8433 N AURA AVE 91324
Certificate Information: 8433 N AURA AVE 91324
- Application / Permit
- 24010-20000-01649
- Plan Check / Job No.
- B24VN05496
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New detached ADU per CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 8/20/2024
- Issuing Office
- Current Status
- CofO Issued on 2/9/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/25/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/30/2024 | SHANGQIN XIE |
| Corrections Issued | 5/1/2024 | SHANGQIN XIE |
| Applicant returned to address corrections | 7/13/2024 | LAWRENCE QUIRANTE |
| Plan Check Approved | 8/1/2024 | TSE MING HUANG |
| Issued | 8/20/2024 | APPLICANT |
| CofO in Progress | 2/4/2026 | CHRIS CHRISTENSEN |
| Permit Finaled | 2/9/2026 | JOHN JANSON |
| CofO Issued | 2/9/2026 | JOHN JANSON |
| Permit Finaled | 2/9/2026 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 5/3/2024 | EDGAR ALCARAZ |
| Roof/Waste drainage to street | Cleared | 5/3/2024 | EDGAR ALCARAZ |
| Eng Process Fee Ord 176,300 | Cleared | 5/9/2024 | EDGAR ALCARAZ |
| Sewer availability | Cleared | 5/10/2024 | EDGAR ALCARAZ |
| Hydrant and Access approval | Cleared | 6/8/2024 | KURT CORRAL |
| Construction near power lines | Cleared | 7/18/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Arakelyan,, Aram; Lic. No.: C82796 | 145 S GLENOAKS BI 328 BURBANK, CA 91502 |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 9/10/2024 | Approved | JEFFREY HARTLINE |
| Footing/Foundation/Slab | 9/24/2024 | Approved | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 11/19/2024 | Conditional Approval | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 11/19/2024 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Deputy Wood Construction | 11/21/2024 | Conditional Approval | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 12/10/2024 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 12/10/2024 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 12/10/2024 | Approved | CHRIS CHRISTENSEN |
| HVAC-Rough | 12/10/2024 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 12/10/2024 | Partial Approval | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 12/10/2024 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 12/11/2024 | Approved | CHRIS CHRISTENSEN |
| Underground Mechanical | 12/24/2024 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 1/28/2025 | Partial Approval | CHRIS CHRISTENSEN |
| Insulation | 1/31/2025 | Approved | CHRIS CHRISTENSEN |
| Drywall Nailing | 2/6/2025 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 2/6/2025 | Approved | CHRIS CHRISTENSEN |
| Shower Pan | 2/6/2025 | Approved | CHRIS CHRISTENSEN |
| Sewer | 2/18/2025 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 3/25/2025 | Corrections Issued | CHRIS CHRISTENSEN |
| PLUMBING-Final | 3/25/2025 | Corrections Issued | CHRIS CHRISTENSEN |
| Final | 5/2/2025 | Corrections Issued | CHRIS CHRISTENSEN |
| Green Building Final | 5/2/2025 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 5/2/2025 | SGSOV Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 5/2/2025 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Smoke Detectors | 5/2/2025 | Approved | CHRIS CHRISTENSEN |
| Final | 2/2/2026 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Green Building Final | 2/2/2026 | Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 2/2/2026 | Approved | CHRIS CHRISTENSEN |