14756 1/2 W LEMAY ST 91405
Certificate Information: 14756 1/2 W LEMAY ST 91405
- Application / Permit
- 24010-20000-01842
- Plan Check / Job No.
- B24VN06077
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN NEW 1,121 SQ. FT. OF DETACHED ACCESSORY DWELLING UNIT WITH NFPA 13-D FIRE SPRINKLERS
- Permit Issued
- Issued on 10/16/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/8/2024 | NEHEMIAS RAMOS |
| Corrections Issued | 5/9/2024 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 5/30/2024 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 6/20/2024 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 7/5/2024 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 7/15/2024 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 9/27/2024 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 10/2/2024 | SUNMIN LEE |
| Applicant returned to address corrections | 10/3/2024 | TSE MING HUANG |
| Plan Check Approved | 10/4/2024 | TSE MING HUANG |
| Plan Check Approved | 10/7/2024 | TSE MING HUANG |
| Issued | 10/16/2024 | APPLICANT |
| CofO in Progress | 4/24/2025 | RYAN SALAZAR |
| Permit Finaled | 4/25/2025 | RUBEN SALAS |
| CofO Issued | 4/25/2025 | RUBEN SALAS |
| Permit Finaled | 4/25/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 9/7/2024 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 9/7/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 9/12/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 9/12/2024 | RYAN CASTRO |
| Construction near power lines | Cleared | 9/25/2024 | RIDWAN HARDY |
| Hydrant and Access approval | Cleared | 9/30/2024 | KURT CORRAL |
Contact Information
| Architect | Hezghiayan,, Albert; Lic. No.: NA34337 | , |
| Contractor | Owner-Builder | , |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/30/2024 | Partial Approval | RYAN SALAZAR |
| Excavation/Setback/Form/Re-Bar | 11/12/2024 | Approved | RYAN SALAZAR |
| Drywall Nailing | 12/9/2024 | Not Ready for Inspection | RYAN SALAZAR |
| Floor/Roof Diaphrgm/Shear Wall | 12/9/2024 | Partial Approval | RYAN SALAZAR |
| ELECTRICAL-Rough | 12/30/2024 | Approved | RYAN SALAZAR |
| HVAC-Rough | 12/30/2024 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 12/30/2024 | Partial Approval | RYAN SALAZAR |
| PLUMBING-Rough | 12/30/2024 | Partial Approval | RYAN SALAZAR |
| PLUMBING-Rough | 1/21/2025 | Approved | GAREN HAYRAPETYAN |
| Insulation | 1/29/2025 | Corrections Issued | RYAN SALAZAR |
| Drywall Nailing | 2/4/2025 | Approved | CHRISTOPHER ROJAS |
| Final | 2/4/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Insulation | 2/4/2025 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 2/18/2025 | Approved | RYAN SALAZAR |
| Green Building Rough | 2/18/2025 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 2/18/2025 | Approved | RYAN SALAZAR |
| Shower Pan | 2/18/2025 | Approved | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 2/18/2025 | Approved | RYAN SALAZAR |
| Final | 4/21/2025 | Corrections Issued | RYAN SALAZAR |
| Footing/Foundation/Slab | 4/21/2025 | Approved | RYAN SALAZAR |
| Green Building Final | 4/21/2025 | Not Ready for Inspection | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 4/21/2025 | SGSOV Not Required | RYAN SALAZAR |
| Service/Power Release | 4/21/2025 | Approved | RYAN SALAZAR |
| Smoke Detectors | 4/21/2025 | Approved | RYAN SALAZAR |
| Final | 4/25/2025 | OK to Issue CofO | RYAN SALAZAR |
| Green Building Final | 4/25/2025 | Approved | RYAN SALAZAR |