11204 W SYLVAN ST 91606

Certificate Information: 11204 W SYLVAN ST 91606

Application / Permit
24010-20000-01608
Plan Check / Job No.
B24VN05327
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan: New A.D.U. attached to existing detached garage per LAMC 12.22 A.33 (c)-(d). Revise the existing garage to reduce size. Design per licensed engineer.
Permit Issued
Issued on 12/5/2024
Issuing Office
Current Status
CofO Issued on 1/30/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/19/2024 APPLICANT
Assigned to Plan Check Engineer 4/22/2024 CAROLEAN BASMA
Corrections Issued 4/23/2024 CAROLEAN BASMA
Plan Check Approved 11/13/2024 CAROLEAN BASMA
Issued 12/5/2024 APPLICANT
CofO in Progress 1/20/2026 MATTHEW NELSON
Permit Finaled 1/30/2026 RUBEN SALAS
CofO Issued 1/30/2026 RUBEN SALAS
Permit Finaled 1/30/2026 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 7/9/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 7/9/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 7/9/2024 BIAINA HARITUNIAN
Sewer availability Cleared 7/9/2024 BIAINA HARITUNIAN
Construction near power lines Cleared 11/3/2024 TINA MIRANDA

Contact Information

Contractor Owner-Builder       ,
Engineer Casillas,, Rafael Ortega; Lic. No.: NA68234       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/29/2025 Partial Approval MISAEL ESPARZA
Sewer 1/29/2025 Approved MISAEL ESPARZA
Footing/Foundation/Slab 2/4/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 2/27/2025 Not Ready for Inspection JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 3/4/2025 Partial Approval JOSE AVILA
PLUMBING-Rough 4/14/2025 Approved JOSE AVILA
Deputy Wood Construction 4/15/2025 Conditional Approval JOSE AVILA
ELECTRICAL-Rough 4/17/2025 Corrections Issued JOSE AVILA
HVAC-Rough 4/17/2025 Corrections Issued JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 5/8/2025 Partial Approval JOSE AVILA
ELECTRICAL-Rough 5/14/2025 Corrections Issued ROBERTO PALACIOS-LOPEZ
HVAC-Rough 5/14/2025 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 5/15/2025 Approved JOSE AVILA
HVAC-Rough 5/15/2025 Approved JOSE AVILA
BUILDING-Rough-Frame 5/21/2025 Approved JOSE AVILA
Insulation 6/9/2025 No Access for Inspection JOSE AVILA
Insulation 6/13/2025 Approved JOSE AVILA
Drywall Nailing 6/20/2025 Approved JOSE AVILA
Shower Pan 6/26/2025 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 6/30/2025 Approved JOSE AVILA
Underground Mechanical 10/8/2025 Approved JOSE AVILA
Gas Test 11/17/2025 Approved JOSE AVILA
Final 1/16/2026 OK to Issue CofO MATTHEW NELSON
Footing/Foundation/Slab 1/16/2026 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 1/16/2026 SGSOV Approved MATTHEW NELSON
Smoke Detectors 1/16/2026 Approved MATTHEW NELSON