12709 W GAULT ST 91605
Certificate Information: 12709 W GAULT ST 91605
- Application / Permit
- 24010-20000-01512
- Plan Check / Job No.
- B24VN04967
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 41'-0" X 31'-0" DETACHED ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d).
- Permit Issued
- Issued on 7/5/2024
- Issuing Office
- Current Status
- CofO Issued on 4/24/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/12/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/19/2024 | ARTIN ZARUKIAN |
| Corrections Issued | 4/20/2024 | ARTIN ZARUKIAN |
| Building Plans Picked Up | 4/22/2024 | APPLICANT |
| Plan Check Approved | 7/2/2024 | ALEC MOUSAKHANIAN |
| No Progress | 7/2/2024 | ALEC MOUSAKHANIAN |
| Plan Check Approved | 7/2/2024 | ALEC MOUSAKHANIAN |
| Issued | 7/5/2024 | APPLICANT |
| CofO in Progress | 4/11/2025 | OGANES TARAKHCHYAN |
| Permit Finaled | 4/24/2025 | RUBEN SALAS |
| CofO Issued | 4/24/2025 | RUBEN SALAS |
| Permit Finaled | 4/24/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/23/2024 | BIAINA HARITUNIAN |
| Eng Process Fee Ord 176,300 | Cleared | 4/23/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 4/23/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 6/3/2024 | BIAINA HARITUNIAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/22/2024 | Partial Approval | JOSE AVILA |
| Footing/Foundation/Slab | 7/25/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 7/30/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Footing/Foundation/Slab | 8/23/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Pre-Inspection | 8/23/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 8/28/2024 | Corrections Issued | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 8/28/2024 | Partial Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 8/28/2024 | Approved | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 9/23/2024 | Approved | OGANES TARAKHCHYAN |
| Verify Sprinkler Sign Off | 9/23/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 10/2/2024 | Approved | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 11/1/2024 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Green Building Rough | 11/1/2024 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| HVAC-Rough | 11/1/2024 | Corrections Issued | GAREN HAYRAPETYAN |
| PLUMBING-Rough | 11/1/2024 | Corrections Issued | GAREN HAYRAPETYAN |
| Verify Sprinkler Sign Off | 11/1/2024 | Approved | GAREN HAYRAPETYAN |
| ELECTRICAL-Rough | 11/19/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| HVAC-Rough | 11/19/2024 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 11/19/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Sewer | 11/19/2024 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 11/25/2024 | Approved | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 12/2/2024 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 12/2/2024 | Approved | OGANES TARAKHCHYAN |
| Insulation | 12/12/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 12/12/2024 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 12/20/2024 | Approved | OGANES TARAKHCHYAN |
| Shower Pan | 1/30/2025 | Approved | MICHAEL CORTEZ |
| Interior/Exterior Lathing | 2/12/2025 | Approved | MICHAEL CORTEZ |
| Final | 3/4/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Final | 3/4/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Smoke Detectors | 3/4/2025 | Approved | OGANES TARAKHCHYAN |
| Final | 3/11/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Final | 3/11/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Final | 4/1/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Final | 4/4/2025 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Service/Power Release | 4/4/2025 | Approved | OGANES TARAKHCHYAN |
| Final | 4/10/2025 | OK to Issue CofO | OGANES TARAKHCHYAN |
| Green Building Final | 4/10/2025 | Approved | OGANES TARAKHCHYAN |