4048 N SHADYGLADE AVE 91604

Certificate Information: 4048 N SHADYGLADE AVE 91604

Application / Permit
24010-20000-01549
Plan Check / Job No.
B24VN05047
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 19'-3" X 41' ACCESSORY DWELLING UNIT LAMC 12.22 A.33 (c)-(d). NFPA 13D FIRE SPRINKLERS THROUGHOUT.
Permit Issued
Issued on 6/24/2024
Issuing Office
Valley
Current Status
CofO Issued on 6/25/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/15/2024 APPLICANT
Assigned to Plan Check Engineer 4/18/2024 RAPHAEL ROSAS
Corrections Issued 4/23/2024 RAPHAEL ROSAS
Quality Review Completed 4/23/2024 STEVEN KIM
Building Plans Picked Up 4/25/2024 APPLICANT
Applicant returned to address corrections 6/20/2024 RAPHAEL ROSAS
Plan Check Approved 6/24/2024 RAPHAEL ROSAS
Issued 6/24/2024 APPLICANT
CofO in Progress 6/18/2025 CHRISTOPHE COCHRAN
Permit Finaled 6/25/2025 RUBEN SALAS
CofO Issued 6/25/2025 RUBEN SALAS
Permit Finaled 6/25/2025 RUBEN SALAS

Permit Application Clearance Information

ZI Cleared 4/30/2024 BRENNEN OBETO
Address approval Cleared 5/1/2024 BIAINA HARITUNIAN
Eng Process Fee Ord 176,300 Cleared 5/6/2024 BIAINA HARITUNIAN
Sewer availability Cleared 5/6/2024 BIAINA HARITUNIAN
Low Impact Development (LID) Cleared 5/8/2024 SARAH YOUSSEF
Hydrant and Access approval Cleared 5/25/2024 KURT CORRAL
Roof/Waste drainage to street Cleared 5/29/2024 BIAINA HARITUNIAN
Construction near power lines Cleared 6/17/2024 ENRIQUE ACOSTA

Contact Information

Contractor Owner-Builder       ,
Engineer Nazari,, Arthur; Lic. No.: C53497 23300 POMPANO STREET      MALIBU, CA 90265

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/26/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Underground Mechanical 7/26/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Excavation/Setback/Form/Re-Bar 8/2/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Underground Mechanical 8/2/2024 Approved CHRISTOPHE COCHRAN
Footing/Foundation/Slab 8/7/2024 Approved CHRISTOPHE COCHRAN
Deputy Reinf. Concrete 8/8/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 9/3/2024 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 10/11/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 10/11/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
PLUMBING-Rough 10/11/2024 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 10/17/2024 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 10/17/2024 Corrections Issued CHRISTOPHE COCHRAN
HVAC-Rough 10/17/2024 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 10/24/2024 No Access for Inspection CHRISTOPHE COCHRAN
Shower Pan 10/24/2024 No Access for Inspection CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 11/7/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Green Building Rough 11/7/2024 Approved CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 11/7/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 11/19/2024 Partial Approval CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 11/19/2024 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 12/9/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 12/13/2024 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 12/13/2024 Partial Approval CHRISTOPHE COCHRAN
Insulation 12/18/2024 Not Ready for Inspection CHRISTOPHE COCHRAN
Interior/Exterior Lathing 12/18/2024 Corrections Issued CHRISTOPHE COCHRAN
Insulation 12/24/2024 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 12/24/2024 Not Ready for Inspection MICHAEL CORTEZ
Interior/Exterior Lathing 12/30/2024 Approved LOUIS ESCOTO
Drywall Nailing 1/14/2025 Approved MICHAEL CORTEZ
Rough-Elec/Plmb/HVAC 5/20/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
Final 5/23/2025 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 5/23/2025 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 5/23/2025 SGSOV Not Required CHRISTOPHE COCHRAN
Service/Power Release 5/23/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
Smoke Detectors 5/23/2025 Approved CHRISTOPHE COCHRAN
Final 6/4/2025 Corrections Issued CHRISTOPHE COCHRAN
Final 6/6/2025 Conditional Approval CHRISTOPHE COCHRAN
Service/Power Release 6/6/2025 Not Ready for Inspection CHRISTOPHE COCHRAN
Final 6/18/2025 OK to Issue CofO CHRISTOPHE COCHRAN
Service/Power Release 6/18/2025 Approved CHRISTOPHE COCHRAN