18001 W RAYEN ST 91325

Certificate Information: 18001 W RAYEN ST 91325

Application / Permit
24010-20000-01530
Plan Check / Job No.
B24VN05005
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 59'-6" X 21'-6" ONE STORY DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d).
Permit Issued
Issued on 5/23/2024
Issuing Office
Valley
Current Status
CofO Issued on 5/23/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/15/2024 APPLICANT
Assigned to Plan Check Engineer 4/22/2024 ARTIN ZARUKIAN
Corrections Issued 4/22/2024 ARTIN ZARUKIAN
Building Plans Picked Up 4/25/2024 APPLICANT
Plan Check Approved 5/23/2024 ISIS ARGUETA
Issued 5/23/2024 APPLICANT
CofO in Progress 5/21/2025 CHRISTOPHER ROJAS
CofO Issued 5/23/2025 RUBEN SALAS
Permit Finaled 5/23/2025 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/29/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 4/29/2024 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 4/29/2024 LEE GUILBEAUX
Sewer availability Cleared 4/29/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 4/29/2024 LEE GUILBEAUX

Contact Information

Contractor Owner-Builder       ,
Engineer Rhee,, Kyle; Lic. No.: C78215 2753 WAVERLY DR 403      LOS ANGELES, CA 90039

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/24/2024 Partial Approval JAVIER RAMOS JR
Pre-Inspection 7/24/2024 Approved JAVIER RAMOS JR
Excavation/Setback/Form/Re-Bar 8/9/2024 Partial Approval JAVIER RAMOS JR
Footing/Foundation/Slab 8/9/2024 Corrections Issued JAVIER RAMOS JR
Footing/Foundation/Slab 8/14/2024 Approved JAVIER RAMOS JR
BUILDING-Rough-Frame 10/18/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 10/18/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Green Building Rough 10/18/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Special/Order Compliance 10/18/2024 Corrections Issued ROBERTO PALACIOS-LOPEZ
Verify Sprinkler Sign Off 10/18/2024 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
Floor/Roof Diaphrgm/Shear Wall 10/31/2024 Partial Approval JACK KARGODORIAN
BUILDING-Rough-Frame 11/4/2024 Approved KEVIN BERBERYAN
Green Building Rough 11/4/2024 Not Ready for Inspection KEVIN BERBERYAN
Rough-Elec/Plmb/HVAC 11/4/2024 Corrections Issued KEVIN BERBERYAN
Verify Sprinkler Sign Off 11/4/2024 Approved KEVIN BERBERYAN
BUILDING-Rough-Frame 11/12/2024 Approved JAVIER RAMOS JR
ELECTRICAL-Rough 11/12/2024 Approved JAVIER RAMOS JR
Floor/Roof Diaphrgm/Shear Wall 11/12/2024 Approved JAVIER RAMOS JR
Green Building Rough 11/12/2024 Approved JAVIER RAMOS JR
HVAC-Rough 11/12/2024 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 11/12/2024 Partial Approval JAVIER RAMOS JR
PLUMBING-Rough 11/12/2024 Approved JAVIER RAMOS JR
Insulation 11/19/2024 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 11/19/2024 Approved JAVIER RAMOS JR
Shower Pan 11/19/2024 Approved JAVIER RAMOS JR
Drywall Nailing 11/25/2024 Approved ROBERT GOLD
ELECTRICAL-Final 3/19/2025 Approved JAVIER RAMOS JR
Final 3/19/2025 Corrections Issued JAVIER RAMOS JR
Green Building Final 3/19/2025 Not Ready for Inspection JAVIER RAMOS JR
HVAC-Final 3/19/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 3/19/2025 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 3/19/2025 SGSOV Not Required JAVIER RAMOS JR
Smoke Detectors 3/19/2025 Approved JAVIER RAMOS JR
Final 5/21/2025 OK to Issue CofO CHRISTOPHER ROJAS
Green Building Final 5/21/2025 Approved CHRISTOPHER ROJAS
Service/Power Release 5/21/2025 Approved CHRISTOPHER ROJAS