8911 N SWINTON AVE 91343
Certificate Information: 8911 N SWINTON AVE 91343
- Application / Permit
- 24010-20000-01436
- Plan Check / Job No.
- B24VN04708
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: New 2-story (43'-4" x 28'-1.5" Irregular Shape) Accessory Building with an Accessory Dwelling Unit per LAMC 12.22 A.33 (c) - (d), Storage and a 1-Car Garage
- Permit Issued
- Issued on 6/27/2024
- Issuing Office
- Current Status
- CofO Issued on 7/11/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/9/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/18/2024 | VAHAN JIVALAGIAN |
| Corrections Issued | 4/19/2024 | VAHAN JIVALAGIAN |
| Quality Review Completed | 4/24/2024 | OMID HEDAYAT |
| Applicant returned to address corrections | 5/31/2024 | VAHAN JIVALAGIAN |
| Applicant returned to address corrections | 6/21/2024 | VAHAN JIVALAGIAN |
| Applicant returned to address corrections | 6/25/2024 | VAHAN JIVALAGIAN |
| Plan Check Approved | 6/26/2024 | VAHAN JIVALAGIAN |
| Issued | 6/27/2024 | APPLICANT |
| CofO in Progress | 6/13/2025 | SALVADOR MARTINEZ |
| Permit Finaled | 7/11/2025 | RUBEN SALAS |
| CofO Issued | 7/11/2025 | RUBEN SALAS |
| Permit Finaled | 7/11/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/25/2024 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 4/25/2024 | CARLOS AGUILERA |
| Sewer availability | Cleared | 4/25/2024 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 5/2/2024 | CARLOS AGUILERA |
| Construction within easement | Cleared | 6/12/2024 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Vasquez,, Luis Fernando; Lic. No.: C56232 | 375 LA MIRADA AVENUE SAN MARINO, CA 91108 |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/12/2024 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Rough | 7/12/2024 | Conditional Approval | RAUL OLAGI |
| Footing/Foundation/Slab | 7/18/2024 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 7/22/2024 | Corrections Issued | RAUL OLAGI |
| Footing/Foundation/Slab | 7/23/2024 | Approved | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2024 | Partial Approval | RAUL OLAGI |
| Sewer | 10/11/2024 | Approved | RAUL OLAGI |
| Deputy Wood Construction | 12/10/2024 | Conditional Approval | RAUL OLAGI |
| Special/Order Compliance | 12/27/2024 | Corrections Issued | RAUL OLAGI |
| Floor/Roof Diaphrgm/Shear Wall | 1/2/2025 | Corrections Issued | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 1/15/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 1/15/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/15/2025 | Approved | SALVADOR MARTINEZ |
| PLUMBING-Rough | 1/15/2025 | Approved | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 1/21/2025 | Approved | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 1/27/2025 | Partial Approval | SALVADOR MARTINEZ |
| Shower Pan | 1/27/2025 | Approved | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 1/31/2025 | Approved | SALVADOR MARTINEZ |
| HVAC-Rough | 2/12/2025 | Partial Approval | GAREN HAYRAPETYAN |
| BUILDING-Rough-Frame | 2/14/2025 | Conditional Approval | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 2/19/2025 | Approved | SALVADOR MARTINEZ |
| Green Building Rough | 2/19/2025 | Approved | SALVADOR MARTINEZ |
| Verify Sprinkler Sign Off | 2/19/2025 | Approved | SALVADOR MARTINEZ |
| Insulation | 2/28/2025 | Partial Approval | SALVADOR MARTINEZ |
| Drywall Nailing | 3/7/2025 | Approved | LOUIS ESCOTO |
| Insulation | 3/7/2025 | Approved | LOUIS ESCOTO |
| Pre-Inspection | 3/18/2025 | Partial Inspection | RAUL OLAGI |
| ELECTRICAL-Final | 5/7/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 5/7/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Green Building Final | 5/7/2025 | Approved | SALVADOR MARTINEZ |
| HVAC-Final | 5/7/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Final | 5/7/2025 | Approved | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 5/7/2025 | SGSOV Not Required | SALVADOR MARTINEZ |
| Service/Power Release | 5/7/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Smoke Detectors | 5/7/2025 | Approved | SALVADOR MARTINEZ |
| ELECTRICAL-Final | 5/13/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Final | 5/13/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| HVAC-Final | 5/13/2025 | Approved | SALVADOR MARTINEZ |
| Service/Power Release | 5/13/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Final | 5/16/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Service/Power Release | 5/16/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Final | 5/23/2025 | OK to Issue CofO | SALVADOR MARTINEZ |
| Service/Power Release | 5/23/2025 | Approved | SALVADOR MARTINEZ |