14587 1/2 W LYLE ST 91342
Certificate Information: 14587 1/2 W LYLE ST 91342
- Application / Permit
- 24010-20000-01767
- Plan Check / Job No.
- B24VN05873
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New (40' x 17'-8" Irregular Shape) Accessory Dwelling Unit per LAMC 12.22 A.33 (c)-(d) with (9'-1" x 17'-8") covered patio on first story
- Permit Issued
- Issued on 7/18/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 1/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/29/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 5/2/2024 | VAHAN JIVALAGIAN |
| Corrections Issued | 5/4/2024 | VAHAN JIVALAGIAN |
| Quality Review Completed | 5/6/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 5/7/2024 | APPLICANT |
| Applicant returned to address corrections | 7/11/2024 | VAHAN JIVALAGIAN |
| Plan Check Approved | 7/15/2024 | VAHAN JIVALAGIAN |
| Issued | 7/18/2024 | APPLICANT |
| CofO in Progress | 12/27/2024 | KEVIN BERBERYAN |
| Permit Finaled | 1/3/2025 | RUBEN SALAS |
| CofO Issued | 1/3/2025 | RUBEN SALAS |
| Permit Finaled | 1/3/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 5/8/2024 | EDGAR ALCARAZ |
| ZA Case | Cleared | 5/8/2024 | ASHLEY RODARTE |
| Address approval | Cleared | 5/13/2024 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 5/14/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 5/14/2024 | EDGAR ALCARAZ |
| Miscellaneous | Cleared | 7/3/2024 | VAHAN JIVALAGIAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 7/23/2024 | Approved | KEVIN BERBERYAN |
| Excavation/Setback/Form/Re-Bar | 7/26/2024 | Approved | KEVIN BERBERYAN |
| Footing/Foundation/Slab | 7/26/2024 | Approved | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/26/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2024 | Corrections Issued | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2024 | Conditional Approval | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 9/27/2024 | Approved | KEVIN BERBERYAN |
| HVAC-Rough | 9/27/2024 | Corrections Issued | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 9/27/2024 | Approved | KEVIN BERBERYAN |
| PLUMBING-Rough | 9/27/2024 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 9/30/2024 | Partial Approval | KEVIN BERBERYAN |
| Green Building Rough | 9/30/2024 | Approved | KEVIN BERBERYAN |
| Insulation | 9/30/2024 | Corrections Issued | KEVIN BERBERYAN |
| Verify Sprinkler Sign Off | 9/30/2024 | Approved | KEVIN BERBERYAN |
| Wood Frame | 9/30/2024 | Partial Approval | KEVIN BERBERYAN |
| Drywall Nailing | 10/3/2024 | Corrections Issued | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 10/3/2024 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 12/9/2024 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 12/9/2024 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Final | 12/9/2024 | Corrections Issued | KEVIN BERBERYAN |
| Final | 12/9/2024 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 12/9/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| HVAC-Final | 12/9/2024 | Corrections Issued | KEVIN BERBERYAN |
| PLUMBING-Final | 12/9/2024 | Corrections Issued | KEVIN BERBERYAN |
| SGSOV-Seismic Gas S/O Valve | 12/9/2024 | SGSOV Not Required | KEVIN BERBERYAN |
| Service/Power Release | 12/9/2024 | Corrections Issued | KEVIN BERBERYAN |
| Smoke Detectors | 12/9/2024 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Final | 12/16/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| Final | 12/16/2024 | Corrections Issued | KEVIN BERBERYAN |
| Green Building Final | 12/16/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| HVAC-Final | 12/16/2024 | Approved | KEVIN BERBERYAN |
| PLUMBING-Final | 12/16/2024 | Not Ready for Inspection | KEVIN BERBERYAN |
| Service/Power Release | 12/16/2024 | Corrections Issued | KEVIN BERBERYAN |
| ELECTRICAL-Final | 12/18/2024 | Approved | KEVIN BERBERYAN |
| PLUMBING-Final | 12/18/2024 | Approved | KEVIN BERBERYAN |
| Final | 12/27/2024 | OK to Issue CofO | KEVIN BERBERYAN |
| Green Building Final | 12/27/2024 | Approved | KEVIN BERBERYAN |
| Service/Power Release | 12/27/2024 | Approved | KEVIN BERBERYAN |