23922-23924 W HAMLIN ST 91307

Certificate Information: 23922-23924 W HAMLIN ST 91307

Application / Permit
24010-20000-01735
Plan Check / Job No.
B24VN05754
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan: (N) 1-STORY SINGLE FAMILY DWELLING PER SENATE BILL 9 TWO-UNIT DEVELOPMENT AND ATTACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e)
Permit Issued
Issued on 9/11/2024
Issuing Office
Current Status
CofO Issued on 5/4/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/26/2024 APPLICANT
Assigned to Plan Check Engineer 5/9/2024 DANIEL YIP
Corrections Issued 5/10/2024 DANIEL YIP
Quality Review Completed 5/13/2024 GARO TELMI
Applicant returned to address corrections 9/4/2024 DANIEL YIP
Plan Check Approved 9/11/2024 DANIEL YIP
Issued 9/11/2024 APPLICANT
CofO in Progress 3/25/2026 TROY SANDERS
Permit Finaled 5/4/2026 JOHN JANSON
CofO Issued 5/4/2026 JOHN JANSON
Permit Finaled 5/4/2026 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 5/21/2024 CARLOS RAMIREZ
Roof/Waste drainage to street Cleared 5/21/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 5/23/2024 CARLOS RAMIREZ
Sewer availability Cleared 5/23/2024 CARLOS RAMIREZ
Senate Bill 9 Cleared 5/24/2024 DORIAN AGUILAR
Hydrant and Access approval Cleared 7/2/2024 KURT CORRAL
Construction near power lines Cleared 8/9/2024 RIDWAN HARDY
Miscellaneous Cleared 8/22/2024 SIMON LIU

Contact Information

Architect Dembsky,, Amit; Lic. No.: C30383 5739 KANAN ROAD # 133      AGOURA HILLS, CA 91301
Architect Dembsky,, Amit; Lic. No.: NA30383       ,
Contractor La-Decks; Lic. No.: 968237-B       ,
Contractor Shpigel'S; Lic. No.: 968237-B       ,

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/31/2025 Partial Approval TROY SANDERS
Underground Mechanical 1/31/2025 Not Ready for Inspection TROY SANDERS
Footing/Foundation/Slab 2/20/2025 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 4/1/2025 Partial Approval TROY SANDERS
Green Building Rough 4/1/2025 Not Ready for Inspection TROY SANDERS
Verify Sprinkler Sign Off 4/1/2025 Not Ready for Inspection TROY SANDERS
PLUMBING-Rough 4/29/2025 Corrections Issued SCOTT SOBEL
BUILDING-Rough-Frame 5/6/2025 Approved TROY SANDERS
ELECTRICAL-Rough 5/6/2025 Partial Approval TROY SANDERS
HVAC-Rough 5/6/2025 Approved TROY SANDERS
Verify Sprinkler Sign Off 5/6/2025 Approved TROY SANDERS
PLUMBING-Rough 5/15/2025 Approved TROY SANDERS
ELECTRICAL-Rough 5/22/2025 Approved TROY SANDERS
Insulation 5/27/2025 Approved TROY SANDERS
Interior/Exterior Lathing 5/27/2025 Partial Approval TROY SANDERS
Drywall Nailing 6/4/2025 Approved TROY SANDERS
Green Building Rough 6/4/2025 Approved TROY SANDERS
Shower Pan 6/23/2025 Approved TROY SANDERS
Interior/Exterior Lathing 6/30/2025 Partial Approval TROY SANDERS
Underground Mechanical 8/5/2025 Approved TROY SANDERS
Service/Power Release 9/8/2025 Not Ready for Inspection TROY SANDERS
Final 11/12/2025 Not Ready for Inspection TROY SANDERS
Green Building Final 11/12/2025 Corrections Issued TROY SANDERS
SGSOV-Seismic Gas S/O Valve 11/12/2025 SGSOV Approved TROY SANDERS
Service/Power Release 11/12/2025 Approved TROY SANDERS
Smoke Detectors 11/12/2025 Approved TROY SANDERS
Special/Order Compliance 1/12/2026 Corrections Issued ROBERT GOLD
Final 3/25/2026 OK to Issue CofO TROY SANDERS
Green Building Final 3/25/2026 Approved TROY SANDERS