11554-11556 W BLIX ST 91602

Certificate Information: 11554-11556 W BLIX ST 91602

Application / Permit
24010-20000-01517
Plan Check / Job No.
B24VN04985
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 48' X 72'-6" SINGLE FAMILY DWELLING W/ ATTACHED ACCESSORY DWELLING UNIT AND 2-CAR GARAGE. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 6/20/2024
Issuing Office
Current Status
CofO Issued on 3/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/12/2024 APPLICANT
Assigned to Plan Check Engineer 4/18/2024 RAPHAEL ROSAS
Corrections Issued 4/23/2024 RAPHAEL ROSAS
Quality Review Completed 4/23/2024 STEVEN KIM
Building Plans Picked Up 4/25/2024 APPLICANT
Applicant returned to address corrections 6/6/2024 RAPHAEL ROSAS
Plan Check Approved 6/20/2024 RAPHAEL ROSAS
Issued 6/20/2024 APPLICANT
CofO in Progress 2/25/2025 CHRISTOPHER ROJAS
Permit Finaled 3/13/2025 RUBEN SALAS
CofO Issued 3/13/2025 RUBEN SALAS
Permit Finaled 3/13/2025 RUBEN SALAS

Permit Application Clearance Information

Low Impact Development (LID) Cleared 4/30/2024 MARTIN FRAGOSO
Address approval Cleared 5/1/2024 LEE GUILBEAUX
Permit Cleared 5/1/2024 LEE GUILBEAUX
Roof/Waste drainage to street Cleared 5/1/2024 LEE GUILBEAUX
Public Works-Highway Ded. Cleared 5/1/2024 LEE GUILBEAUX
Eng Process Fee Ord 176,300 Cleared 5/6/2024 LEE GUILBEAUX
Sewer availability Cleared 5/6/2024 LEE GUILBEAUX
Specific Plan Cleared 5/8/2024 JOANNA MARROQUIN
ZI Cleared 5/8/2024 JOANNA MARROQUIN
ZI Cleared 5/8/2024 JOANNA MARROQUIN
Trees in Parkway Cleared 5/21/2024 ADALBERTO VERA
Hydrant and Access approval Cleared 5/30/2024 GILBERT URREA

Contact Information

Contractor Owner-Builder       ,
Engineer Nazari,, Arthur; Lic. No.: C53497 23300 POMPANO STREET      MALIBU, CA 90265

Inspector Information

JAVIER RAMOS JR, (818) 374-1163 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/10/2024 Partial Approval CHRISTOPHER ROJAS
PLUMBING-Rough 7/10/2024 Corrections Issued CHRISTOPHER ROJAS
Structural Steel Frame 7/10/2024 Partial Approval CHRISTOPHER ROJAS
Underground Mechanical 7/10/2024 Approved CHRISTOPHER ROJAS
Deputy Reinf. Concrete 7/11/2024 Conditional Approval JUAN VALENZUELA
Footing/Foundation/Slab 7/15/2024 Approved CHRISTOPHER ROJAS
Excavation/Setback/Form/Re-Bar 7/18/2024 Partial Approval JUAN VALENZUELA
Underground Mechanical 7/18/2024 Corrections Issued CHRISTOPHER ROJAS
Floor/Roof Diaphrgm/Shear Wall 7/25/2024 Partial Approval SALVADOR MARTINEZ
Deputy Wood Construction 7/26/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 8/8/2024 Corrections Issued CHRISTOPHER ROJAS
Deputy Steel/Welding 8/9/2024 Conditional Approval ROBERT GOLD
Deputy Wood Construction 8/9/2024 Conditional Approval ROBERT GOLD
Deputy Wood Construction 8/22/2024 Conditional Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 8/22/2024 Partial Approval CHRISTOPHER ROJAS
HVAC-Rough 8/22/2024 Corrections Issued CHRISTOPHER ROJAS
PLUMBING-Rough 8/22/2024 Approved CHRISTOPHER ROJAS
ELECTRICAL-Rough 8/29/2024 Approved CHRISTOPHER ROJAS
HVAC-Rough 8/29/2024 Approved CHRISTOPHER ROJAS
BUILDING-Rough-Frame 9/5/2024 Approved CHRISTOPHER ROJAS
Green Building Rough 9/5/2024 Approved CHRISTOPHER ROJAS
MERV13>=Rough 9/5/2024 Approved CHRISTOPHER ROJAS
Verify Sprinkler Sign Off 9/5/2024 Approved CHRISTOPHER ROJAS
Insulation 9/11/2024 Approved CHRISTOPHER ROJAS
Interior/Exterior Lathing 9/11/2024 Approved CHRISTOPHER ROJAS
Shower Pan 9/11/2024 Approved CHRISTOPHER ROJAS
Drywall Nailing 9/16/2024 Not Ready for Inspection CHRISTOPHER ROJAS
Drywall Nailing 9/23/2024 Approved CHRISTOPHER ROJAS
Final 9/23/2024 Corrections Issued CHRISTOPHER ROJAS
Final 1/22/2025 Corrections Issued CHRISTOPHER ROJAS
Green Building Final 1/22/2025 Partial Inspection CHRISTOPHER ROJAS
MERV13>=Final 1/22/2025 Approved CHRISTOPHER ROJAS
Service/Power Release 1/22/2025 Partial Inspection CHRISTOPHER ROJAS
Smoke Detectors 1/22/2025 Approved CHRISTOPHER ROJAS
Final 2/6/2025 Partial Inspection CHRISTOPHER ROJAS
Green Building Final 2/6/2025 Approved CHRISTOPHER ROJAS
Service/Power Release 2/6/2025 Approved CHRISTOPHER ROJAS
Final 2/24/2025 OK to Issue CofO CHRISTOPHER ROJAS