8827 N COLLETT AVE 91343

Certificate Information: 8827 N COLLETT AVE 91343

Application / Permit
24010-20000-01554
Plan Check / Job No.
B24VN05060
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK PER WFPP
Permit Issued
Issued on 8/23/2024
Issuing Office
Valley
Current Status
CofO Issued on 9/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/15/2024 APPLICANT
Assigned to Plan Check Engineer 4/22/2024 JEROME MAGAT PALMA
Corrections Issued 4/24/2024 JEROME MAGAT PALMA
Building Plans Picked Up 4/29/2024 APPLICANT
Plan Check Approved 8/19/2024 ARAMIK SHAHMIRZAIAN
Issued 8/23/2024 APPLICANT
CofO in Progress 9/11/2025 GAREN HAYRAPETYAN
CofO Issued 9/23/2025 RUBEN SALAS
Permit Finaled 9/23/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/4/2024 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 5/4/2024 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 5/6/2024 CARLOS AGUILERA
Sewer availability Cleared 5/6/2024 CARLOS AGUILERA
Construction near power lines Cleared 8/9/2024 RIDWAN HARDY

Contact Information

Contractor Simoni John Ioan; Lic. No.: 620256-B P O BOX 2736      NORTH HILLS, CA 91393

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI
WILLIAM WREN, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/8/2025 Conditional Approval SALVADOR MARTINEZ
Footing/Foundation/Slab 4/8/2025 Conditional Approval SALVADOR MARTINEZ
PLUMBING-Rough 4/8/2025 Partial Approval SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 4/23/2025 Approved SALVADOR MARTINEZ
Wood Frame 4/23/2025 Not Ready for Inspection SALVADOR MARTINEZ
ELECTRICAL-Rough 5/5/2025 Corrections Issued SALVADOR MARTINEZ
HVAC-Rough 5/5/2025 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 5/5/2025 Corrections Issued SALVADOR MARTINEZ
Underground Mechanical 5/5/2025 Corrections Issued SALVADOR MARTINEZ
BUILDING-Rough-Frame 5/8/2025 Partial Approval SALVADOR MARTINEZ
ELECTRICAL-Rough 5/8/2025 Partial Approval SALVADOR MARTINEZ
Green Building Rough 5/8/2025 Approved SALVADOR MARTINEZ
Sewer 5/8/2025 Approved SALVADOR MARTINEZ
Underground Mechanical 5/8/2025 Partial Approval SALVADOR MARTINEZ
Verify Sprinkler Sign Off 5/8/2025 Approved SALVADOR MARTINEZ
Insulation 5/16/2025 Approved RYAN SALAZAR
Interior/Exterior Lathing 5/16/2025 Partial Approval RYAN SALAZAR
Drywall Nailing 5/27/2025 Approved GAREN HAYRAPETYAN
Shower Pan 5/27/2025 Approved GAREN HAYRAPETYAN
Interior/Exterior Lathing 6/2/2025 Approved SALVADOR MARTINEZ
Underground Mechanical 6/2/2025 Approved SALVADOR MARTINEZ
ELECTRICAL-Final 7/9/2025 Corrections Issued JOAQUIN GREENOUGH
PLUMBING-Final 7/9/2025 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 7/16/2025 Approved SALVADOR MARTINEZ
ELECTRICAL-Final 7/16/2025 Approved SALVADOR MARTINEZ
Final 7/16/2025 OK to Issue CofO SALVADOR MARTINEZ
Footing/Foundation/Slab 7/16/2025 Approved SALVADOR MARTINEZ
Green Building Final 7/16/2025 Approved SALVADOR MARTINEZ
HVAC-Final 7/16/2025 Approved SALVADOR MARTINEZ
HVAC-Rough 7/16/2025 Approved SALVADOR MARTINEZ
PLUMBING-Rough 7/16/2025 Approved SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 7/16/2025 SGSOV No Gas SALVADOR MARTINEZ
Service/Power Release 7/16/2025 Approved SALVADOR MARTINEZ
Smoke Detectors 7/16/2025 Approved SALVADOR MARTINEZ