9151 N HAZELTINE AVE 91402

Certificate Information: 9151 N HAZELTINE AVE 91402

Application / Permit
24010-20000-01838
Plan Check / Job No.
B24VN06071
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 36'8" X 30' DETACHED ONE STORY ACCESSORY DWELLING UNIT AS PER CA Govt. Code 65852.2(e)(1)(C), NFPA-13D FIRE SPRINKLERS REQUIRED THROUGHOUT, ALL WORK PER WFPP
Permit Issued
Issued on 1/14/2025
Issuing Office
Current Status
CofO Issued on 5/14/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/3/2024 APPLICANT
Assigned to Plan Check Engineer 5/16/2024 RARES BODEA
Corrections Issued 5/23/2024 RARES BODEA
Quality Review Completed 5/23/2024 STEVEN KIM
Building Plans Picked Up 5/24/2024 APPLICANT
Applicant returned to address corrections 12/17/2024 RARES BODEA
Plan Check Approved 1/14/2025 RARES BODEA
Issued 1/14/2025 APPLICANT
CofO in Progress 5/4/2026 JOSE AVILA
Permit Finaled 5/14/2026 RUBEN SALAS
CofO Issued 5/14/2026 RUBEN SALAS
Permit Finaled 5/14/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/3/2024 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 6/3/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 6/3/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 7/16/2024 LEE GUILBEAUX
Hydrant and Access approval Cleared 7/16/2024 JOHN CONNEALLY
Private sewage disp. approval Cleared 12/3/2024 MICHAEL TEMPLE

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/3/2025 Partial Approval JENNIFER RABUCHIN
Sewer 4/3/2025 Partial Approval JENNIFER RABUCHIN
Footing/Foundation/Slab 4/15/2025 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 5/19/2025 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 5/19/2025 Not Ready for Inspection JENNIFER RABUCHIN
Drywall Nailing 6/4/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
Green Building Rough 6/4/2025 Not Ready for Inspection NICHOLAS TROWBRIDGE
HVAC-Rough 6/4/2025 Approved NICHOLAS TROWBRIDGE
BUILDING-Rough-Frame 6/10/2025 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 6/10/2025 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 6/10/2025 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 6/10/2025 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 6/10/2025 Corrections Issued JENNIFER RABUCHIN
Verify Sprinkler Sign Off 6/10/2025 Not Ready for Inspection JENNIFER RABUCHIN
BUILDING-Rough-Frame 6/24/2025 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 6/24/2025 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 6/24/2025 Partial Approval JENNIFER RABUCHIN
Verify Sprinkler Sign Off 6/24/2025 Partial Approval JENNIFER RABUCHIN
Gas Test 7/2/2025 Approved LOUIS ESCOTO
Insulation 7/2/2025 Approved LOUIS ESCOTO
Drywall Nailing 7/9/2025 Approved JENNIFER RABUCHIN
Shower Pan 8/1/2025 Approved JENNIFER RABUCHIN
Shower Pan 8/13/2025 Partial Approval KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 3/9/2026 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 3/9/2026 Corrections Issued JENNIFER RABUCHIN
Final 3/9/2026 Corrections Issued JENNIFER RABUCHIN
Green Building Final 3/9/2026 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Final 3/9/2026 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 3/9/2026 SGSOV Approved JENNIFER RABUCHIN
Service/Power Release 3/9/2026 Not Ready for Inspection JENNIFER RABUCHIN
Smoke Detectors 3/9/2026 Approved JENNIFER RABUCHIN
Verify Sprinkler Sign Off 3/9/2026 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 4/3/2026 Approved JENNIFER RABUCHIN
Final 4/3/2026 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 4/3/2026 Approved JENNIFER RABUCHIN
HVAC-Final 4/3/2026 Approved JENNIFER RABUCHIN
PLUMBING-Final 4/3/2026 Approved JENNIFER RABUCHIN
Service/Power Release 4/3/2026 Not Ready for Inspection JENNIFER RABUCHIN
Final 5/4/2026 Not Ready for Inspection JOSE AVILA
Service/Power Release 5/4/2026 Approved JOSE AVILA