9240 N NATICK AVE 91343

Certificate Information: 9240 N NATICK AVE 91343

Application / Permit
24010-20000-01763
Plan Check / Job No.
B24VN05861
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 10/17/2024
Issuing Office
Current Status
Issued on 10/17/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/29/2024 APPLICANT
Assigned to Plan Check Engineer 5/6/2024 JEROME MAGAT PALMA
Corrections Issued 5/7/2024 JEROME MAGAT PALMA
Building Plans Picked Up 5/10/2024 APPLICANT
Plan Check Approved 9/9/2024 OMAR GARNICA
Issued 10/17/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 5/17/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 5/17/2024 BIAINA HARITUNIAN
Sewer availability Cleared 5/20/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 6/11/2024 BIAINA HARITUNIAN
Construction near power lines Cleared 9/9/2024 TINA MIRANDA

Contact Information

Contractor F S Design & Construction Inc; Lic. No.: 727272-B 20520 OXNARD ST      WOODLAND, CA 91367

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/21/2024 Partial Approval GREGG CUMMINGS
Footing/Foundation/Slab 10/25/2024 Corrections Issued VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 11/25/2024 Partial Approval VINCENT HANLEY
Footing/Foundation/Slab 11/25/2024 Approved VINCENT HANLEY
Underground Mechanical 11/25/2024 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 12/10/2024 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 12/10/2024 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 12/10/2024 Approved VINCENT HANLEY
Green Building Rough 12/10/2024 Approved VINCENT HANLEY
HVAC-Rough 12/10/2024 Approved VINCENT HANLEY
PLUMBING-Rough 12/10/2024 Approved VINCENT HANLEY
BUILDING-Rough-Frame 12/12/2024 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 12/12/2024 Approved VINCENT HANLEY
Insulation 12/12/2024 Approved VINCENT HANLEY
Interior/Exterior Lathing 12/12/2024 Partial Approval VINCENT HANLEY
BUILDING-Rough-Frame 12/16/2024 Approved JENNIFER RABUCHIN
Drywall Nailing 12/16/2024 Approved JENNIFER RABUCHIN
Shower Pan 12/16/2024 Approved JENNIFER RABUCHIN
Special/Order Compliance 12/16/2024 Corrections Issued JENNIFER RABUCHIN
Verify Sprinkler Sign Off 12/16/2024 Partial Approval JENNIFER RABUCHIN
Drywall Nailing 12/18/2024 Approved VINCENT HANLEY
Interior/Exterior Lathing 1/8/2025 Approved LOUIS ESCOTO