12977 1/2 W CORCORAN PL 91340
Certificate Information: 12977 1/2 W CORCORAN PL 91340
- Application / Permit
- 24010-20000-01825
- Plan Check / Job No.
- B24VN06034
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- *EPLAN* NEW 35'-8" X 24' TWO STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 11/7/2024
- Issuing Office
- Current Status
- CofO Issued on 1/28/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/3/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/9/2024 | SELLA BENYAMIN |
| Corrections Issued | 5/14/2024 | SELLA BENYAMIN |
| Quality Review Completed | 5/30/2024 | STEVEN KIM |
| Plan Check Approved | 10/31/2024 | SELLA BENYAMIN |
| Issued | 11/7/2024 | APPLICANT |
| CofO in Progress | 12/18/2025 | MICHEL ABAJAN |
| CofO in Progress | 1/5/2026 | MICHEL ABAJAN |
| No Progress | 1/5/2026 | MICHEL ABAJAN |
| CofO in Progress | 1/5/2026 | MICHEL ABAJAN |
| No Progress | 1/23/2026 | RAUL OLAGI |
| CofO in Progress | 1/23/2026 | RAUL OLAGI |
| CofO in Progress | 1/27/2026 | RAUL OLAGI |
| CofO in Progress | 1/27/2026 | RAUL OLAGI |
| Permit Finaled | 1/28/2026 | RUBEN SALAS |
| CofO Issued | 1/28/2026 | RUBEN SALAS |
| Permit Finaled | 1/28/2026 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/16/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 5/16/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/20/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 5/20/2024 | BIAINA HARITUNIAN |
| Construction near power lines | Cleared | 9/25/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rahman,, Moksudur; Lic. No.: C69263 | 6572 SHEFFIELD CHINO, CA 91710 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/27/2025 | Partial Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 4/16/2025 | Partial Approval | MICHEL ABAJAN |
| Sewer | 4/16/2025 | Approved | MICHEL ABAJAN |
| Excavation/Setback/Form/Re-Bar | 4/29/2025 | Approved | MICHEL ABAJAN |
| Footing/Foundation/Slab | 4/29/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 4/29/2025 | Partial Approval | MICHEL ABAJAN |
| Underground Mechanical | 4/29/2025 | Partial Approval | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 6/11/2025 | Corrections Issued | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/11/2025 | Partial Approval | MICHEL ABAJAN |
| Green Building Rough | 6/11/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| PLUMBING-Rough | 6/11/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| Underground Mechanical | 6/11/2025 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 6/11/2025 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 6/20/2025 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 6/20/2025 | Approved | MICHEL ABAJAN |
| Green Building Rough | 6/20/2025 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 6/20/2025 | Corrections Issued | MICHEL ABAJAN |
| PLUMBING-Rough | 6/20/2025 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 6/25/2025 | Approved | MICHEL ABAJAN |
| Insulation | 6/25/2025 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 6/25/2025 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 6/27/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| Drywall Nailing | 7/2/2025 | Approved | LOUIS ESCOTO |
| Shower Pan | 7/2/2025 | Corrections Issued | LOUIS ESCOTO |
| Shower Pan | 7/10/2025 | Approved | LOUIS ESCOTO |
| ELECTRICAL-Final | 10/10/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| Final | 10/10/2025 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 10/10/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| HVAC-Final | 10/10/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 10/10/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 10/10/2025 | SGSOV Not Required | MICHEL ABAJAN |
| Service/Power Release | 10/10/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 10/10/2025 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 11/25/2025 | Approved | MICHEL ABAJAN |
| Final | 11/25/2025 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 11/25/2025 | Approved | MICHEL ABAJAN |
| HVAC-Final | 11/25/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 11/25/2025 | Approved | MICHEL ABAJAN |
| Service/Power Release | 11/25/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| Final | 12/12/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| Service/Power Release | 12/12/2025 | Approved | MICHEL ABAJAN |
| Special/Order Compliance | 1/23/2026 | Corrections Issued | RAUL OLAGI |
| Final | 1/27/2026 | OK to Issue CofO | RAUL OLAGI |