11554-11556 W BLIX ST 91602
Certificate Information: 11554-11556 W BLIX ST 91602
- Application / Permit
- 24010-20000-01517
- Plan Check / Job No.
- B24VN04985
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 48' X 72'-6" SINGLE FAMILY DWELLING W/ ATTACHED ACCESSORY DWELLING UNIT AND 2-CAR GARAGE. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 6/20/2024
- Issuing Office
- Current Status
- CofO Issued on 3/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/12/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/18/2024 | RAPHAEL ROSAS |
| Corrections Issued | 4/23/2024 | RAPHAEL ROSAS |
| Quality Review Completed | 4/23/2024 | STEVEN KIM |
| Building Plans Picked Up | 4/25/2024 | APPLICANT |
| Applicant returned to address corrections | 6/6/2024 | RAPHAEL ROSAS |
| Plan Check Approved | 6/20/2024 | RAPHAEL ROSAS |
| Issued | 6/20/2024 | APPLICANT |
| CofO in Progress | 2/25/2025 | CHRISTOPHER ROJAS |
| Permit Finaled | 3/13/2025 | RUBEN SALAS |
| CofO Issued | 3/13/2025 | RUBEN SALAS |
| Permit Finaled | 3/13/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Low Impact Development (LID) | Cleared | 4/30/2024 | MARTIN FRAGOSO |
| Address approval | Cleared | 5/1/2024 | LEE GUILBEAUX |
| Permit | Cleared | 5/1/2024 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 5/1/2024 | LEE GUILBEAUX |
| Public Works-Highway Ded. | Cleared | 5/1/2024 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 5/6/2024 | LEE GUILBEAUX |
| Sewer availability | Cleared | 5/6/2024 | LEE GUILBEAUX |
| Specific Plan | Cleared | 5/8/2024 | JOANNA MARROQUIN |
| ZI | Cleared | 5/8/2024 | JOANNA MARROQUIN |
| ZI | Cleared | 5/8/2024 | JOANNA MARROQUIN |
| Trees in Parkway | Cleared | 5/21/2024 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 5/30/2024 | GILBERT URREA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nazari,, Arthur; Lic. No.: C53497 | 23300 POMPANO STREET MALIBU, CA 90265 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/10/2024 | Partial Approval | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 7/10/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Structural Steel Frame | 7/10/2024 | Partial Approval | CHRISTOPHER ROJAS |
| Underground Mechanical | 7/10/2024 | Approved | CHRISTOPHER ROJAS |
| Deputy Reinf. Concrete | 7/11/2024 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 7/15/2024 | Approved | CHRISTOPHER ROJAS |
| Excavation/Setback/Form/Re-Bar | 7/18/2024 | Partial Approval | JUAN VALENZUELA |
| Underground Mechanical | 7/18/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Floor/Roof Diaphrgm/Shear Wall | 7/25/2024 | Partial Approval | SALVADOR MARTINEZ |
| Deputy Wood Construction | 7/26/2024 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Deputy Steel/Welding | 8/9/2024 | Conditional Approval | ROBERT GOLD |
| Deputy Wood Construction | 8/9/2024 | Conditional Approval | ROBERT GOLD |
| Deputy Wood Construction | 8/22/2024 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 8/22/2024 | Partial Approval | CHRISTOPHER ROJAS |
| HVAC-Rough | 8/22/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| PLUMBING-Rough | 8/22/2024 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Rough | 8/29/2024 | Approved | CHRISTOPHER ROJAS |
| HVAC-Rough | 8/29/2024 | Approved | CHRISTOPHER ROJAS |
| BUILDING-Rough-Frame | 9/5/2024 | Approved | CHRISTOPHER ROJAS |
| Green Building Rough | 9/5/2024 | Approved | CHRISTOPHER ROJAS |
| MERV13>=Rough | 9/5/2024 | Approved | CHRISTOPHER ROJAS |
| Verify Sprinkler Sign Off | 9/5/2024 | Approved | CHRISTOPHER ROJAS |
| Insulation | 9/11/2024 | Approved | CHRISTOPHER ROJAS |
| Interior/Exterior Lathing | 9/11/2024 | Approved | CHRISTOPHER ROJAS |
| Shower Pan | 9/11/2024 | Approved | CHRISTOPHER ROJAS |
| Drywall Nailing | 9/16/2024 | Not Ready for Inspection | CHRISTOPHER ROJAS |
| Drywall Nailing | 9/23/2024 | Approved | CHRISTOPHER ROJAS |
| Final | 9/23/2024 | Corrections Issued | CHRISTOPHER ROJAS |
| Final | 1/22/2025 | Corrections Issued | CHRISTOPHER ROJAS |
| Green Building Final | 1/22/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| MERV13>=Final | 1/22/2025 | Approved | CHRISTOPHER ROJAS |
| Service/Power Release | 1/22/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| Smoke Detectors | 1/22/2025 | Approved | CHRISTOPHER ROJAS |
| Final | 2/6/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| Green Building Final | 2/6/2025 | Approved | CHRISTOPHER ROJAS |
| Service/Power Release | 2/6/2025 | Approved | CHRISTOPHER ROJAS |
| Final | 2/24/2025 | OK to Issue CofO | CHRISTOPHER ROJAS |