7607 N HINDS AVE 91605
Certificate Information: 7607 N HINDS AVE 91605
- Application / Permit
- 24010-20000-01414
- Plan Check / Job No.
- B24VN04628
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN: PROPOSED DETACHED 1,138 SF ADU.
- Permit Issued
- Issued on 6/3/2024
- Issuing Office
- Current Status
- CofO Issued on 12/19/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/10/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/12/2024 | SERGIO MUNIZ |
| Corrections Issued | 4/13/2024 | SERGIO MUNIZ |
| Plan Check Approved | 6/1/2024 | SERGIO MUNIZ |
| Plan Check Approved | 6/3/2024 | JEROME MAGAT PALMA |
| Issued | 6/3/2024 | APPLICANT |
| CofO in Progress | 11/22/2024 | MATTHEW NELSON |
| Permit Finaled | 12/19/2024 | RUBEN SALAS |
| CofO Issued | 12/19/2024 | RUBEN SALAS |
| Permit Finaled | 12/19/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 4/17/2024 | BIAINA HARITUNIAN |
| Roof/Waste drainage to street | Cleared | 4/17/2024 | BIAINA HARITUNIAN |
| Clean Up Green Up | Cleared | 4/22/2024 | DORIAN AGUILAR |
| Eng Process Fee Ord 176,300 | Cleared | 4/22/2024 | BIAINA HARITUNIAN |
| Sewer availability | Cleared | 4/22/2024 | BIAINA HARITUNIAN |
| Hydrant and Access approval | Cleared | 5/25/2024 | RUEL COLE |
| Construction near power lines | Cleared | 5/28/2024 | WALTER RAMIREZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/20/2024 | Corrections Issued | DAVID ANDERSON |
| Footing/Foundation/Slab | 6/20/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Excavation/Setback/Form/Re-Bar | 6/26/2024 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 7/9/2024 | Partial Approval | MATTHEW NELSON |
| PLUMBING-Rough | 7/9/2024 | Partial Approval | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2024 | Partial Approval | MATTHEW NELSON |
| PLUMBING-Rough | 8/30/2024 | Approved | MATTHEW NELSON |
| ELECTRICAL-Rough | 9/10/2024 | Approved | MATTHEW NELSON |
| HVAC-Rough | 9/10/2024 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 9/12/2024 | Approved | MATTHEW NELSON |
| Green Building Rough | 9/12/2024 | Approved | MATTHEW NELSON |
| Verify Sprinkler Sign Off | 9/12/2024 | Approved | MATTHEW NELSON |
| Insulation | 9/17/2024 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 9/17/2024 | Approved | MATTHEW NELSON |
| Drywall Nailing | 9/25/2024 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 9/25/2024 | Approved | MATTHEW NELSON |
| ELECTRICAL-Final | 10/9/2024 | Corrections Issued | MATTHEW NELSON |
| ELECTRICAL-Rough | 10/11/2024 | Partial Approval | MATTHEW NELSON |
| ELECTRICAL-Final | 11/18/2024 | Corrections Issued | MATTHEW NELSON |
| Final | 11/18/2024 | Corrections Issued | MATTHEW NELSON |
| Footing/Foundation/Slab | 11/18/2024 | Approved | MATTHEW NELSON |
| Green Building Final | 11/18/2024 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 11/18/2024 | SGSOV Approved | MATTHEW NELSON |
| Service/Power Release | 11/18/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Smoke Detectors | 11/18/2024 | Corrections Issued | MATTHEW NELSON |
| ELECTRICAL-Final | 11/21/2024 | Approved | MATTHEW NELSON |
| Final | 11/21/2024 | Partial Inspection | MATTHEW NELSON |
| Smoke Detectors | 11/21/2024 | Approved | MATTHEW NELSON |
| Final | 11/22/2024 | OK to Issue CofO | MATTHEW NELSON |
| Service/Power Release | 11/22/2024 | Approved | MATTHEW NELSON |