832 1/4-1/2 W SOLANO AVE 90012
Certificate Information: 832 1/4-1/2 W SOLANO AVE 90012
- Application / Permit
- 24010-20000-01400
- Plan Check / Job No.
- B24VN04571
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New irregular shaped two stories 49' x 27' 6" two ADU per GC 66323(a)(4). All work done per engineer.
- Permit Issued
- Issued on 2/28/2025
- Issuing Office
- Valley
- Current Status
- CofO Issued on 11/14/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/5/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 4/18/2024 | NAREG ATARIAN |
| Corrections Issued | 4/23/2024 | NAREG ATARIAN |
| Quality Review Completed | 4/26/2024 | OMID HEDAYAT |
| Building Plans Picked Up | 5/3/2024 | APPLICANT |
| Applicant returned to address corrections | 5/24/2024 | NAREG ATARIAN |
| Applicant returned to address corrections | 7/29/2024 | NAREG ATARIAN |
| Applicant returned to address corrections | 10/18/2024 | NAREG ATARIAN |
| Plan Check Approved | 2/12/2025 | NAREG ATARIAN |
| Issued | 2/28/2025 | APPLICANT |
| CofO in Progress | 11/6/2025 | ALIZAH MAYAGOITIA |
| No Progress | 11/10/2025 | CHARLES BOGHOSKHAN |
| CofO in Progress | 11/10/2025 | CHARLES BOGHOSKHAN |
| Permit Finaled | 11/14/2025 | DEROLD HAUFF |
| CofO Issued | 11/14/2025 | DEROLD HAUFF |
| Permit Finaled | 11/14/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Street Frontage | Cleared | 10/22/2024 | JESSICA OPINION |
| Eng Process Fee Ord 176,300 | Cleared | 10/25/2024 | JESSICA OPINION |
| Sewer availability | Cleared | 10/25/2024 | JESSICA OPINION |
| Hydrant and Access approval | Cleared | 12/20/2024 | PATRICK PEREZ |
| Roof/Waste drainage to street | Cleared | 2/5/2025 | JUSTIN BICOL |
| Address approval | Cleared | 2/12/2025 | ADRIAN SANCHEZ |
| GPI Written Notices | Cleared | 2/12/2025 | LANNY MERRICK |
| Grading Pre-Inspection | Cleared | 2/12/2025 | LANNY MERRICK |
Contact Information
| Contractor | New Ways To Build; Lic. No.: 1112181-B | 13429 DESMOND STREET PACOIMA, CA 91331 |
| Engineer | Basma,, Ali J; Lic. No.: C53080 | 6047 TAMPA AVE SUITE 304 TARZANA, CA 91356 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/18/2025 | Partial Inspection | OSVALDO PARAMO |
| Underground Mechanical | 4/2/2025 | Corrections Issued | DAVID WILLIAMS |
| Excavation/Setback/Form/Re-Bar | 4/4/2025 | Corrections Issued | OSVALDO PARAMO |
| PLUMBING-Rough | 4/4/2025 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 4/21/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Sewer | 4/21/2025 | Approved | ALIZAH MAYAGOITIA |
| Excavation/Setback/Form/Re-Bar | 4/22/2025 | Approved | ALIZAH MAYAGOITIA |
| Masonry Wall/Backfill | 5/1/2025 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 5/28/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2025 | Partial Approval | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 7/9/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 7/9/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Rough | 7/9/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 7/9/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 7/9/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 7/25/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 7/25/2025 | Approved | ALIZAH MAYAGOITIA |
| Green Building Rough | 7/25/2025 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 7/25/2025 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 7/25/2025 | Approved | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 7/28/2025 | Approved | ALIZAH MAYAGOITIA |
| Verify Sprinkler Sign Off | 7/28/2025 | Approved | ALIZAH MAYAGOITIA |
| Insulation | 7/29/2025 | Approved | GEM DE OCAMPO |
| Drywall Nailing | 8/4/2025 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 8/19/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 10/21/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 10/21/2025 | Approved | ALIZAH MAYAGOITIA |
| Green Building Final | 10/21/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 10/21/2025 | SGSOV No Gas | ALIZAH MAYAGOITIA |
| Service/Power Release | 10/21/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Smoke Detectors | 10/21/2025 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Final | 11/6/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 11/6/2025 | OK to Issue CofO | ALIZAH MAYAGOITIA |
| Green Building Final | 11/6/2025 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Final | 11/6/2025 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Final | 11/6/2025 | Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 11/6/2025 | Approved | ALIZAH MAYAGOITIA |