23445 W CALABASAS ROAD 91302
Certificate Information: 23445 W CALABASAS ROAD 91302
- Application / Permit
- 24010-20000-01511
- Plan Check / Job No.
- B24VN04964
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (23) Accessory Building (to permitted use)
- Work Description
- (N) DETACHED 1-STORY RESTROOM BLDG
- Permit Issued
- Issued on 9/8/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/23/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/12/2024 | APPLICANT |
| Assigned to Zoning Architect | 4/18/2024 | ERIC ROMERO |
| Assigned to Plan Check Engineer | 4/18/2024 | PETER MOSESIAN |
| Corrections Issued | 4/21/2024 | PETER MOSESIAN |
| Quality Review Completed | 4/24/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 5/2/2024 | APPLICANT |
| Disabled Access Plans Picked Up | 5/17/2024 | APPLICANT |
| Green Plans Picked Up | 5/17/2024 | APPLICANT |
| Plan Check Approved | 9/3/2025 | ALFRED RAMIREZ |
| Issued | 9/8/2025 | APPLICANT |
| CofO in Progress | 4/1/2026 | ROBERT DAVIS |
| Permit Finaled | 4/23/2026 | RICKEY JACKSON |
| CofO Issued | 4/23/2026 | RICKEY JACKSON |
| Permit Finaled | 4/23/2026 | RICKEY JACKSON |
Permit Application Clearance Information
| City Hist. Cultural Monument | Cleared | 4/30/2024 | LAMBERT GIESSINGER |
| Historic monument | Cleared | 4/30/2024 | LAMBERT GIESSINGER |
| ZA Case | Cleared | 6/20/2024 | JACQUELINE TORRES |
| ZA Case | Cleared | 6/20/2024 | JACQUELINE TORRES |
| ZA Case | Cleared | 6/20/2024 | JACQUELINE TORRES |
| ZA Case | Cleared | 6/20/2024 | JACQUELINE TORRES |
| ZA Case | Cleared | 6/20/2024 | JACQUELINE TORRES |
| Eng Process Fee Ord 176,300 | Cleared | 6/21/2024 | TAL SHEMEN |
| Roof/Waste drainage to street | Cleared | 6/21/2024 | TAL SHEMEN |
| Watercourse | Cleared | 6/21/2024 | TAL SHEMEN |
| ZA Case | Cleared | 6/26/2024 | JACQUELINE TORRES |
| ZA Case | Cleared | 6/26/2024 | JACQUELINE TORRES |
| Comm Cor/Mini-Mall | Cleared | 6/27/2024 | DANIEL CORONADO |
| Comm Cor/Mini-Mall | Cleared | 6/27/2024 | DANIEL CORONADO |
| Comm Cor/Mini-Mall | Cleared | 6/27/2024 | JACQUELINE TORRES |
| ZI | Cleared | 6/27/2024 | DANIEL CORONADO |
| Green Code | Cleared | 9/10/2024 | MICHAEL AYERS |
| Grading Pre-Inspection | Cleared | 10/4/2024 | PETER MOSESIAN |
| DAS Clearance | Cleared | 10/24/2024 | OLLIE CARTER |
| Flood clearance | Cleared | 7/23/2025 | ELYSE GREPO |
| Zoning Plan Check | Cleared | 8/25/2025 | PETER MOSESIAN |
Contact Information
| Contractor | Gordon Hodgson Construction Inc; Lic. No.: 864086-B | 9800 D TOPANGA CANYON BLVD #346 CHATSWORTH, CA 91311 |
| Engineer | Castillo,, Margarito; Lic. No.: S4808 | 1205 PINE AVE SUITE 201 LONG BEACH, CA 90813 |
Inspector Information
| ROBERT DAVIS, (818) 374-1125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 11/4/2025 | Partial Approval | BRIAN KELLY |
| Deputy Drilled-In Anchors | 11/13/2025 | Conditional Approval | GREGORY POMISH |
| Footing/Foundation/Slab | 11/13/2025 | Not Ready for Inspection | GREGORY POMISH |
| Footing/Foundation/Slab | 12/1/2025 | Partial Approval | ROBERT DAVIS |
| Deputy Drilled-In Anchors | 12/8/2025 | Conditional Approval | BRIAN KELLY |
| Footing/Foundation/Slab | 12/8/2025 | Approved | BRIAN KELLY |
| Green Building Rough | 2/6/2026 | Approved | ROBERT DAVIS |
| Verify Sprinkler Sign Off | 2/6/2026 | Partial Inspection | ROBERT DAVIS |
| Wood Frame | 2/6/2026 | Conditional Approval | ROBERT DAVIS |
| Interior/Exterior Lathing | 3/10/2026 | Partial Approval | ROBERT DAVIS |
| Drywall Nailing | 3/26/2026 | Approved | ROBERT DAVIS |
| Final | 3/26/2026 | OK to Issue CofO | ROBERT DAVIS |
| Green Building Final | 3/26/2026 | Approved | ROBERT DAVIS |
| SGSOV-Seismic Gas S/O Valve | 3/26/2026 | SGSOV No Gas | ROBERT DAVIS |
| Smoke Detectors | 3/26/2026 | Approved | ROBERT DAVIS |
| Verify Sprinkler Sign Off | 3/26/2026 | Approved | ROBERT DAVIS |
| Wood Frame | 3/26/2026 | Approved | ROBERT DAVIS |