11759 N CHIVERS AVE 91331
Certificate Information: 11759 N CHIVERS AVE 91331
- Application / Permit
- 24010-20000-01802
- Plan Check / Job No.
- B24VN05950
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 15' X 33' DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d)
- Permit Issued
- Issued on 8/8/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/1/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/30/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/7/2024 | KAMYAR EMAMI |
| Corrections Issued | 5/7/2024 | KAMYAR EMAMI |
| Building Plans Picked Up | 5/8/2024 | APPLICANT |
| Issued | 8/8/2024 | APPLICANT |
| CofO in Progress | 6/18/2025 | MICHEL ABAJAN |
| Permit Finaled | 7/1/2025 | RUBEN SALAS |
| CofO Issued | 7/1/2025 | RUBEN SALAS |
| Permit Finaled | 7/1/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/11/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 5/11/2024 | CARLOS AGUILERA |
| Clean Up Green Up | Cleared | 5/13/2024 | ALEX VELA |
| Eng Process Fee Ord 176,300 | Cleared | 5/13/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 5/13/2024 | CARLOS AGUILERA |
| ZI | Cleared | 5/13/2024 | ALEX VELA |
| Construction near power lines | Cleared | 7/10/2024 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| MICHEL ABAJAN, (818) 374-9932 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/27/2024 | Partial Approval | MICHEL ABAJAN |
| PLUMBING-Rough | 9/27/2024 | Partial Approval | MICHEL ABAJAN |
| Footing/Foundation/Slab | 10/1/2024 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/10/2024 | Partial Approval | MICHEL ABAJAN |
| ELECTRICAL-Rough | 10/22/2024 | Not Ready for Inspection | MICHEL ABAJAN |
| Interior/Exterior Lathing | 10/22/2024 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 10/22/2024 | Approved | MICHEL ABAJAN |
| Sewer | 10/22/2024 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 12/24/2024 | Approved | MICHEL ABAJAN |
| BUILDING-Rough-Frame | 12/31/2024 | Approved | MICHEL ABAJAN |
| Green Building Rough | 12/31/2024 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 12/31/2024 | Approved | MICHEL ABAJAN |
| MERV13>=Rough | 12/31/2024 | Approved | MICHEL ABAJAN |
| Shower Pan | 12/31/2024 | Approved | MICHEL ABAJAN |
| Verify Sprinkler Sign Off | 12/31/2024 | Approved | MICHEL ABAJAN |
| Insulation | 1/3/2025 | Approved | MICHEL ABAJAN |
| Drywall Nailing | 1/7/2025 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 1/7/2025 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Final | 4/21/2025 | Approved | MICHEL ABAJAN |
| Final | 4/21/2025 | Corrections Issued | MICHEL ABAJAN |
| Green Building Final | 4/21/2025 | Approved | MICHEL ABAJAN |
| HVAC-Final | 4/21/2025 | Approved | MICHEL ABAJAN |
| MERV13>=Final | 4/21/2025 | Approved | MICHEL ABAJAN |
| PLUMBING-Final | 4/21/2025 | Approved | MICHEL ABAJAN |
| SGSOV-Seismic Gas S/O Valve | 4/21/2025 | SGSOV Not Required | MICHEL ABAJAN |
| Service/Power Release | 4/21/2025 | Not Ready for Inspection | MICHEL ABAJAN |
| Smoke Detectors | 4/21/2025 | Approved | MICHEL ABAJAN |
| Final | 5/30/2025 | No Access for Inspection | NICHOLAS TROWBRIDGE |
| Service/Power Release | 5/30/2025 | No Access for Inspection | NICHOLAS TROWBRIDGE |
| Final | 6/13/2025 | OK to Issue CofO | MICHEL ABAJAN |
| Service/Power Release | 6/13/2025 | Approved | MICHEL ABAJAN |