10534 N VARIEL AVE 91311

Certificate Information: 10534 N VARIEL AVE 91311

Application / Permit
24010-20000-01567
Plan Check / Job No.
B24VN05123
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 39'-10" X 41'-3" IRREGULAR SHAPED DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). FIRE SPRINKLER (NFPA 13R) REQUIRED THROUGHOUT.
Permit Issued
Issued on 7/5/2024
Issuing Office
Valley
Current Status
Issued on 7/5/2024
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/16/2024 APPLICANT
Assigned to Plan Check Engineer 4/24/2024 ARTIN ZARUKIAN
Corrections Issued 4/29/2024 ARTIN ZARUKIAN
Building Plans Picked Up 4/29/2024 APPLICANT
Plan Check Approved 6/27/2024 ALEC MOUSAKHANIAN
Issued 7/5/2024 APPLICANT

Permit Application Clearance Information

Address approval Cleared 5/4/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 5/4/2024 CARLOS AGUILERA
Sewer availability Cleared 5/6/2024 CARLOS AGUILERA
Grading Pre-Inspection Cleared 5/7/2024 ROBERT PINA
Eng Process Fee Ord 176,300 Cleared 6/26/2024 CARLOS AGUILERA
GPI Written Notices Cleared 6/27/2024 ARTIN ZARUKIAN
Hydrant and Access approval Cleared 6/27/2024 KURT CORRAL

Contact Information

Contractor Sosa Remodeling & Construction; Lic. No.: 1036208-B 18757 LEADWELL ST      RESEDA, CA 91335

Inspector Information

JACK KARGODORIAN, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI
KRISTEN CAUSEY, (818) 774-4319 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 7/9/2024 Partial Approval DAVID SCANTLIN
Excavation/Setback/Form/Re-Bar 8/20/2024 Partial Approval DAVID SCANTLIN
Footing/Foundation/Slab 8/20/2024 Partial Approval DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 10/2/2024 Approved DAVID SCANTLIN
Footing/Foundation/Slab 10/2/2024 Approved DAVID SCANTLIN
BUILDING-Rough-Frame 11/4/2024 Not Ready for Inspection DAVID SCANTLIN
Floor/Roof Diaphrgm/Shear Wall 11/4/2024 Partial Approval DAVID SCANTLIN
Verify Sprinkler Sign Off 11/4/2024 Not Ready for Inspection DAVID SCANTLIN
Interior/Exterior Lathing 12/13/2024 Partial Approval DAVID SCANTLIN
BUILDING-Rough-Frame 4/15/2025 Approved DAVID SCANTLIN
Green Building Rough 4/15/2025 Approved DAVID SCANTLIN
Insulation 4/15/2025 Partial Approval DAVID SCANTLIN
Verify Sprinkler Sign Off 4/15/2025 Approved DAVID SCANTLIN
Drywall Nailing 5/1/2025 Approved DAVID SCANTLIN
ELECTRICAL-Final 6/4/2026 Not Ready for Inspection JACK KARGODORIAN
Final 6/4/2026 Corrections Issued JACK KARGODORIAN
Green Building Final 6/4/2026 Approved JACK KARGODORIAN
HVAC-Final 6/4/2026 Approved JACK KARGODORIAN
PLUMBING-Final 6/4/2026 Approved JACK KARGODORIAN
SGSOV-Seismic Gas S/O Valve 6/4/2026 SGSOV Not Ready JACK KARGODORIAN
Service/Power Release 6/4/2026 Corrections Issued JACK KARGODORIAN
Smoke Detectors 6/4/2026 Approved JACK KARGODORIAN