7641 N BEN AVE 91605
Certificate Information: 7641 N BEN AVE 91605
- Application / Permit
- 24010-20000-01682
- Plan Check / Job No.
- B24VN05672
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 2-story Accessory Dwelling Unit (26'-6" x 17'-8") per CA Govt. Code 65852.2(e)(1)(B) and applicable part of LAMC 12.22 A.33(c)-(d), (g)
- Permit Issued
- Issued on 5/29/2024
- Issuing Office
- Current Status
- CofO Issued on 1/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/24/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/25/2024 | VAHAN JIVALAGIAN |
| Corrections Issued | 4/26/2024 | VAHAN JIVALAGIAN |
| Quality Review Completed | 4/26/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 4/29/2024 | APPLICANT |
| Plan Check Approved | 5/29/2024 | VAHAN JIVALAGIAN |
| Issued | 5/29/2024 | APPLICANT |
| CofO in Progress | 1/16/2025 | MATTHEW NELSON |
| Permit Finaled | 1/24/2025 | RUBEN SALAS |
| CofO Issued | 1/24/2025 | RUBEN SALAS |
| Permit Finaled | 1/24/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Clean Up Green Up | Cleared | 4/30/2024 | ALEX VELA |
| Address approval | Cleared | 5/3/2024 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 5/3/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 5/3/2024 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 5/13/2024 | LEE GUILBEAUX |
| Sewer availability | Cleared | 5/13/2024 | LEE GUILBEAUX |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Andrejic,, Milos; Lic. No.: C67443 | 3601 BEVERLY RIDGE DR SHERMAN OAKS, CA 91423 |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 6/20/2024 | Approved | KEVIN BERBERYAN |
| Excavation/Setback/Form/Re-Bar | 7/2/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Excavation/Setback/Form/Re-Bar | 7/8/2024 | Approved | MATTHEW NELSON |
| Footing/Foundation/Slab | 7/8/2024 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 7/8/2024 | Partial Approval | MATTHEW NELSON |
| BUILDING-Rough-Frame | 7/19/2024 | Corrections Issued | MATTHEW NELSON |
| Green Building Rough | 7/19/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 7/19/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Wood Frame | 7/19/2024 | Corrections Issued | MATTHEW NELSON |
| Wood Frame | 7/22/2024 | Partial Approval | MATTHEW NELSON |
| Wood Frame | 7/30/2024 | Corrections Issued | MATTHEW NELSON |
| BUILDING-Rough-Frame | 8/13/2024 | Partial Approval | MATTHEW NELSON |
| ELECTRICAL-Rough | 8/13/2024 | Approved | MATTHEW NELSON |
| PLUMBING-Rough | 8/13/2024 | Approved | MATTHEW NELSON |
| HVAC-Rough | 8/19/2024 | Approved | MATTHEW NELSON |
| Wood Frame | 8/19/2024 | Corrections Issued | MATTHEW NELSON |
| Deputy Wood Construction | 8/22/2024 | Conditional Approval | DAVID MATSON |
| BUILDING-Rough-Frame | 8/23/2024 | Partial Approval | MATTHEW NELSON |
| Green Building Rough | 8/23/2024 | Approved | MATTHEW NELSON |
| Shower Pan | 8/23/2024 | Approved | MATTHEW NELSON |
| Insulation | 8/27/2024 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 8/27/2024 | Partial Approval | GAREN HAYRAPETYAN |
| Insulation | 8/29/2024 | Corrections Issued | MATTHEW NELSON |
| Special/Order Compliance | 8/29/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Drywall Nailing | 9/3/2024 | Approved | MATTHEW NELSON |
| Insulation | 9/3/2024 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 9/17/2024 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 12/9/2024 | Approved | DAVID ANDERSON |
| Final | 12/9/2024 | Corrections Issued | DAVID ANDERSON |
| Green Building Final | 12/9/2024 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 12/9/2024 | SGSOV Not Required | DAVID ANDERSON |
| Service/Power Release | 12/9/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Smoke Detectors | 12/9/2024 | Approved | DAVID ANDERSON |
| Verify Sprinkler Sign Off | 12/9/2024 | Approved | DAVID ANDERSON |
| Final | 1/8/2025 | OK to Issue CofO | MATTHEW NELSON |
| Service/Power Release | 1/8/2025 | Approved | MATTHEW NELSON |