10630-10632 N STANWIN AVE 91345

Certificate Information: 10630-10632 N STANWIN AVE 91345

Application / Permit
24010-20000-01826
Plan Check / Job No.
B23VN18077
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Eplan Convert attached Garage with addition to ADU per Ordinance
Permit Issued
Issued on 9/17/2024
Issuing Office
Current Status
CofO Issued on 4/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/14/2024 APPLICANT
Assigned to Plan Check Engineer 5/20/2024 HERNAN ARREOLA
Corrections Issued 5/20/2024 HERNAN ARREOLA
Applicant returned to address corrections 7/10/2024 LUKE GONZALES
Plan Check Approved 8/21/2024 LUKE GONZALES
Issued 9/17/2024 APPLICANT
CofO in Progress 3/28/2025 JENNIFER RABUCHIN
Permit Finaled 4/8/2025 RUBEN SALAS
CofO Issued 4/8/2025 RUBEN SALAS
Permit Finaled 4/8/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/13/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 7/13/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/30/2024 CARLOS AGUILERA
Sewer availability Cleared 7/30/2024 CARLOS AGUILERA

Contact Information

Contractor Caf Constitutions Inc; Lic. No.: 1087305-B       ,
Contractor Caf Constructions Inc; Lic. No.: 1087305-B       ,
Engineer Wu,, Shu; Lic. No.: C90391 136 LOST HILLS      IRVINE, CA 92618
Engineer Wu,, Shu; Lic. No.: NA90391       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 11/8/2024 Approved JENNIFER RABUCHIN
Footing/Foundation/Slab 11/8/2024 Approved JENNIFER RABUCHIN
METHANE-Barrier 11/8/2024 Approved JENNIFER RABUCHIN
METHANE-Subgrade 11/8/2024 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 12/12/2024 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 12/12/2024 Corrections Issued JENNIFER RABUCHIN
HVAC-Rough 12/12/2024 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 12/12/2024 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 12/20/2024 Approved ROBERT GOLD
ELECTRICAL-Rough 12/20/2024 Approved ROBERT GOLD
Green Building Rough 12/20/2024 Approved ROBERT GOLD
HVAC-Rough 12/20/2024 Approved ROBERT GOLD
MERV13>=Rough 12/20/2024 Approved ROBERT GOLD
PLUMBING-Rough 12/20/2024 Approved ROBERT GOLD
Insulation 12/26/2024 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 12/26/2024 Partial Approval JENNIFER RABUCHIN
Insulation 12/27/2024 Approved JENNIFER RABUCHIN
Order to Comply 12/27/2024 Not Required JENNIFER RABUCHIN
Drywall Nailing 12/31/2024 Approved MICHAEL CORTEZ
Final 3/14/2025 Corrections Issued JENNIFER RABUCHIN
Green Building Final 3/14/2025 Corrections Issued JENNIFER RABUCHIN
MERV13>=Final 3/14/2025 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 3/14/2025 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 3/14/2025 Approved JENNIFER RABUCHIN
Final 3/18/2025 Not Ready for Inspection JENNIFER RABUCHIN
Green Building Final 3/18/2025 Conditional Approval JENNIFER RABUCHIN
ELECTRICAL-Final 3/28/2025 Approved JENNIFER RABUCHIN
Final 3/28/2025 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 3/28/2025 Approved JENNIFER RABUCHIN
HVAC-Final 3/28/2025 Approved JENNIFER RABUCHIN
PLUMBING-Final 3/28/2025 Approved JENNIFER RABUCHIN