12939 N EL DORADO AVE 91342

Certificate Information: 12939 N EL DORADO AVE 91342

Application / Permit
24010-20000-01757
Plan Check / Job No.
B24VN05842
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New detached Accessory dwelling unit per LAMC 12.22 A.33(c) AND (d).
Permit Issued
Issued on 1/6/2025
Issuing Office
Current Status
CofO Issued on 1/2/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/30/2024 APPLICANT
Assigned to Plan Check Engineer 5/3/2024 PINANK PATEL
Corrections Issued 5/4/2024 PINANK PATEL
Applicant returned to address corrections 10/9/2024 PINANK PATEL
Applicant returned to address corrections 10/16/2024 PINANK PATEL
Plan Check Approved 10/29/2024 PINANK PATEL
Issued 1/6/2025 APPLICANT
CofO in Progress 12/8/2025 NICHOLAS TROWBRIDGE
Permit Finaled 1/2/2026 RUBEN SALAS
CofO Issued 1/2/2026 RUBEN SALAS
Permit Finaled 1/2/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/10/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 5/10/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 5/21/2024 CARLOS AGUILERA
Hydrant and Access approval Cleared 7/5/2024 GILBERT URREA
Sewer availability Cleared 7/9/2024 CARLOS AGUILERA
GPI Written Notices Cleared 10/8/2024 PINANK PATEL
Grading Pre-Inspection Cleared 10/8/2024 PINANK PATEL

Contact Information

Contractor Owner-Builder       ,
Engineer Keshishian,, Anthony; Lic. No.: C89551 2654 RISA D      GLENDALE, CA 91208

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/21/2025 Corrections Issued KEVIN BERBERYAN
PLUMBING-Rough 4/28/2025 Approved KEVIN BERBERYAN
Excavation/Setback/Form/Re-Bar 5/7/2025 Not Ready for Inspection KEVIN BERBERYAN
Special/Order Compliance 5/13/2025 Corrections Issued KEVIN BERBERYAN
BUILDING-Rough-Frame 7/25/2025 Corrections Issued KEVIN BERBERYAN
ELECTRICAL-Rough 7/25/2025 Approved KEVIN BERBERYAN
HVAC-Rough 7/25/2025 Corrections Issued KEVIN BERBERYAN
PLUMBING-Rough 7/25/2025 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 8/5/2025 Approved KEVIN BERBERYAN
Green Building Rough 8/5/2025 Approved KEVIN BERBERYAN
Interior/Exterior Lathing 8/5/2025 Approved KEVIN BERBERYAN
Insulation 8/11/2025 Corrections Issued KEVIN BERBERYAN
Drywall Nailing 8/20/2025 Approved KEVIN BERBERYAN
ELECTRICAL-Final 10/2/2025 Corrections Issued KEVIN BERBERYAN
ELECTRICAL-Final 10/7/2025 Approved KEVIN BERBERYAN
Service/Power Release 10/7/2025 Approved KEVIN BERBERYAN
Final 12/2/2025 Corrections Issued KEVIN BERBERYAN
Footing/Foundation/Slab 12/2/2025 Approved KEVIN BERBERYAN
Green Building Final 12/2/2025 Approved KEVIN BERBERYAN
SGSOV-Seismic Gas S/O Valve 12/2/2025 SGSOV Not Required KEVIN BERBERYAN
Smoke Detectors 12/2/2025 Approved KEVIN BERBERYAN
Final 12/5/2025 OK to Issue CofO NICHOLAS TROWBRIDGE