | Conditional Approval | ARUTYUN MADATYAN |
| Deputy Wood Construction | 9/18/2024 | Approved | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 9/18/2024 | Partial Approval | JOHN KIDWELL |
| Deputy Wood Construction | 10/10/2024 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2024 | Corrections Issued | MORRIS JACKSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2024 | Partial Approval | JOHN KIDWELL |
| PLUMBING-Rough | 12/5/2024 | Approved | JOHN COLEMAN |
| Shower Pan | 12/6/2024 | Approved | JOHN KIDWELL |
| ELECTRICAL-Rough | 12/19/2024 | Approved | JOHN KIDWELL |
| HVAC-Rough | 12/19/2024 | Approved | JOHN KIDWELL |
| BUILDING-Rough-Frame | 1/23/2025 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2025 | Partial Approval | JOHN KIDWELL |
| Green Building Rough | 1/23/2025 | Not Ready for Inspection | JOHN KIDWELL |
| BUILDING-Rough-Frame | 2/3/2025 | Approved | JOHN KIDWELL |
| Green Building Rough | 2/3/2025 | Approved | JOHN KIDWELL |
| Drywall Nailing | 2/14/2025 | Approved | JOHN KIDWELL |
| Insulation | 2/14/2025 | Approved | JOHN KIDWELL |
| Interior/Exterior Lathing | 2/14/2025 | Partial Approval | JOHN KIDWELL |
| Interior/Exterior Lathing | 2/21/2025 | Approved | MORRIS JACKSON |
| ELECTRICAL-Final | 6/13/2025 | Approved | JOHN KIDWELL |
| HVAC-Final | 6/13/2025 | Conditional Approval | JOHN KIDWELL |
| Service/Power Release | 6/24/2025 | Partial Inspection | JOHN KIDWELL |
| Service/Power Release | 7/2/2025 | Approved | JOHN KIDWELL |
| Final | 7/29/2025 | Not Ready for Inspection | JOHN KIDWELL |
| Green Building Final | 7/29/2025 | Approved | JOHN KIDWELL |
| HVAC-Final | 7/29/2025 | Approved | JOHN KIDWELL |
| PLUMBING-Final | 7/29/2025 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 7/29/2025 | SGSOV Approved | JOHN KIDWELL |
| Smoke Detectors | 7/29/2025 | Approved | JOHN KIDWELL |
| Final | 8/1/2025 | OK to Issue CofO | JOHN KIDWELL |