11801 N GLENOAKS BLVD 91340

Certificate Information: 11801 N GLENOAKS BLVD 91340

Application / Permit
24010-20000-01771
Plan Check / Job No.
B24VN05883
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
EPLAN NEW 2-STORY detached ADU
Permit Issued
Issued on 10/3/2024
Issuing Office
Current Status
CofO Issued on 4/24/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/7/2024 APPLICANT
Assigned to Plan Check Engineer 5/16/2024 ARSALAN SHABESTARI
Corrections Issued 5/28/2024 ARSALAN SHABESTARI
Quality Review Completed 6/5/2024 GARO TELMI
Plan Check Approved 9/24/2024 ARSALAN SHABESTARI
Issued 10/3/2024 APPLICANT
CofO in Progress 3/26/2025 MICHEL ABAJAN
Permit Finaled 4/24/2025 RUBEN SALAS
CofO Issued 4/24/2025 RUBEN SALAS
Permit Finaled 4/24/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 6/29/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 6/29/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 7/8/2024 CARLOS AGUILERA
Sewer availability Cleared 7/8/2024 CARLOS AGUILERA
ZI Cleared 8/8/2024 DORIAN AGUILAR

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/23/2024 Not Ready for Inspection MICHEL ABAJAN
PLUMBING-Rough 12/23/2024 Partial Approval MICHEL ABAJAN
Footing/Foundation/Slab 12/27/2024 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 1/6/2025 Partial Approval MICHEL ABAJAN
Sewer 1/13/2025 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 1/21/2025 Conditional Approval MICHEL ABAJAN
ELECTRICAL-Rough 1/21/2025 Approved MICHEL ABAJAN
Floor/Roof Diaphrgm/Shear Wall 1/21/2025 Partial Approval MICHEL ABAJAN
Green Building Rough 1/21/2025 Approved MICHEL ABAJAN
HVAC-Rough 1/21/2025 Approved MICHEL ABAJAN
PLUMBING-Rough 1/21/2025 Approved MICHEL ABAJAN
Verify Sprinkler Sign Off 1/21/2025 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 1/24/2025 Approved MICHEL ABAJAN
Insulation 1/24/2025 Approved MICHEL ABAJAN
Interior/Exterior Lathing 1/24/2025 Approved MICHEL ABAJAN
Drywall Nailing 1/28/2025 Approved MICHEL ABAJAN
Interior/Exterior Lathing 2/7/2025 Approved MICHEL ABAJAN
Underground Mechanical 3/3/2025 Approved MICHEL ABAJAN
ELECTRICAL-Final 3/21/2025 Approved MICHEL ABAJAN
Final 3/21/2025 Corrections Issued MICHEL ABAJAN
Green Building Final 3/21/2025 Approved MICHEL ABAJAN
HVAC-Final 3/21/2025 Approved MICHEL ABAJAN
PLUMBING-Final 3/21/2025 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 3/21/2025 SGSOV Not Required MICHEL ABAJAN
Service/Power Release 3/21/2025 Not Ready for Inspection MICHEL ABAJAN
Smoke Detectors 3/21/2025 Approved MICHEL ABAJAN
ELECTRICAL-Final 3/25/2025 Approved MICHEL ABAJAN
Final 3/25/2025 OK to Issue CofO MICHEL ABAJAN
HVAC-Final 3/25/2025 Approved MICHEL ABAJAN
PLUMBING-Final 3/25/2025 Approved MICHEL ABAJAN