12977 1/2 W CORCORAN PL 91340

Certificate Information: 12977 1/2 W CORCORAN PL 91340

Application / Permit
24010-20000-01825
Plan Check / Job No.
B24VN06034
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*EPLAN* NEW 35'-8" X 24' TWO STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 11/7/2024
Issuing Office
Current Status
CofO Issued on 1/28/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/3/2024 APPLICANT
Assigned to Plan Check Engineer 5/9/2024 SELLA BENYAMIN
Corrections Issued 5/14/2024 SELLA BENYAMIN
Quality Review Completed 5/30/2024 STEVEN KIM
Plan Check Approved 10/31/2024 SELLA BENYAMIN
Issued 11/7/2024 APPLICANT
CofO in Progress 12/18/2025 MICHEL ABAJAN
CofO in Progress 1/5/2026 MICHEL ABAJAN
No Progress 1/5/2026 MICHEL ABAJAN
CofO in Progress 1/5/2026 MICHEL ABAJAN
No Progress 1/23/2026 RAUL OLAGI
CofO in Progress 1/23/2026 RAUL OLAGI
CofO in Progress 1/27/2026 RAUL OLAGI
CofO in Progress 1/27/2026 RAUL OLAGI
Permit Finaled 1/28/2026 RUBEN SALAS
CofO Issued 1/28/2026 RUBEN SALAS
Permit Finaled 1/28/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/16/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 5/16/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 5/20/2024 BIAINA HARITUNIAN
Sewer availability Cleared 5/20/2024 BIAINA HARITUNIAN
Construction near power lines Cleared 9/25/2024 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,
Engineer Rahman,, Moksudur; Lic. No.: C69263 6572 SHEFFIELD      CHINO, CA 91710

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/27/2025 Partial Inspection MICHEL ABAJAN
PLUMBING-Rough 4/16/2025 Partial Approval MICHEL ABAJAN
Sewer 4/16/2025 Approved MICHEL ABAJAN
Excavation/Setback/Form/Re-Bar 4/29/2025 Approved MICHEL ABAJAN
Footing/Foundation/Slab 4/29/2025 Approved MICHEL ABAJAN
PLUMBING-Rough 4/29/2025 Partial Approval MICHEL ABAJAN
Underground Mechanical 4/29/2025 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 6/11/2025 Corrections Issued MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 6/11/2025 Partial Approval MICHEL ABAJAN
Green Building Rough 6/11/2025 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Rough 6/11/2025 Not Ready for Inspection MICHEL ABAJAN
Underground Mechanical 6/11/2025 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 6/11/2025 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 6/20/2025 Approved MICHEL ABAJAN
ELECTRICAL-Rough 6/20/2025 Approved MICHEL ABAJAN
Green Building Rough 6/20/2025 Approved MICHEL ABAJAN
HVAC-Rough 6/20/2025 Corrections Issued MICHEL ABAJAN
PLUMBING-Rough 6/20/2025 Approved MICHEL ABAJAN
HVAC-Rough 6/25/2025 Approved MICHEL ABAJAN
Insulation 6/25/2025 Approved MICHEL ABAJAN
Interior/Exterior Lathing 6/25/2025 Approved MICHEL ABAJAN
Drywall Nailing 6/27/2025 Not Ready for Inspection MICHEL ABAJAN
Drywall Nailing 7/2/2025 Approved LOUIS ESCOTO
Shower Pan 7/2/2025 Corrections Issued LOUIS ESCOTO
Shower Pan 7/10/2025 Approved LOUIS ESCOTO
ELECTRICAL-Final 10/10/2025 Not Ready for Inspection MICHEL ABAJAN
Final 10/10/2025 Corrections Issued MICHEL ABAJAN
Green Building Final 10/10/2025 Not Ready for Inspection MICHEL ABAJAN
HVAC-Final 10/10/2025 Approved MICHEL ABAJAN
PLUMBING-Final 10/10/2025 Not Ready for Inspection MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 10/10/2025 SGSOV Not Required MICHEL ABAJAN
Service/Power Release 10/10/2025 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 10/10/2025 Approved MICHEL ABAJAN
ELECTRICAL-Final 11/25/2025 Approved MICHEL ABAJAN
Final 11/25/2025 Corrections Issued MICHEL ABAJAN
Green Building Final 11/25/2025 Approved MICHEL ABAJAN
HVAC-Final 11/25/2025 Approved MICHEL ABAJAN
PLUMBING-Final 11/25/2025 Approved MICHEL ABAJAN
Service/Power Release 11/25/2025 Not Ready for Inspection MICHEL ABAJAN
Final 12/12/2025 Not Ready for Inspection MICHEL ABAJAN
Service/Power Release 12/12/2025 Approved MICHEL ABAJAN
Special/Order Compliance 1/23/2026 Corrections Issued RAUL OLAGI
Final 1/27/2026 OK to Issue CofO RAUL OLAGI