8827 N COLLETT AVE 91343
Certificate Information: 8827 N COLLETT AVE 91343
- Application / Permit
- 24010-20000-01554
- Plan Check / Job No.
- B24VN05060
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK PER WFPP
- Permit Issued
- Issued on 8/23/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 9/23/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2024 | JEROME MAGAT PALMA |
| Corrections Issued | 4/24/2024 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 4/29/2024 | APPLICANT |
| Plan Check Approved | 8/19/2024 | ARAMIK SHAHMIRZAIAN |
| Issued | 8/23/2024 | APPLICANT |
| CofO in Progress | 9/11/2025 | GAREN HAYRAPETYAN |
| CofO Issued | 9/23/2025 | RUBEN SALAS |
| Permit Finaled | 9/23/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/4/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 5/4/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 5/6/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 5/6/2024 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 8/9/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Simoni John Ioan; Lic. No.: 620256-B | P O BOX 2736 NORTH HILLS, CA 91393 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/8/2025 | Conditional Approval | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 4/8/2025 | Conditional Approval | SALVADOR MARTINEZ |
| PLUMBING-Rough | 4/8/2025 | Partial Approval | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/23/2025 | Approved | SALVADOR MARTINEZ |
| Wood Frame | 4/23/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 5/5/2025 | Corrections Issued | SALVADOR MARTINEZ |
| HVAC-Rough | 5/5/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 5/5/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Underground Mechanical | 5/5/2025 | Corrections Issued | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 5/8/2025 | Partial Approval | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 5/8/2025 | Partial Approval | SALVADOR MARTINEZ |
| Green Building Rough | 5/8/2025 | Approved | SALVADOR MARTINEZ |
| Sewer | 5/8/2025 | Approved | SALVADOR MARTINEZ |
| Underground Mechanical | 5/8/2025 | Partial Approval | SALVADOR MARTINEZ |
| Verify Sprinkler Sign Off | 5/8/2025 | Approved | SALVADOR MARTINEZ |
| Insulation | 5/16/2025 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 5/16/2025 | Partial Approval | RYAN SALAZAR |
| Drywall Nailing | 5/27/2025 | Approved | GAREN HAYRAPETYAN |
| Shower Pan | 5/27/2025 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 6/2/2025 | Approved | SALVADOR MARTINEZ |
| Underground Mechanical | 6/2/2025 | Approved | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 7/9/2025 | Corrections Issued | JOAQUIN GREENOUGH |
| PLUMBING-Final | 7/9/2025 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 7/16/2025 | Approved | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 7/16/2025 | Approved | SALVADOR MARTINEZ |
| Final | 7/16/2025 | OK to Issue CofO | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 7/16/2025 | Approved | SALVADOR MARTINEZ |
| Green Building Final | 7/16/2025 | Approved | SALVADOR MARTINEZ |
| HVAC-Final | 7/16/2025 | Approved | SALVADOR MARTINEZ |
| HVAC-Rough | 7/16/2025 | Approved | SALVADOR MARTINEZ |
| PLUMBING-Rough | 7/16/2025 | Approved | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 7/16/2025 | SGSOV No Gas | SALVADOR MARTINEZ |
| Service/Power Release | 7/16/2025 | Approved | SALVADOR MARTINEZ |
| Smoke Detectors | 7/16/2025 | Approved | SALVADOR MARTINEZ |