6549 N RADFORD AVE 91606

Certificate Information: 6549 N RADFORD AVE 91606

Application / Permit
24010-20000-01546
Plan Check / Job No.
B24VN03659
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(N) 1-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(d) (NFPA-13D FIRE SPRINKLERS THROUGHOUT) **ePlan**
Permit Issued
Issued on 10/8/2024
Issuing Office
Current Status
CofO Issued on 9/11/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/21/2024 APPLICANT
Assigned to Plan Check Engineer 4/4/2024 NILOOFAR MEHRAIN
Corrections Issued 4/15/2024 NILOOFAR MEHRAIN
Quality Review Completed 4/26/2024 JASON HEALEY
Applicant returned to address corrections 8/8/2024 NILOOFAR MEHRAIN
Applicant returned to address corrections 10/3/2024 NILOOFAR MEHRAIN
Plan Check Approved 10/8/2024 NILOOFAR MEHRAIN
Issued 10/8/2024 APPLICANT
CofO in Progress 7/29/2025 ROBERTO PALACIOS-LOPEZ
Permit Finaled 9/11/2025 RUBEN SALAS
CofO Issued 9/11/2025 RUBEN SALAS
Permit Finaled 9/11/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 5/20/2024 EDGAR ALCARAZ
Eng Process Fee Ord 176,300 Cleared 5/21/2024 EDGAR ALCARAZ
Construction near power lines Cleared 6/16/2024 WALTER RAMIREZ
Construction within easement Cleared 6/16/2024 WALTER RAMIREZ
Sewer availability Cleared 6/17/2024 EDGAR ALCARAZ
Low Impact Development (LID) Cleared 6/24/2024 LUIS LUVANO
Roof/Waste drainage to street Cleared 7/23/2024 EDGAR ALCARAZ
Hydrant and Access approval Cleared 7/24/2024 JOHN CONNEALLY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/25/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 10/25/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Excavation/Setback/Form/Re-Bar 10/30/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 10/30/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Footing/Foundation/Slab 11/15/2024 Approved ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 12/4/2024 Partial Approval ROBERTO PALACIOS-LOPEZ
Sewer 12/4/2024 Approved ROBERTO PALACIOS-LOPEZ
BUILDING-Rough-Frame 12/12/2024 Partial Inspection MISAEL ESPARZA
ELECTRICAL-Rough 12/12/2024 Partial Inspection MISAEL ESPARZA
Green Building Rough 12/12/2024 Partial Inspection MISAEL ESPARZA
HVAC-Rough 12/12/2024 Partial Inspection MISAEL ESPARZA
PLUMBING-Rough 12/12/2024 Partial Inspection MISAEL ESPARZA
Verify Sprinkler Sign Off 12/12/2024 Partial Inspection MISAEL ESPARZA
BUILDING-Rough-Frame 12/16/2024 Conditional Approval ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Rough 12/16/2024 Approved ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 12/16/2024 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 12/16/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
PLUMBING-Rough 12/16/2024 Approved ROBERTO PALACIOS-LOPEZ
Insulation 12/24/2024 Approved MICHAEL CORTEZ
Interior/Exterior Lathing 12/24/2024 Partial Approval MICHAEL CORTEZ
Shower Pan 12/24/2024 Corrections Issued MICHAEL CORTEZ
BUILDING-Rough-Frame 12/30/2024 Approved ROBERTO PALACIOS-LOPEZ
Drywall Nailing 12/30/2024 Approved ROBERTO PALACIOS-LOPEZ
Green Building Rough 12/30/2024 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Rough 12/30/2024 Approved ROBERTO PALACIOS-LOPEZ
Shower Pan 12/30/2024 Approved ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 12/30/2024 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 1/7/2025 Approved ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 4/4/2025 Not Ready for Inspection JOSE AVILA
ELECTRICAL-Final 4/7/2025 Conditional Approval JOSE AVILA
ELECTRICAL-Final 7/2/2025 Approved ROBERTO PALACIOS-LOPEZ
HVAC-Final 7/2/2025 Approved ROBERTO PALACIOS-LOPEZ
PLUMBING-Final 7/2/2025 Approved ROBERTO PALACIOS-LOPEZ
Final 7/29/2025 OK to Issue CofO ROBERTO PALACIOS-LOPEZ
Green Building Final 7/29/2025 Approved ROBERTO PALACIOS-LOPEZ
SGSOV-Seismic Gas S/O Valve 7/29/2025 SGSOV Not Required ROBERTO PALACIOS-LOPEZ
Service/Power Release 7/29/2025 Approved ROBERTO PALACIOS-LOPEZ
Smoke Detectors 7/29/2025 Approved ROBERTO PALACIOS-LOPEZ