21309 W LEMARSH ST 91311

Certificate Information: 21309 W LEMARSH ST 91311

Application / Permit
24010-20000-01587
Plan Check / Job No.
B24VN05217
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 5/2/2024
Issuing Office
Current Status
CofO Issued on 4/4/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/17/2024 APPLICANT
Assigned to Plan Check Engineer 4/22/2024 JEROME MAGAT PALMA
Corrections Issued 4/23/2024 JEROME MAGAT PALMA
Building Plans Picked Up 4/29/2024 APPLICANT
Plan Check Approved 5/2/2024 ALEC MOUSAKHANIAN
Issued 5/2/2024 APPLICANT
CofO in Progress 10/31/2024 KRISTEN BEVERIDGE
No Progress 9/10/2025 HENRY KIM
CofO in Progress 9/10/2025 HENRY KIM
Permit Finaled 4/4/2026 MICHAEL PELHAM
CofO Issued 4/4/2026 MICHAEL PELHAM
Permit Finaled 4/4/2026 MICHAEL PELHAM

Permit Application Clearance Information

Address approval Cleared 4/24/2024 CARLOS RAMIREZ
Roof/Waste drainage to street Cleared 4/24/2024 CARLOS RAMIREZ
Eng Process Fee Ord 176,300 Cleared 4/26/2024 MARKOS PEREZ-BRAN
Sewer availability Cleared 4/26/2024 MARKOS PEREZ-BRAN

Contact Information

Contractor We The People Construction Inc; Lic. No.: 1076924-B 5352 LAUREL CANYON BLVD # 200      VALLEY VILLAGE, CA 91607
Engineer Wassef,, Mena; Lic. No.: C84979 28131 VALERIO CT      VALENCIA, CA 91354

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 5/14/2024 Partial Approval DAVID SCANTLIN
Excavation/Setback/Form/Re-Bar 5/15/2024 Not Ready for Inspection DAVID SCANTLIN
Footing/Foundation/Slab 5/15/2024 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 6/5/2024 Not Ready for Inspection DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 6/5/2024 Approved DAVID SCANTLIN
Rough-Elec/Plmb/HVAC 6/5/2024 Approved DAVID SCANTLIN
Underground Mechanical 6/5/2024 Approved DAVID SCANTLIN
Interior/Exterior Lathing 6/6/2024 Approved DAVID SCANTLIN
Drywall Nailing 6/10/2024 Approved ARUTYUN MADATYAN
Green Building Rough 6/10/2024 Approved ARUTYUN MADATYAN
Interior/Exterior Lathing 6/20/2024 No Access for Inspection DAVID SCANTLIN
Interior/Exterior Lathing 6/27/2024 Approved DAVID SCANTLIN
Shower Pan 6/27/2024 Approved DAVID SCANTLIN
Underground Mechanical 9/4/2024 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 10/29/2024 Approved KRISTEN CAUSEY
Final 10/29/2024 OK to Issue CofO KRISTEN CAUSEY
Green Building Final 10/29/2024 Approved KRISTEN CAUSEY
SGSOV-Seismic Gas S/O Valve 10/29/2024 SGSOV Approved KRISTEN CAUSEY
Service/Power Release 10/29/2024 Approved KRISTEN CAUSEY
Smoke Detectors 10/29/2024 Approved KRISTEN CAUSEY
Verify Sprinkler Sign Off 10/29/2024 Approved KRISTEN CAUSEY