832 1/4-1/2 W SOLANO AVE 90012

Certificate Information: 832 1/4-1/2 W SOLANO AVE 90012

Application / Permit
24010-20000-01400
Plan Check / Job No.
B24VN04571
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New irregular shaped two stories 49' x 27' 6" two ADU per GC 66323(a)(4). All work done per engineer.
Permit Issued
Issued on 2/28/2025
Issuing Office
Valley
Current Status
CofO Issued on 11/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/5/2024 APPLICANT
Assigned to Plan Check Engineer 4/18/2024 NAREG ATARIAN
Corrections Issued 4/23/2024 NAREG ATARIAN
Quality Review Completed 4/26/2024 OMID HEDAYAT
Building Plans Picked Up 5/3/2024 APPLICANT
Applicant returned to address corrections 5/24/2024 NAREG ATARIAN
Applicant returned to address corrections 7/29/2024 NAREG ATARIAN
Applicant returned to address corrections 10/18/2024 NAREG ATARIAN
Plan Check Approved 2/12/2025 NAREG ATARIAN
Issued 2/28/2025 APPLICANT
CofO in Progress 11/6/2025 ALIZAH MAYAGOITIA
No Progress 11/10/2025 CHARLES BOGHOSKHAN
CofO in Progress 11/10/2025 CHARLES BOGHOSKHAN
Permit Finaled 11/14/2025 DEROLD HAUFF
CofO Issued 11/14/2025 DEROLD HAUFF
Permit Finaled 11/14/2025 DEROLD HAUFF

Permit Application Clearance Information

Street Frontage Cleared 10/22/2024 JESSICA OPINION
Eng Process Fee Ord 176,300 Cleared 10/25/2024 JESSICA OPINION
Sewer availability Cleared 10/25/2024 JESSICA OPINION
Hydrant and Access approval Cleared 12/20/2024 PATRICK PEREZ
Roof/Waste drainage to street Cleared 2/5/2025 JUSTIN BICOL
Address approval Cleared 2/12/2025 ADRIAN SANCHEZ
GPI Written Notices Cleared 2/12/2025 LANNY MERRICK
Grading Pre-Inspection Cleared 2/12/2025 LANNY MERRICK

Contact Information

Contractor New Ways To Build; Lic. No.: 1112181-B 13429 DESMOND STREET      PACOIMA, CA 91331
Engineer Basma,, Ali J; Lic. No.: C53080 6047 TAMPA AVE   SUITE 304    TARZANA, CA 91356

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/18/2025 Partial Inspection OSVALDO PARAMO
Underground Mechanical 4/2/2025 Corrections Issued DAVID WILLIAMS
Excavation/Setback/Form/Re-Bar 4/4/2025 Corrections Issued OSVALDO PARAMO
PLUMBING-Rough 4/4/2025 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 4/21/2025 Corrections Issued ALIZAH MAYAGOITIA
Sewer 4/21/2025 Approved ALIZAH MAYAGOITIA
Excavation/Setback/Form/Re-Bar 4/22/2025 Approved ALIZAH MAYAGOITIA
Masonry Wall/Backfill 5/1/2025 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 5/5/2025 Partial Approval ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 5/28/2025 Corrections Issued ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 5/28/2025 Partial Approval ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 7/9/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Floor/Roof Diaphrgm/Shear Wall 7/9/2025 Corrections Issued ALIZAH MAYAGOITIA
Green Building Rough 7/9/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
PLUMBING-Rough 7/9/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 7/9/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 7/25/2025 Corrections Issued ALIZAH MAYAGOITIA
ELECTRICAL-Rough 7/25/2025 Approved ALIZAH MAYAGOITIA
Green Building Rough 7/25/2025 Approved ALIZAH MAYAGOITIA
HVAC-Rough 7/25/2025 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 7/25/2025 Approved ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 7/28/2025 Approved ALIZAH MAYAGOITIA
Verify Sprinkler Sign Off 7/28/2025 Approved ALIZAH MAYAGOITIA
Insulation 7/29/2025 Approved GEM DE OCAMPO
Drywall Nailing 8/4/2025 Approved ALIZAH MAYAGOITIA
Interior/Exterior Lathing 8/19/2025 Approved ALIZAH MAYAGOITIA
Final 10/21/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Footing/Foundation/Slab 10/21/2025 Approved ALIZAH MAYAGOITIA
Green Building Final 10/21/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 10/21/2025 SGSOV No Gas ALIZAH MAYAGOITIA
Service/Power Release 10/21/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Smoke Detectors 10/21/2025 Approved ALIZAH MAYAGOITIA
ELECTRICAL-Final 11/6/2025 Approved ALIZAH MAYAGOITIA
Final 11/6/2025 OK to Issue CofO ALIZAH MAYAGOITIA
Green Building Final 11/6/2025 Approved ALIZAH MAYAGOITIA
HVAC-Final 11/6/2025 Approved ALIZAH MAYAGOITIA
PLUMBING-Final 11/6/2025 Approved ALIZAH MAYAGOITIA
Service/Power Release 11/6/2025 Approved ALIZAH MAYAGOITIA