4046 N SHADYGLADE AVE 91604
Certificate Information: 4046 N SHADYGLADE AVE 91604
- Application / Permit
- 24010-20000-01548
- Plan Check / Job No.
- B24VN05047
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 38' X 60' IRREGULAR SHAPED 2-STORY SFD W/ 2-CAR GARAGE NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 6/24/2024
- Issuing Office
- Valley
- Current Status
- CofO Issued on 6/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/15/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/18/2024 | RAPHAEL ROSAS |
| Corrections Issued | 4/23/2024 | RAPHAEL ROSAS |
| Quality Review Completed | 4/23/2024 | STEVEN KIM |
| Building Plans Picked Up | 4/25/2024 | APPLICANT |
| Applicant returned to address corrections | 6/20/2024 | RAPHAEL ROSAS |
| Plan Check Approved | 6/24/2024 | RAPHAEL ROSAS |
| Issued | 6/24/2024 | APPLICANT |
| CofO in Progress | 6/18/2025 | CHRISTOPHE COCHRAN |
| Permit Finaled | 6/25/2025 | RUBEN SALAS |
| CofO Issued | 6/25/2025 | RUBEN SALAS |
| Permit Finaled | 6/25/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 5/1/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 5/6/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 5/6/2024 | BIAINA HARITUNIAN |
| Low Impact Development (LID) | Cleared | 5/7/2024 | SARAH YOUSSEF |
| Hydrant and Access approval | Cleared | 5/25/2024 | KURT CORRAL |
| Roof/Waste drainage to street | Cleared | 5/29/2024 | BIAINA HARITUNIAN |
| Trees in Parkway | Cleared | 6/5/2024 | ADALBERTO VERA |
| ZI | Cleared | 6/6/2024 | BRENNEN OBETO |
| Permit | Cleared | 6/17/2024 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nazari,, Arthur; Lic. No.: C53497 | 23300 POMPANO STREET MALIBU, CA 90265 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/26/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 7/26/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Underground Mechanical | 7/26/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Excavation/Setback/Form/Re-Bar | 8/2/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Underground Mechanical | 8/2/2024 | Approved | CHRISTOPHE COCHRAN |
| Excavation/Setback/Form/Re-Bar | 8/5/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 8/7/2024 | Approved | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Deputy Wood Construction | 9/3/2024 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 9/3/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 10/11/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/11/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| PLUMBING-Rough | 10/11/2024 | Approved | CHRISTOPHE COCHRAN |
| ELECTRICAL-Rough | 10/17/2024 | Approved | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2024 | Approved | CHRISTOPHE COCHRAN |
| HVAC-Rough | 10/17/2024 | Approved | CHRISTOPHE COCHRAN |
| Deputy Wood Construction | 10/22/2024 | Conditional Approval | JUAN VALENZUELA |
| Shower Pan | 10/25/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Shower Pan | 10/30/2024 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 11/5/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Shower Pan | 11/7/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Sewer | 11/15/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Shower Pan | 11/15/2024 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 11/19/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Green Building Rough | 11/19/2024 | Approved | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 11/19/2024 | Approved | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 12/9/2024 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| BUILDING-Rough-Frame | 12/13/2024 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 12/13/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Insulation | 12/18/2024 | Corrections Issued | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 12/18/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Insulation | 12/24/2024 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 12/24/2024 | Not Ready for Inspection | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 12/30/2024 | Approved | LOUIS ESCOTO |
| Drywall Nailing | 1/14/2025 | Approved | MICHAEL CORTEZ |
| Rough-Elec/Plmb/HVAC | 5/20/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Final | 5/23/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| Green Building Final | 5/23/2025 | Approved | CHRISTOPHE COCHRAN |
| Service/Power Release | 5/23/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Smoke Detectors | 5/23/2025 | Approved | CHRISTOPHE COCHRAN |
| Final | 6/4/2025 | Corrections Issued | CHRISTOPHE COCHRAN |
| Final | 6/6/2025 | Conditional Approval | CHRISTOPHE COCHRAN |
| Service/Power Release | 6/6/2025 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Final | 6/18/2025 | OK to Issue CofO | CHRISTOPHE COCHRAN |
| Service/Power Release | 6/18/2025 | Approved | CHRISTOPHE COCHRAN |