15537 W LEMARSH ST 91345

Certificate Information: 15537 W LEMARSH ST 91345

Application / Permit
24010-20000-01582
Plan Check / Job No.
B24VN05193
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLIGN UNIT PER GCS 65852.2(e)(1)(B) AND LAMC 12.22 A.33(c),(d) AND (g) - ALL WORK PER WFPP
Permit Issued
Issued on 12/10/2024
Issuing Office
Current Status
CofO Issued on 5/27/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/30/2024 APPLICANT
Assigned to Plan Check Engineer 5/3/2024 DANIEL ABRAMYAN
Corrections Issued 5/4/2024 DANIEL ABRAMYAN
Applicant returned to address corrections 11/5/2024 SERGIO MUNIZ
Applicant returned to address corrections 11/13/2024 LUISANGEL VALENZUELA
Plan Check Approved 11/21/2024 LUISANGEL VALENZUELA
Issued 12/10/2024 APPLICANT
CofO in Progress 5/19/2025 JENNIFER RABUCHIN
Permit Finaled 5/27/2025 RUBEN SALAS
CofO Issued 5/27/2025 RUBEN SALAS
Permit Finaled 5/27/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/21/2024 BIAINA HARITUNIAN
Roof/Waste drainage to street Cleared 5/21/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 5/31/2024 BIAINA HARITUNIAN
Sewer availability Cleared 5/31/2024 BIAINA HARITUNIAN
Construction near power lines Cleared 10/30/2024 TINA MIRANDA
Hold Cleared 1/28/2025 SANDRA SOH

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 12/19/2024 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 12/19/2024 Conditional Approval JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 1/9/2025 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 1/9/2025 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 1/9/2025 Partial Approval JENNIFER RABUCHIN
Deputy Drilled-In Anchors 1/10/2025 Conditional Approval JOHN COLEMAN
Floor/Roof Diaphrgm/Shear Wall 1/31/2025 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 1/31/2025 Not Ready for Inspection JENNIFER RABUCHIN
PLUMBING-Rough 2/4/2025 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 2/6/2025 Partial Approval JENNIFER RABUCHIN
ELECTRICAL-Rough 2/6/2025 Corrections Issued JENNIFER RABUCHIN
Green Building Rough 2/6/2025 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 2/6/2025 Partial Approval JENNIFER RABUCHIN
MERV13>=Rough 2/6/2025 Approved JENNIFER RABUCHIN
PLUMBING-Rough 2/6/2025 Approved JENNIFER RABUCHIN
Sewer 2/6/2025 Approved JENNIFER RABUCHIN
Verify Sprinkler Sign Off 2/6/2025 Approved JENNIFER RABUCHIN
Insulation 2/11/2025 Approved LOUIS ESCOTO
ELECTRICAL-Rough 2/12/2025 Approved LOUIS ESCOTO
Shower Pan 2/12/2025 Approved LOUIS ESCOTO
Drywall Nailing 2/14/2025 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 2/14/2025 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 2/25/2025 Corrections Issued JENNIFER RABUCHIN
Underground Mechanical 2/28/2025 Approved JENNIFER RABUCHIN
Service/Power Release 3/12/2025 Partial Inspection KEVIN BERBERYAN
ELECTRICAL-Final 4/2/2025 Corrections Issued JENNIFER RABUCHIN
HVAC-Final 4/2/2025 Corrections Issued JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 4/21/2025 SGSOV Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 5/7/2025 Approved JENNIFER RABUCHIN
Final 5/7/2025 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 5/7/2025 Approved JENNIFER RABUCHIN
Green Building Final 5/7/2025 Approved JENNIFER RABUCHIN
MERV13>=Final 5/7/2025 Approved JENNIFER RABUCHIN
Service/Power Release 5/7/2025 Not Ready for Inspection JENNIFER RABUCHIN
Smoke Detectors 5/7/2025 Approved JENNIFER RABUCHIN
Final 5/12/2025 Corrections Issued WILLIAM WREN
Service/Power Release 5/12/2025 Not Ready for Inspection WILLIAM WREN
ELECTRICAL-Final 5/14/2025 Approved JENNIFER RABUCHIN
Final 5/14/2025 OK to Issue CofO JENNIFER RABUCHIN
HVAC-Final 5/14/2025 Approved JENNIFER RABUCHIN
PLUMBING-Final 5/14/2025 Approved JENNIFER RABUCHIN
Service/Power Release 5/14/2025 Approved JENNIFER RABUCHIN