11838 W ARMINTA ST 91605

Certificate Information: 11838 W ARMINTA ST 91605

Application / Permit
24010-20000-01577
Plan Check / Job No.
B24VN05181
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) DETACHED 2-STORY SFD PER SB9 (NFPA-13D SPRINKLERS THROUGHOUT)
Permit Issued
Issued on 2/27/2025
Issuing Office
Valley
Current Status
CofO Issued on 4/10/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/17/2024 APPLICANT
Assigned to Plan Check Engineer 4/25/2024 PETER MOSESIAN
Corrections Issued 5/2/2024 PETER MOSESIAN
Quality Review Completed 5/2/2024 OMID HEDAYAT
Building Plans Picked Up 10/9/2024 APPLICANT
Plan Check Approved 1/14/2025 NILOOFAR MEHRAIN
Issued 2/27/2025 APPLICANT
CofO in Progress 3/13/2026 MATTHEW NELSON
Permit Finaled 4/10/2026 RUBEN SALAS
CofO Issued 4/10/2026 RUBEN SALAS
Permit Finaled 4/10/2026 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 8/30/2024 RYAN CASTRO
Eng Process Fee Ord 176,300 Cleared 9/3/2024 RYAN CASTRO
Sewer availability Cleared 9/3/2024 RYAN CASTRO
Clean Up Green Up Cleared 10/7/2024 NATHAN ROMINE
ZI Cleared 10/7/2024 NATHAN ROMINE
Senate Bill 9 Cleared 10/21/2024 NATHAN ROMINE
Address approval Cleared 10/23/2024 RYAN CASTRO
Hydrant and Access approval Cleared 1/7/2025 JERRY KAO

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 3625 BEVERLY RIDGE DRIVE      SHERMAN OAKS, CA 91423

Inspector Information

MATTHEW NELSON, (818) 374-1170 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/28/2025 Not Ready for Inspection MATTHEW NELSON
Pre-Inspection 3/28/2025 Not Ready for Inspection MATTHEW NELSON
PLUMBING-Rough 4/2/2025 Partial Approval MATTHEW NELSON
Excavation/Setback/Form/Re-Bar 4/4/2025 Approved MATTHEW NELSON
Footing/Foundation/Slab 4/4/2025 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 5/8/2025 Corrections Issued NICHOLAS TROWBRIDGE
Deputy Wood Construction 5/9/2025 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 5/12/2025 Partial Approval NICHOLAS TROWBRIDGE
Floor/Roof Diaphrgm/Shear Wall 6/6/2025 Corrections Issued MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 6/13/2025 Partial Approval MATTHEW NELSON
ELECTRICAL-Rough 6/17/2025 Approved MATTHEW NELSON
HVAC-Rough 6/17/2025 Approved MATTHEW NELSON
PLUMBING-Rough 6/17/2025 Approved MATTHEW NELSON
BUILDING-Rough-Frame 6/23/2025 Not Ready for Inspection MATTHEW NELSON
Green Building Rough 6/23/2025 Approved MATTHEW NELSON
Insulation 6/23/2025 Partial Approval MATTHEW NELSON
Verify Sprinkler Sign Off 6/23/2025 Approved MATTHEW NELSON
Drywall Nailing 6/27/2025 Not Ready for Inspection MATTHEW NELSON
Interior/Exterior Lathing 6/27/2025 Not Ready for Inspection MATTHEW NELSON
BUILDING-Rough-Frame 6/30/2025 Approved MATTHEW NELSON
Interior/Exterior Lathing 7/15/2025 Approved MATTHEW NELSON
Drywall Nailing 2/9/2026 Approved MATTHEW NELSON
Final 2/9/2026 Not Ready for Inspection MATTHEW NELSON
Green Building Final 2/9/2026 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 2/9/2026 SGSOV Not Ready MATTHEW NELSON
Service/Power Release 2/9/2026 Not Ready for Inspection MATTHEW NELSON
Smoke Detectors 2/9/2026 Approved MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 2/11/2026 SGSOV Not Ready MATTHEW NELSON
Final 3/9/2026 OK to Issue CofO MATTHEW NELSON
SGSOV-Seismic Gas S/O Valve 3/9/2026 SGSOV Approved MATTHEW NELSON
Service/Power Release 3/9/2026 Approved MATTHEW NELSON