7457 S MCCONNELL AVE 90045

Certificate Information: 7457 S MCCONNELL AVE 90045

Application / Permit
24010-20000-01713
Plan Check / Job No.
B24VN04655
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 1-STORY DETACHED ACCESSORY DWELLING UNIT (795 SQFT) PER LAMC 12.22 A.33(c)(d) W/NFPA 13D SPRINKLERS THROUGHOUT
Permit Issued
Issued on 1/13/2025
Issuing Office
Valley
Current Status
Issued on 1/13/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/8/2024 APPLICANT
Assigned to Plan Check Engineer 4/18/2024 PETER MOSESIAN
Corrections Issued 4/25/2024 PETER MOSESIAN
Quality Review Completed 4/26/2024 OMID HEDAYAT
Building Plans Picked Up 4/29/2024 APPLICANT
Plan Check Approved 12/23/2024 PETER MOSESIAN
Issued 1/13/2025 APPLICANT

Permit Application Clearance Information

ZA Case Cleared 5/6/2024 ASHLEY RODARTE
ZA Case Cleared 5/6/2024 ASHLEY RODARTE
Construction near power lines Cleared 6/26/2024 RIDWAN HARDY
Address approval Cleared 7/30/2024 DIANA RENTERIA
Eng Process Fee Ord 176,300 Cleared 8/22/2024 DIANA RENTERIA
Sewer availability Cleared 8/22/2024 DIANA RENTERIA
Specific Plan Cleared 9/5/2024 PEDRO AYALA
Hydrant and Access approval Cleared 9/10/2024 KURT CORRAL
Roof/Waste drainage to street Cleared 10/5/2024 LIAM ODONOVAN
Miscellaneous Cleared 12/2/2024 DIANA RENTERIA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

Wood Frame 6/11/2026   

Inspection Request History

Deputy Reinf. Concrete 2/24/2025 Conditional Approval DAVID FEILER
Deputy Reinf. Concrete 2/24/2025 Conditional Approval HERBERT GIRON
Piling/Pier/Caisson 2/24/2025 Corrections Issued HERBERT GIRON
Piling/Pier/Caisson 2/25/2025 Partial Approval TEMISTOCLES CAAL
Piling/Pier/Caisson 3/5/2025 Partial Approval TEMISTOCLES CAAL
Deputy Reinf. Concrete 3/7/2025 Conditional Approval JAYLIN GRAVITTE
Deputy Reinf. Concrete 4/21/2025 Conditional Approval JESUS PINEDA
Excavation/Setback/Form/Re-Bar 4/23/2025 Partial Approval JESUS PINEDA
Special/Order Compliance 4/23/2025 Partial Inspection TEMISTOCLES CAAL
Deputy Reinf. Concrete 5/13/2025 Approved RUBEN RIVAS
Footing/Foundation/Slab 5/13/2025 Partial Approval RUBEN RIVAS
Excavation/Setback/Form/Re-Bar 5/14/2025 Partial Approval JESUS PINEDA
Deputy Grading 5/19/2025 Conditional Approval JESUS PINEDA
Deputy Reinf. Concrete 5/19/2025 Conditional Approval JESUS PINEDA
Excavation/Setback/Form/Re-Bar 5/28/2025 Partial Approval JESUS PINEDA
METHANE-Barrier 6/26/2025 Partial Approval JESUS RODRIGUEZ
PLUMBING-Rough 6/26/2025 Partial Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 7/9/2025 Approved JESUS PINEDA
METHANE-Barrier 7/9/2025 Approved JESUS PINEDA
METHANE-Subgrade 7/9/2025 Approved JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 4/2/2026 Corrections Issued JESUS PINEDA